US Army use in NW Europe
US Army use of M7s in the European Theater was generally limited
to armored field artillery battalions. However, for the landings at Utah Beach
on D-Day, the 4th Infantry Division's "three light field artillery
battalions, the 29th, 42nd and 44th, were issued self-propelled 105mm
howitzers, M7, in lieu of the towed howitzer." The field artillery
battalions organic to US infantry divisions were organized into three
firing batteries, A, B and C each with 4 guns, for a total of 12 per
battalion, so it is thought that the 4th ID's field artillery battalions
came ashore with 12 M7s each. In addition, the 4th ID's After Action
Report states that the veteran 65th Armored Field Artillery Battalion of
the 5th Field Artillery Group was attached for the assault at Utah. All
of the SP units were to be transported in LCTs and, as with the
Commonwealth Priests and Sextons used on D-Day, they were to provide
"fire afloat" but appear to have been allotted only 15 rounds per gun
for this action. The 4th ID's 8th Infantry Regiment led the first wave
of the assault, and the current pushed its landing craft about a mile
south of the planned landing zones into an area that was not as well
defended. This enabled the troops to touch down more or less intact and
in good order. A commentator in the AAR called this "An act of
Providence." As a result, the assaulting and follow up waves were able
to move inland and make contact with elements of the 82nd and 101st
Airborne Divisions. At Utah, a more or less secure beachhead was
established before noon, permitting over 21,000 men and 1700 vehicles to
be put ashore before the end of the day. The 29th Field Artillery
Battalion claims to have been the first artillery unit to land at about
0930 hours. However, Battery B was destroyed about a mile offshore when
its LCT [LCT(5)-458] was blown up by a mine killing 39 gunners and
injuring 20 more. Despite this devastating loss, the M7s of Batteries A
and C provided fire support to the 8th Infantry Regiment as it made its
way inland across the few causeways that traversed the inundated area
behind the beachhead. The commander of the 29th Field Artillery Bn., Lt.
Col. Joel Thomason, described the unit's actions on D-Day, "During the
afternoon we moved the battalion to a position south-east of St. Mere
Eglise and some seven or eight miles from the beach. There we fired some
missions throughout the afternoon and night in support of the three
battalions of the 8th Infantry. When darkness came at about 10:30 PM, we
set up the harassing and interdiction fires on suspected enemy
locations and key road junctions." The 65th AFA Bn with 18 M7s is also
stated to have landed at 0930. Its mission was to move inland as quickly
as possible and provide support to the 101st Airborne Division. During
disembarkation, "One howitzer was put out of action by artillery fire"
and another lost a track to a mine. PFC Denver O. Sayre who served with
Battery C, 44th FA Bn wrote of his
experiences on D-Day.
Sayre reported that he landed with the 3rd Battalion, 22nd Infantry
[4th ID]. "As F.O. (Forward Observer), it was necessary to move forward
with the infantry to obtain a clear view of the enemy emplacements to
direct our artillery fire by radio commands...We were glad when we
heard that 10:30 AM on D-Day our 105 guns mounted on M-7 tanks came
ashore and at 10:38 AM they were firing on the German positions! Our
Battery C, 44th F.A. became the first field artillery to fire on
targets in France on D-Day." In any case, by last light all of the 4th
ID's artillery was in position inland prepared to support further
offensive operations or to help repel what the planners anticipated
would be the inevitable German counterattack. We could not find a
single photo or film clip that we could positively identify as showing
an M7 in the Utah Beach area on D-Day. Here we have a map from the US
Army Green Book, "Cross Channel Attack" showing the "Night Positions"
on D-Day. The artillery units are highlighted in red.
Here
we have gone back to southern England a few days before the invasion to
show photos of M7s of one of the 4th ID's Field Artillery Battalions.
For many years there has been some confusion regarding the unit and the
location of the photo of “Big Chief III” (4039530), seen at the top left
of our montage. The US National Archives has some film footage showing
M7s of B Battery of the 4th ID’s 42nd FA Bn (center inset)
loading aboard LCTs on the River Dart at Dartmouth, Devon on or about
1st June 1944. We recognized one of the M7s in the footage as
“Big Chief III”, as seen loading aboard LCT-621 in the
still at the bottom left. This confirmed the Priest's unit,
and we were also able to match “Big Chief III” to a known
Signal Corps still photo of LCT-621 (on the left of the photo at bottom
right). A close examination of the building in the right-hand
background of our original photo reveals that it was “The
Ship In Dock Inn”. A bit of searching showed
that the very same pub is still open for business, and
is located on Ridge Hill, just 50 yards from the River Dart
in Dartmouth. In fact, the Inn has a framed copy of the “Big
Chief III” photo on its walls. Further confirmation came
from the website LCT Stories,
which states the “42nd Field Artillery Battalion (force of 342 with 91
vehicles) transported to Utah Beach aboard LCT(6): 765, 620, 621, 662,
763, and British LCT 2421.” To follow up a little on the story of 4th
ID's FA Bns, in an "Immediate Report of Combat Observations" dated 15
April 1945, Brig. Gen. H.W. Blakely, Commanding General of the 4th ID
wrote," Our divisional light artillery consists of two self-propelled
battalions and one towed battalion...Originally all three battalions
were self-propelled but one was converted to towed after about three
months. I believe the self-propelled is preferrable in this theater. All
the chiefs of section want the self-propelled... We could readily use
six-gun batteries, thus adding 50% to our firepower." So, it would seem,
at least two of the 4th ID's FA Bns remained equipped with M7s up to at
least mid-April 1945, and the CG and gunners of the 4th ID thought it
would be advantageous if their organic Field Artillery Bns were
converted to the equivalent of 18-gun Armored Field Artillery Bns.
Of the 5 beaches assaulted by the Allies on D-Day, the defenses at Omaha
came closest to what Hitler envisioned for his impenetrable "Atlantic
Wall." The first assault waves landed at 0630 hours, and suffered such
heavy casualties that, for several hours, the stunned survivors were
incapable of organizing and mounting any kind of attack. The planners
had assumed that the beach defenses would be cleared quickly and had the
artillery scheduled to land at H+90 (8:00 am). The two other Armored
Field Artillery Battalions of the 5th Field Artillery Group, the 58th
and 62nd, were assigned to Omaha in support of the 116th Infantry
Regiment, 29th Infantry Division and the 16th Infantry Regiment, 1st
Infantry Division respectively. Two Field Artillery Battalions, the 7th
of the 16th IR and the 111th of the 116th IR were also assigned, but
unlike at Utah, they were not converted to M7s for the assault. Instead,
each of their 12 towed howitzers were to be transported to the beach by
DUKW amphibious trucks launched from LSTs 7 to 12 miles offshore. This
was a disastrous decision, similar to the decision to launch the DD
Shermans of the 741st Tank Battalion. As it was, all but 6 of the DUKWs
were swamped in the Force 4 sea conditions that existed on D-Day. In the
meantime, the After Action Report of the 62nd AFA Bn states that the
unit fired a total of 349 rounds from offshore as part of an obviously
unsuccessful "beach drenching" program which also involved air and naval
forces. The AAR reports that their LCTs tried to land on schedule at
H+90, "but were forced away" by intense enemy fire. An oral account by
Sgt. Jerry W. Eades of Battery B, 62nd AFA Bn mentions that his LCT was
hit by 20mm fire causing a number of casualties. Three M7s of Battery B
were finally landed 7 hours later at 1500 hours (3:00 pm), but one
struck a mine "and had to be abandoned when the tide came in." The
infantry assault had turned the tide of battle at this point, but the
beach was still far from safe, and the gunners of Battery B suffered 13
casualties from enemy artillery fire. At 3:15 a second LCT was only able
to unload two M7s before it was driven off by "heavy enemy shelling."
The two Battery A M7s were placed alongside the two from Battery B
landed earlier, "giving our infantry some artillery support from a
composite battery of four M7s." The great problem at Omaha was that
exits off the beach could not be cleared until late in the day, and all
manner of vehicles both working and wrecked were piled up on the shore.
At around 4:00 pm, the composite battery was able to move 200 yards
inland opposite St Laurent-sur-Mer. At 6:30 pm, two more M7s were
landed, but another of Battery B, which seems to have been Sgt. Eades'
M7, was "lost off shore" when it drowned in the surf. Just after dark,
there was "a low level bombing attack on the beach", but the composite
battery of now 6 M7s suffered no damage, and shortly thereafter moved to
a new position 500 yards northeast of St Laurent-sur-Mer. Finally, two
LCTs carrying 6 M7s of Battery C and 2 of Battery A were reported to
have beached at 2200 hours (10:00 pm) about 2 miles east of the
composite battery and set up a "firing position 1,000 yards northeast of
Colleville-sur-Mer, 500 yards off the beaches." Navy
Medicine has
posted this fine photo with the caption, "Normandy invasion casualty
transferred to LST [sic] for trip back to England...circa June 1944."
The tactical marking "1A 62F" can be seen on the Jeep as well as on the
M7 in the background, which also appears to have "A-2" painted on. We
take this to mean "1st Army, 62nd Armored Field Artillery Battalion" and
for the Priest, the number 2 vehicle of Battery A. The Registration
Number of the M7 with the M10 trailer is USA 4039265 indicating February
1943 acceptance. Although the caption is dated only "circa June 1944",
we can't help but think that the photo was taken on the evening of D-Day
before these M7s and Jeeps were put ashore.
The Armored Field Artillery Battalions of the 5th Field Artillery Group
were veterans of the campaigns in Tunisia and Sicily, and, as such, were
chosen to partake in the initial assault waves on D-Day. Readers might
recall that Batteries A and B of the 58th AFA Bn had supported two "end
run" amphibious landings towards the end of the campaign in Sicily in
August 1943. The D-Day experiences of the 58th AFA Bn at Omaha pretty
much mirrored those of the 62nd AFA Bn. The battalion's M7s "fired
afloat" and then the LCTs attempted to land as scheduled at mid-morning
but were "prevented from doing so by underwater obstacles and heavy
fire." By a process of elimination, we think that M7 SN 2537 shown above
on display at the museum in Port en Bessin must have been on LCT 197.
According to the "Report of Loss of Landing Craft US LCT(5) 197,
LCT(5)294, by Commander, LCT Flotilla 18", dated 10 July 1944, LCT 197
struck a mine which split her seams. For several hours the crew, with
the assistance of a repair tug, tried to keep her afloat, and "The craft
attempted three more beachings with one engine but was
unsuccessful...The craft headed seaward to transfer its load to an LST.
At 2035 [10:35 pm] all engines were out, the afterdeck on the port side
was inundated. All Army personnel had been previously removed, and at
2055 the ship was abandoned with its complete load aboard. The craft
turned over to port almost immediately and sank slowly, approximately
four miles off Omaha Beach." The late Jacques Lemonchois claims to have
salvaged the Priest 3 nautical miles offshore. The M7's dataplate is on
display inside a case at the museum. It is in near perfect condition, so
we must conclude that it is a casting made of brass, even though
towards the end of 1942, the Army had directed that the plates be made
of steel in order to conserve brass. Even more amazing, M. Lemonchois
recovered some of the personal effects of Corporal John H. Glass of
Battery C, the driver of the M7. These included an envelope with his
name, Army Serial Number and unit. Using that information, Lemonchois
was able to track down Mr. Glass who returned to Normandy in 1984 at age
65 for what was described as an "emotional ceremony" in which he
collected up his lost items including "boots, shaving soap, personal
mail and packs of cigarettes." Returning to D-Day, the souvenir history
of the 58th AFA Bn reports that "By 1800 hours [6:00 pm], the battalion
had 11 of its guns on shore and ready to fire." The 115th Infantry
Regiment of the 29th ID requested the support of "a couple" of the M7s
of Battery B in its attack on St. Laurent. An officer's report in Joseph
Balkoski's fine book, "Omaha Beach" has it that at around 9:00 pm, the
M7s "fired direct shots at the enemy-occupied houses from a couple of
hundred yards away. The Germans began flying out of the windows right
and left. We ended up capturing the buildings due to this devastating
direct fire." The 58th reported D-Day losses of 9 men killed, 17 wounded
and 10 missing. In addition, the unit had lost 5 M7s with trailers, 5
half-tracks, and 2 L-4 [Piper Cub] observation planes.
Despite heavy losses at Omaha, the Atlantic Wall had been
penetrated at all of the beaches in a single day, permitting the massive
buildup of men and materiel to proceed. While less than 100 US Army M7s
had been landed on D-Day, losses were made up as quickly as possible.
For instance, the 58th AFA Bn reported that they received 2 M7s on 8
June and 2 more on the 9th, bringing their working total up to 15. The
security of the beachheads may be illustrated by the fact that on 9
June, elements of the 2nd Armored Division began to come ashore at Omaha
Beach near Saint Laurent with minimal interference from the Germans.
This was the first of 6 US and 1 French armored divisions that were
deployed during the campaign in Normandy. On 10 June, the 14th Armored
Field Artillery Battalion landed as part of Combat Command A, 2nd AD.
The screen capture above shows one of the 14th's M7s, "Conflict"
possibly headed to CCA's "Dewaterproofing Area" near Le Bray. As
mentioned previously, we believe that the fold down panels (1) affixed
to the sides and rear of the superstructure were directed to be
installed by modification kit on all US Army M7s in the UK before D-Day.
The "side extension" (2) of the fording kit used by the US in the UK
differs from that employed by the British in that it is in one piece. In
this case, it gives the appearance of being mounted on top of the fold
down panel, but there are other instances where the fold down panel is
actually seen folded down and the side extension is installed at or
perhaps a little below the original seam (inset). The USA Number of
"Conflict" can be read as 4039455 indicating May 1943 production. This
unit was probably produced on the same day or the same week as SN 2537
at Port en Bessin, which would have been USA 4039453. However, the Port
en Bessin M7 can be seen with a series of weld beads along the bottom of
the upper hull suggesting that it was once installed with sand shield
strips similar to those used to attach the "universal" sand shields on
Shermans starting in mid 1943 production. "Conflict" does not show these
weld beads. Period photos suggest that the AFA Bns of the 2nd AD added
mine racks (3) to their M7s while in the UK. Period photos also show
that some 2nd AD M7s were retrofitted with what appears to be a standard
pioneer tool rack (4) as used on many US WWII softskins. This is seen
mounted under the pulpit as here. On 13 June, CCA was given its first
assignment, which was to secure the bridgehead at Isigny and "clean out
the Germans to the south thereof." However, the mission was changed
abruptly based on an Ultra decrypt indicating an impending German
counterattack against elements of the 101st Airborne Division at
Carentan. At 1400 hours (2:00 pm) the tanks and armored infantry of CCA
with support from the 14th AFA Bn arrived on the scene and during the
next 24 hours, the US forces drove the enemy back "with heavy losses."
The 101st Airborne dubbed this action "The Battle of Bloody Gulch" and
it basically secured the "seam" between Utah and Omaha Beaches. The
other AFA Bns of the 2nd AD, the 78th and 92nd, landed at Omaha in the
vicinity of Colleville-sur-Mer on 11 June. The AAR of the 78th AFA Bn
provides an idea of the vehicles the unit had at that time:
Elements of the untried 3rd Armored Division began landing at Omaha
Beach on 24 June 1944. The 2nd and 3rd ADs were the only US armored
divisions in the ETO that retained the "heavy" table of organization and
equipment (T/O&E). In a nutshell, the heavy T/O&E authorized
232 Medium tanks versus 168 authorized to the "light" armored divisions,
the 4th through 14th, plus the 16th and 20th. Both the heavy and light
armored divisions were authorized 3 Armored Field Artillery Battalions,
each with a total of 18 M7s. The AAR of the 67th AFA Bn notes that the
unit supported Task Force Y during the 3rd AD's first major engagement,
an assault on Villiers Fossard starting on 29 June. There is some
evidence that the 67th was equipped with at least two tanks in the
Headquarters and Headquarters Battery for use by the unit's forward
observers. Lt. Irving Rudnick, one of the Battalion FOs stated, "Lt.
O'Brien and Lt. Langsdorf joined me at 2230 hours in a medium tank. Lt.
O'Brien stayed with me and Lt. Langsdorf took my light tank back to the
Battalion CP." These tanks may have been filmed landing from an LST on
24 June as shown in the small screen captures on the right. Eventually,
the HQ & HQ Battery of an AFA BN was authorized "3 medium tanks",
but it would seem that this authorization was still in transition in mid
1944. We couldn't find a photo of a 3rd AD M7 in action in June or
July, so instead, the main photo shows an M7 identified in the caption
as "Btry C, 39th Armd. F.A. Bn., 3rd Armd. Div... [blasting] away with
another round at German positions near St. Pois, France. 3 Aug. 44." The
caption writer appears to have misidentified the unit. It seems likely
he meant 391st, one of the 3rd AD's organic AFA Bns. Judging by the M3
type drive sprocket, this is likely a 1942 production M7 that had been
modified by the addition of the "folding armor plates" which seems to
have been the case with almost all of the US Army Priests in Normandy. A
pair of track holders (1) can be seen to have been retrofitted to the
side of the vehicle, and the crew appears to have improvised their own
fittings (2) and mounting points for a camouflage net. A close
examination of the print reveals what we think is the name "Chicago"
half hidden at the bottom of the track holders. The middle and rear M4
type bogies have been retrofitted with bars (3), no doubt to offer
additional climbing footholds for the crew. The item poking out from the
differential housing is part of a hedgerow cutter device (4). These
were added to US tanks and other AFVs prior to the start of Operation
Cobra on 25 July 1944. Cobra proved to be the decisive blow that ended
the stalemate in Normandy and broke the front wide open. The AAR of the
391st records that on 4 August, "friendly 57mm fire penetrated the left
side of the FO 2 tank turrent [sic]", wounding Sgt. Theodore D. Root of
Hq Battery. So, we have a little more evidence that the AFA Bns were
equipped with a few tanks.
The 4th Armored Division began landing at Utah Beach in mid-July 1944
and played a prominent role in the Operation Cobra breakout. The
division's organic Armored Field Artillery Battalions were
the 22nd, 66th and 94th. In "Patton's Vanguard", author Don M. Fox
states that "On July 29, the Fourth slashed its way south from
Coutances in relentless fashion. The drive was so fast and furious that
the two artillery battalions assigned to CCB, the 94th and 66th, had to
play leapfrog in order to provide artillery support and keep the
vanguard within range. One Battalion would fulfill fire missions while
the other moved south; then the battalion that had moved closer to the
fighting would stop and take over fire missions, while the trailing
battalion pulled up stakes and drove to a position still closer to the
front". After the breakout at Avranches, the 4th AD encircled Rennes
and cut off the Brittany Peninsula, reaching Vannes and the Lorient
area on 7 August. On 13 August, the division started its race east
through Orléans and Troyes, then crossed the Moselle River,
encircled Nancy and captured Lunéville on 16 September. At
that point, the 5th German Panzerarmee was ordered to retake
Lunéville, but the inexperienced 111th and 113th Panzer Brigades
were virtually destroyed by the 4th AD during the
much-studied Battle of Arracourt 18-29 September
1944. Although it is not mentioned in the 66th AFA Bn After Action
Report, several sources describe an incident that happened on 19
September at the Headquarters of Combat Command A. "The HQ [at
Arracourt] was under attack by more Panthers. The M7s of the 66th
AFAB were using direct fire in an attempt to hold them at bay. Firing
from a distance of only 650 yards, they held off the tanks until B/37
[B Co/37th Tank Battalion] arrived at 1100 hours...CCA’s
headquarters was saved." The snapshots above were kindly provided by the son of
T-5 George Hemcher. In the photo on the left, George is shown towards
the end of the war posing in front of his M7 of Battery B, 66th
AFA Bn. The photo on the right was taken in Les Clérimois near
Troyes, France in August 1944, and shows George's friend and longtime
section commander, Sgt. Peter Belpulsi, holding a 105mm
round. Of interest is that Peter's brother, Ernest, was the
commander [Chief of Section] of another M7 in Battery B. George Hemcher Jr states that his father "was
originally the Armorer. As the crew changed, he also changed
duties. He wrote a letter saying that he also served with the 51st and
53rd AIB's. As well as 35th and 37th TB. A seven-man crew wasn't always
necessary. So, he volunteered as other units needed replacements.
But the original #1 man was wounded and never returned. Henry Haug
replaced him. At some point in 1945 my father replaced Haug as #1 then
became the M-7 commander after Haug was gone. Haug and Belpulsi were
friends of mine and verified this. They all said that after three
years of training we were trained to handle any position on the M-7."
US Lend Lease
documents have it that the French received a significant number of M7
Priests - 283. Most or all of them appear to have been deployed with
their three armored divisions. For instance, the French 2nd Armored
Division or 2ème Division Blindée, which landed at Utah Beach at the
beginning of August as part of the US Third Army, had three artillery
"groups" that were similar in structure to the US Armored Field
Artillery Battalion. The 1er Groupe, 40ème Régiment d'Artillerie Nord
Africain was part of the Groupement Tactique Langlade. The 11ème Groupe
Blindé, 64ème Régiment d'Artillerie de Division Blindée belonged to the
Groupement Tactique Warabiot and the 1er Groupe, 3ème Régiment
d'Artillerie Coloniale was part of the Groupement Tactique Dio. Each
artillery group was composed of 3 batteries, each one having 2 sections
of 3 guns, for a total of 18 M7s. The "Journals de Marche et Opérations"
(French equivalent of "After Action Reports") of these artillery groups
mention that most of the M7s were issued to the units while in Morocco
between mid-January and early February 1944. Despite that, many of the
2ème DB M7s seen in period photos are ALCO 1942 production, that is,
they are noted with shallow pulpits and/or M3 type drive sprockets.
Also, none of the 2ème DB M7s appear to have been retrofitted with the
modification which provided for armor protection for the exposed 105mm
rounds. This mod seems to have been mandated for US M7s in the UK before
D-Day. Perhaps there weren't enough kits to provide for the 2ème DB?
The photo shows a scene from the "finest hour" of the 2ème Division
Blindée - the Liberation of Paris. The division's M7s are well
represented in the photos and film footage taken on that historic day,
26 August 1944. "Porte d'Orléans" of the 32ème Batterie, 11/64e RADB stands in front of
one of the iconic symbols of Paris, Notre Dame Cathedral. The crew has
removed all but the front sections, but this Priest appears to have been
shipped with the type of sand shields that were original equipment on
most Grants.
So
far, we have discussed 1942 and 1943 production ALCO M7s. By the end of
August 1943, ALCO had produced 2814 such M7s. A total of 1115 had been
or were in the process of being distributed as Lend Lease including 832
to the British and 283 to the French, leaving 1699 available to the US.
Apparently, this was insufficient to meet US requirements and ALCO was
contracted to build an additional 500 units with production restarting 6
months later in March 1944. The 1942/43 M7s had been based on the
chassis of the M3 Medium, while the 1944 models were based on the M4. We
take this to mean in part that the old-fashioned practice of assembling
the lower hull by riveting would be discontinued and replaced by the
standard welded assembly. However, we have noticed a few exceptions
which we shall discuss going forward. The M7 Technical Manual dated 15
August 1944 notes some of the differences between the early and late
models. The TM has it that on the 1942/43 models "Final drive made in
three pieces." That was not really the case, as there are numerous
photos of early Priests with the original one-piece differential housing
Part Number E4186. The TM states that the late models were made with
unspecified one-piece final drives, but the Ordnance Dept. had mandated
the use the "final" type of one-piece diff, Part Number E8543, in all
domestic Sherman production by September 1943, and period photos suggest
that these were factory installed on all M7s and M7B1s produced in 1944
and 1945. The Ordnance Dept. had also directed that "disc type idler
wheels" (1) would replace the welded, spoked type by September 1943, and
the discs have been noted on 1944/45 Priests. The TM does not mention
bogies, but again it is obvious that 1944/45 production Priests were
built exclusively with M4 bogies, with most having the final "upturned"
return roller arms (2). The TM states that the early models were not
produced with the "folding armor plates" (3) or sand shields (4) but the
late models were. An instant recognition feature of a 1944/45 Priest is
the "low" position of the headlights (5), which may have been brought
about by driver complaints from the field regarding the original high
mounts. Grouser stowage was reconfigured, and a fourth grouser box (6)
was added. Stencils (arrows) seen in a few photos show that the small
boxes on the pulpit side held "3 GROUSERS" while the larger boxes each
held 10. The boxes are seen with two holes on each side for the
retaining bars. The "top bows" (7) and "side bows" (8)" that made up the
support frame of the canvas cover were factory installed on the 1944/45
Priests. Shortly after 1944 production began, a pair of cast cable
clamps (9 and inset) and some other fittings were added to the right
side of the M7 hold the tow cable in a new position as seen here.
Serial Number 3167 would have been
accepted in August 1944. It was on display at the Ordnance Museum at
APG for many years and strikes us as the surviving example of a 1944
ALCO M7 that is closest to "as built." For instance, it would appear
that the sand shields were never removed. On the other hand, we suspect
that its original tracks and road wheels may have been switched out at
some point during the course of its service. The Serial or Registration
Number of the M7 shown in the previous caption is not known, but we
would guess that it might have been made a little earlier than SN 3167
since it lacks the cable clamp (circled) on the differential housing
which became a standard fitting on 1944/45 Priests. Without the
retaining bars, the configuration of the pairs of holes on the grouser
boxes is easy to see. These would have made the retaining bars height
adjustable, with the inboard upper holes presumably included to
accommodate items other than grousers, such as spare tracks. We only
know of 9 surviving 1944 ALCO M7s, and all of them have grouser boxes
with two pairs of holes. Frankly we are somewhat surprised at
the consistency of that. One would think that some of those boxes
would have rusted out over the years and been replaced by something
homemade and not necessarily an exact copy. An examination of 1944 M7s
in period photos also consistently shows the "two pairs of holes"
grouser boxes. Based on counting heads, we would conclude that these were exclusive
to 1944 production ALCO M7s; that is, we don't see any evidence that
they were factory installed on M7B1s or Federal Machine and Welder M7s,
and hence we believe that these grousers boxes
with two pairs of holes are an ID feature that can be used
to differentiate between 1944 Production M7s & M7B1s from the front.
Here
we have a rear view of USA 4039918, a June 1944 M7 that was the subject
of an Inspection Control Test at APG. "Blanket baskets" (1) were
mounted on top of the stowage bins, forcing the rearrangement of the
tool stowage yet again with the engine crank and track wrench moved to
the upper rear hull plate. The bore brush staffs (2) were relocated from
the interior firewall to the engine deck, although the 1944 Tech Manual
does not seem to have been updated to reflect this change but gives the
former location. The "fuel tank compartment ventilating grilles" and
"grille protecting covers" are no longer present on the engine deck.
Ventilation was handled by the addition of some louvers (3) on the
fronts and outer sides of the rear stowage bins which permitted air to
enter the engine compartment through pipes inside the bins. The 1944
production M7s were equipped with the Barber-Colman type exhaust
deflectors (4) which had been mandated to be installed in M4/M4A1
Sherman production in late 1943/early 1944. Note that the upper rear
hull plate of the new model was no longer "notched" but went straight
across. While earlier production M7s had only one rear towing lug per
side, the later model had two lugs per side (5) in order to work with
the "Quick Release" towing shackle with handle (6). "Legacy" items that
carried over from earlier M7 production were the M3 type of hinges (7),
which have a sideways "T" shape. The use of the long trailer towing
pintle (8) also appears to have carried over to ALCO's entire 1944 M7
production. This example "still" has the straight return roller arms
(9), but we would guess that supplies of these were nearing exhaustion
by June 1944 and were in the process of being replaced by the upturned
type as seen in the previous photo. For future reference, take note of
items 10 and 11 in the photo.
The
photo on the left provides a more complete view of the louvers on the
stowage bins of the 1944 model M7, including the single louver (1)
running across the front of the box. This is on SN 3167, the ex-APG M7
which is reported to have been placed in storage at Ft Lee, Virginia.
There aren't enough available units to count heads, and the 1944 Tech
Manual does not mention the interior of the bins, so we will just
describe what we have seen. Pierre-Olivier was able to photograph the
bins on three surviving 1944/45 M7s that were missing their lids, such
as SN 3248 (September 1944) on the right. On this example, the interior
of the right-side bin is compartmentalized and there are more louvers
(2) on the divider to permit air to flow from the front of the box to
the intake pipe (3) at the rear. The left-side bin is not
compartmentalized on SN 3248 as well as on SN 3063, but we have seen one
LS bin that is compartmentalized (inset). On that one, a lid can be
seen attached to the pipe by a chain. This was likely intended to close
off the pipe in extreme cold weather situations.
The photo in the upper left shows the configuration of the M3
Medium type armored fuel filler cover with the "short and straight"
locking pin. These featured middle hinge sections with "tabs" that were
attached to the hull by a pair of rivets. This was photographed on a
diesel engine M3A5 Lee, perhaps the only surviving example that still
has one of the "short and straight" pins installed. Note the "GASOLINE"
label screwed on to the cover. As best we can tell such labels were not
factory installed on any ALCO M7s. On 1942/43 M7s, the covers used the
"short and straight" locking pins, but the tabs were welded to the hull
as seen in the upper right on SN 179 a July 1942 M7 on display in Italy.
The lower left photo shows a July 1944 model M7, SN 3099 that has
retained the welded-on tabs, but has replaced the "short and straight"
locking pin with an "angled" locking pin. There are not many such
surviving Priests, but we believe that this was the typical
configuration of 1944 production M7s. The photo on the bottom right
shows an M7B1, SN unknown, on display in Helena, Montana. In this case,
the middle hinge barrel has no tab, but is welded directly to the hull,
plus there is the "angled" locking pin. This is the configuration seen
on the vast majority of Shermans. We believe that it was also the
configuration used on M7B1s along with the Federal Machine and Welder
M7s, all of which were produced in 1945.
The photo shows the engine deck configuration typical of a 1944
production M7. This is SN 3099 (July 1944) on display at the 1st
Cavalry Division Museum at Fort Cavazos (formerly Ft. Hood) Texas. M7s
were built with four main fuel tanks, and on the 1942/43 models, each
had its own filler point. M7s produced in 1944 and 1945 were similar to
Second Generation M4 and M4A1 Shermans in that they were plumbed in
such a way that only a single filler point (1) was required for the two
fuel tanks located on either side of the hull. Thus, the filler points
located on each side of the air intake on the earlier models were
eliminated. Also similar to Second Gen radial Shermans, the 1944 M7
added a new armored filler cover (2) to the rear engine deck plate.
This was for the "engine oil tank" and included a "bayonet gage located
under fill cap." When this was added to Shermans, a small, pressed
metal tag reading "LUBRICATING OIL" was placed next to filler
cover. We can't say we have seen that on the few surviving
examples. As built, there would have been only one angled locking
pin (3) not two as on this example. While M7s did not suffer high
casualties in combat, they were subjected to counter battery fire, and
one might have expected that the 1944 M7s would have introduced an
armored cover over the air intake such as was standard from the
start on M4 and M4A1 Shermans. That was not the case. As seen here
the intake remained unprotected except for a wire mesh screen. However,
per the Tech Manual, under the screen there was an "air inlet shutter
(4) installed in the engine compartment front top plate [that] controls
the amount of air drawn into the engine compartment. The air inlet
shutter control (5) may be placed in "OPEN," "CLOSED," or three
intermediate positions." For a little reminder, the inset shows the
typical engine deck configuration of most 1942/43 production M7s.
The M7 Technical Manual notes that the "Early Models" had
"Instrument panel mounted on front hull wall" as shown on the left. This
was the same panel as used on the M3 Medium and is sometimes referred
to as the "tractor" type. The "Late Models" had "Instrument panel
mounted on left front sponson" as seen in the upper right. The TM
specifically mentions that the clock on the instrument panel
(highlighted in red) of early or 1942/43 M7s was removed from the late
models (1944/45), probably because dashboard clocks were notoriously
unreliable at the time. The Tech Manual images running across the bottom
show the various gauges, switches and buttons of the "tractor" and
later "tombstone" type instrument panels.
Permit
us a brief return to France in the Summer of 1944. The first units of
the 6th Armored Division began landing at Utah Beach on 18 July 1944.
After a period of organization, the division had its first combat on 29
July, a few days after the Cobra breakthrough, when it forced a crossing
of the Sienne River at Pont de La Roche. The Third Army to which the
6th AD was attached, became operational on 1 August. Its original
mission was "to liberate Brittany and turn it into a logistical base for
the Allied armies." The port of Cherbourg had been captured on 29 June,
but the Germans had so thoroughly wrecked the harbor that it would be
of limited use for quite some time. On 1 August, the 6th AD was ordered
to drive west to capture the major port of Brest on the Atlantic coast
of Brittany. In a week, the division moved over 200 miles through enemy
territory, hoping that it might take the port intact by coup de main.
However, when the leading elements of the 6th AD arrived at the outer
defenses of the elaborate fortress complex of Brest on 7 August, their
only real hope of a painless conquest was the bluff of a surrender
ultimatum to what was assumed to be a demoralized enemy. The Germans
refused, and, ultimately, the city was not taken until 19 September 1944
after a long and costly siege, and, of course, the port facilities were
systematically destroyed. However, by that time, the great success of
the Allied breakout had diminished the importance of the port because it
was much too far behind the front lines. The photo above shows an M7
named "COUP DE MAIN" of the 6th AD's 212th AFA Bn. The Registration
Number can be read as "USA 4039749", indicating March 1944 production.
It is thought that the photo was taken sometime around 12 August in a
hedgerow field near Plabennec, a few miles northeast of Brest. On that
day, the 6th AD was ordered to head southeast to Lorient, leaving behind
4000 men of Combat Command A, including the 212 AFA Bn, as a screening
force awaiting the arrival of the three Infantry Divisions that were
tasked with taking the city. In any case, this is the earliest combat
appearance of a 1944 M7 we can document at present. Note the louvered
stowage bin with blanket basket and the "low" position of the head
lights. However, this unit does not have the cast cable clamps welded to
the right side. We can only guess that some of the earliest 1944 M7s
were not built with these, possibly because it was originally intended
that the tow cable would continue to be coiled on the engine deck. In
addition, "COUP DE MAIN" appears to have a riveted lower hull, even
though the practice of riveting should have been discontinued by 1944.
The side of the Priest can be seen with numerous messages chalked on by
citizens celebrating their liberation. For instance, "Vive Roosevelt" is
written just above the "749" of the RN. We suspect that the two Priests
in the background with sand shields are also 1944 M7s while the one on
the far right with the notched upper rear hull plate is likely a 1943
model. The 1946 souvenir "Combat
History of the 6th Armored Division" includes an interesting statistic
regarding the 6th AD's Priests: of the 54 M7s that landed on Utah Beach
in July 1944, 37 of them (69%) were still in service on VE-Day. This can
be compared to only 7 Medium Tanks (4%) out of 168. Photo courtesy of
Bruce Frederick via Jean-Paul Cornec.
Speaking
of riveted lower hulls, here we have photos of the only known (to us)
surviving example of a 1944 ALCO M7 with a riveted lower hull. This is
SN 2843 indicating that it was accepted in March 1944. It would have
been assigned USA 4039759, so built 10 units after 4039749, "COUP DE
MAIN" shown in the previous caption. We might assume that the Ordnance
Inspector at ALCO let a few excess riveted lower hulls pass at first.
The upper hull also appears to have been built originally in the 1942/43
configuration and "recycled" for the 1944 model by filling in the
various holes (1) on the engine deck. A close inspection also shows that
the upper rear hull plate notch (2) has had a piece welded in to
conform with the current design. We wouldn't be surprised if the early
type E8543 differential housing with the cast in steps (3) was original
to SN 2843. These photos were taken at Ft. Sill, Oklahoma over 20 years
ago when SN 2843 was displayed outside. Courtesy of Keith Ross.
The
U.S. Army Field Artillery Museum opened in June 2009 at Ft. Sill, and
SN 2843 is now displayed inside in a diorama depicting an M7 of the
420th AFA BN, 10th AD during the siege of Bastogne. The name of the
101st Airborne Division will be forever associated with Bastogne, but
Combat Command B of the 10th AD played a key role in the city's defense,
particularly in the hours before the 101st arrived. As the city became
completely surrounded, part of the western perimeter was manned by a
motley group of infantry stragglers, tanks, tank destroyers and the M7s
of the 420th AFA Bn. "Team Browne" named for the commander of the 420th,
Lt. Col. Barry Browne, repelled a number of attacks in the area of
Senonchamps, and protected the artillery assets within the perimeter.
Col. Browne died of a shrapnel wound on Christmas day and was
posthumously awarded the Distinguished Service Cross. The siege of
Bastogne was lifted on the afternoon of 26 December. Pierre-Olivier
visited the Artillery Museum in 2023. We mentioned that "COUP DE MAIN"
did not have the cast cable clamps welded to the right side. Plus, we
know of at least 5 other period photos of 1944 ALCOs without the clamps,
including a pair with readable Registration Numbers - 4039738 (March
1944) and 4039822 (April). P-O was able to get a photo showing that they
are not present on SN 2843 as well. By their ubiquity on 1944 and 1945
Priests we must conclude that the clamps were standard fittings, but our
little counting heads exercise suggests that they were left off at
least some of the ALCO M7s produced in March and April.
Something of a curiosity has been observed on four of the surviving 1944
production ALCO M7s. The lower hulls are welded together but the side
plates are also seen with what we had been referring to as "melted
rivets" for want of a better term. The photo at the upper right shows
these on SN 3248 on display at the Russell Museum in Illinois. At first
glance, we had thought that they might have been assembled riveted lower
hulls left over from 1942/43 production, and that they had been
reworked by welding so that they could be recycled for use in the 1944
program. Not being conversant in metal working, we had assumed that the
welding process had "melted" the rivets. However, a closer look at one
example showed that the lower hull's belly plate and rear plate had not
been pre-drilled for riveting so that the hull could not have been an
original riveted assembly. In addition, the "melted rivets" that could
be seen on the inside are not actually holding anything together with
angle brackets; they are simply plugs that are almost perfectly round
blobs about the same size as rivets. We have not come across any ALCO
documentation about this but have had a number of opinions, with the
most likely coming from author Kurt Laughlin who thinks that the side
plates were existing drilled plates on which the rivet holes were filled
with weld metal so that they could be used to complete a welded hull
assembly for the 1944 program. To try to explain further, the photo on
the lower left shows an M3 Lee and illustrates how the rivets at the top
of the lower hull were driven through an "L" bracket which was in turn
attached to the sponson plate. The photo on the lower right is of the M7
in Seneca, Kansas and shows how the "plugs" are not driven through a
bracket and also shows that the top of the lower hull is welded to the
sponson plate. Sorry to say, only the first 3 digits of the Seneca's Serial
Number can be read from the left rear tow lug - 325_. Even so, this
would indicate September 1944 production. We do know that the entire SN
of the M7 at the Russell Museum is 3248 indicating September 1944
acceptance or made about 70 units before the end of M7 production at
ALCO. The upper hulls of both the Seneca and SN 3248 show signs of
having been recycled from the earlier program as well, in that the
notches in the upper rear hull plates are filled in, as are the holes
for the fuel tank compartment ventilating grilles, etc. on the engine
decks. It strikes us as odd that pieces from the earlier program were
being recycled a month before the 1944 program came to an end.
We were informed that the filled in
notch on the upper rear hull plate of SN 2843 in the old Ft. Sill photo
is not very visible. So, here it is on SN 3248 in Zion, Illinois in the
upper left and SN 325X in Seneca, Kansas in the upper right. This was
a simple expedient to adapt the old, notched parts, since the upper
rear hull was designed to go straight across on 1944 and later
production M7s as well as M4 and M4A1 Shermans. The lower photos show
how the rectangular fuel tank compartment ventilating grille holes were
blanked off to conform with the 1944 M7 engine deck configuration.
Returning again to France in the Summer of 1944, the 5th Armored
Division landed at Utah Beach starting on 24 July 1944 and began combat
operations as part of the newly activated Third US Army on 2 August just
as Operation Cobra broke the German lines in the Cotentin Peninsula.
The division drove south "through Coutances, Avranches, and Vitré, and
across the Mayenne River to seize the city of Le Mans, 8 August. Turning
north, the Division forged the steel ring around the Germans in
Normandy by advancing to the edge of the city of Argentan on 12 August- 8
days before the Argentan-Falaise Gap was closed. Turning Argentan over
to the 90th Infantry Division, the 5th Armored advanced 80 miles to
capture the Eure River Line at Dreux on 16 August." Hollywood director
George Stevens served with the Signal Corps during WW II, and his
"SPECOU" [Special Coverage Unit] shot some raw color footage of the 5th
AD's 47th Armored Field Artillery Battalion as it moved through a French
city cheered on by liberated citizens. With some effort, Pierre-Olivier
"found" the town using Google Street View. The scene was shot on the
Rue Saint-Martin in Dreux, not long after the city was taken by CCB, 5th
AD, so 16 or 17 August 1944. What caught our eye was a Priest named
"America" "A-6" that has features identifying it as an M7B1. As it
passes, the Registration Number can be read as USA 4015234- with just
the final number unclear. In any case, even without the last number, the
RN indicates an M7B1 produced in May 1944, so this unit was shipped
overseas quickly and was in service with a combat unit about 2 1/2
months after it rolled off the line at Pressed Steel Car, a fairly
impressive feat. In the front view, the "low" position of the head
lights (1) and the sharp-nosed E8543 differential housing (2) are
indications of a 1944 production M7 or M7B1. In the rear view, the angle
and the extended down shape of the upper rear hull plate (3) is typical
of Shermans and Priests with Ford engines. Note that the stowage bin
(4) is smooth with no louvers, since the Ford V8 engine did not generate
the heat of the Continental Radial and therefore did not require the
additional ventilation. We would mention that another Priest rolls by in
the Stevens footage "B-6" and it can be seen as a 1943 production M7,
so it would seem that the 47th AFA Bn might have been equipped with both
M7s and M7B1s. Some other SC footage was brought to our
attention which shows another M7B1 named "All American" "A-10" with
tactical markings denoting the 71st AFA Bn, 5th AD. This film is undated
but from the context of the other footage in the segment, it appears to
have been taken between the 14th and 16th of August as the 5th AD
advanced from Argentan to Dreux. It seems safe to assume that these
Priests landed with the 5th AD in late July and likely took part in
their battalions' first fire missions in early August.
The 500 HP Ford V8 engine was the US Army's preferred tank power plant
and consequently an order was placed for Priests powered by the Ford
engine. These were given the nomenclature "M7B1." According to a
"Development History" of the type, "At the request of Army Service
Forces, 70% of all 105-mm Howitzer Motor Carriages built in 1944 were
equipped with Ford G.A.A. V-8 gasoline engines." Going by the official
production figures, this was not quite the case. The original M7B1
Production Order T-10154 was for 628 units, but this appears to have
been supplemented by an additional order for 494 units which was
eventually cut back to 198. Thus, the total number of M7B1s manufactured
amounted to 826 units, with 664 produced in 1944. Meanwhile, 500 M7s
were manufactured in 1944. In any case, Pressed Steel Car began M7B1
production in March 1944, the same month that ALCO restarted M7
production. Above provides a right front view of a May 1944 M7B1, Serial
Number 3896, USA 40152359 as photographed at the General Motors Proving
Ground in September 1944. As best we can tell from the limited amount
of historical reference, the appearance of this unit is typical of the
M7B1s produced by PSC from start to finish. The "Development History"
describes the M7B1 as "based on the welded chassis of the Medium Tank
M4A3 constructed of soft plate to give minimum ballistic effectiveness
of one-half inch rolled homogenous armor." We interpret this to mean
that the plates of the lower hull assembly were dimensionally the same
as the M4A3, that is 1 1/2 inches thick on the sides and rear, but were
made of soft plate, not armor. No explanation is offered for the use of
soft plate, but we assume it was to reduce weight. The upper hull was
assembled using 1/2-inch armor plate, except of course for the
differential housing which was the same E8543 casting as used on Second
Generation Shermans.
Here we have a side-by-side
comparison of the grouser boxes seen on the M7B1 on the left and the
1944 ALCO M7 on the right. One would think that Pressed Steel Car and
ALCO would have used the same grouser boxes in the interest of
standardization, but to our eyes, the M7 boxes appear to be an inch or
so higher. They also include the additional holes. We hope to get
some measurements in the future and will report back.
Here
we have a rear view of USA 40152589 (September 1944) which was used in
Endurance Tests by the Armored Board at Ft. Knox in late 1944. As
mentioned earlier, the rear stowage boxes were not louvered for air
intake as on the 1944 M7, and this provides a decent recognition feature when looking at certain period photos. The
sides at the rear were not "jogged in" as on the M7 but went straight
back. Thus, there was room for the taillights (1) to be placed on the
upper sponsons as seen here. The upper rear hull plate was angled as
opposed to the vertical orientation on the M7. It also extended down
further to provide a measure of protection to the engine's radiators.
The M7B1 used the same sheet metal type of exhaust deflector (2) as the
M4A3 Sherman. It is thought that the M7B1 was factory installed from
start to finish with the same "short" trailer towing pintle (3) as used on Second Generation Shermans.
As mentioned earlier, it is our impression that all of the ALCO M7s were
built with the original "long" trailer towing pintles factory
installed. Regarding the M7B1, we don't have a lot of reference but
think that they were factory installed with the "short" pintle as seen
in the Tech Manual illustration in the upper left, and in a close up
(sans pintle) of an APG photo of M7B1 SN 4366 (December 1944) in the
upper right. The original "long" pintle could get bent up in service
causing a misalignment of the rear engine mount and/or making it
impossible to open the engine access doors. As a result, the pintle was
shortened and the redesigned item was ordered to be factory installed as
standard equipment on Second Generation Shermans. We have not come
across any requirement regarding the M7B1s but think that this was used
on
them as well. Some doubt is cast because of the 90 or so
surviving M7B1/B2s, not many have what we think was the factory
installation of the short pintle. Several are installed with the "long"
pintle as seen in the lower left on the M7B2 (SN Unknown) at Camp
Mabry, Texas. Others are noted with a mounting configuration for the
"short" pintle that is "two tiered" as seen (without pintle) on the
M7B1 at the Pivka Museum in Slovenia in the photo on the lower right.
We can only guess that when these units were rebuilt in the post war
years and/or when some were converted to M7B2s, these changes were made. Furthermore, counting heads
suggests that M7B1 production at PSC started with double rear towing
lugs, but was changed to single lugs in January 1945, since the new
T-shaped towing shackles (arrows) only required one lug. A very limited
counting heads suggests that only about the last 100 M7B1s were produced
with the singles.
Modification
Work Order G1-W22 was released in April 1945 and applied to all
Shermans or variants with Ford engines, including the M7B1. The purpose
was to, "Eliminate possibility of ground bursts damaging the radiators
by replacing sheet metal exhaust deflector with one made of armor plate
strips." As usual with mods, "This modification should be applied to all
of the subject vehicles in or destined to be shipped to theaters of
operation that are not so equipped." Furthermore, no vehicle was to be
shipped overseas without this mod after 15 May 1945. Due to its late
date of issue, we doubt if it was ever factory installed on any M7B1s
and can't say that we have seen it in any M7B1 WW II overseas photos.
Quite a few surviving M7B1s and B2s are equipped with the armor plate
exhaust deflector modification, such as the M7B1 on display in Hamilton,
Montana. This Priest has "USA 40172501" painted on, and we suspect that
it may be the original Registration Number. If so, it indicates January
1945 production at PSC. The drawing on the right provides measurements
for the positioning of the pioneer tools. Basically, the addition of the
deflector's hinges forced the relocation of the crowbar 3 1/2 inches up
from the bottom edge of the upper rear hull plate. We consider the
diagram to represent the "official" arrangement of the tools but would
note that a number of surviving M7B1s and M7B2s are seen with the shovel
positioned further to the right. The Hamilton M7B1 shows the alternate
location of the shovel fittings.
This overhead view from the M7B1 Technical Manual shows the vehicle's
engine deck layout including the left and right fuel filler covers plus
the radiator filler cover in the center. We believe that the engine
compartment doors were the same as used on M4A3 Shermans although we
admit that we have not had the opportunity to closely examine or measure
any so far. The TM illustration seems to give a false impression of the
appearance of the grating of the doors, judging by surviving examples.
However, there is another illustration (inset) on page 313 of the TM
which shows what we think was the actual look of the grating on the
doors, that is, identical to M4A3 doors. Note that the rear "Engine
Compartment Cover" (1) is a one-piece plate. As with the M4A3s, in order
to make it easier for crews to remove, this appears to have been
changed to a two section cover at some point not long after the start of
production. The fittings (circled) held the bore brush staffs although
the TM gives their location as "In bracket on rear fighting compartment
wall." (This appears to have been copied verbatim from the M7 TM.) In
any case, in order to open the right engine deck door, it would have
been necessary the remove the staffs.
This Signal Corps photo is dated 13 August 1944 and shows the crew
servicing their "105-mm self-propelled howitzer" during "the Siege of
Brest." The caption identifies the men from left to right as Pvt. John
Siirila, Cpl. Robert Silverman, Pvt. Ed DeSimone, Pvt. Bert Lavare, and
Sgt. William Entrekin. The unit is identified as "83rd Field Artillery
Battalion, 6th Armored Division." According to the unit AAR, the 83rd
Armored Field Artillery Battalion was part of the 5th Field Artillery
Group, and not one of the 6th AD's organic AFA Bns. The battalion landed
at Utah Beach on 25 July and on 1 August was attached to CCA of the 6th
Armored Division. A CCA map dated 12 August shows that the 83rd was
positioned near Plabennec a few miles northeast of Brest and was
providing artillery support in conjunction with the previously mentioned
212th AFA Bn of the 6th AD. The photo obviously shows a 1944 production
Priest, but from this angle, it is practically impossible to determine
if it is an M7 or an M7B1. The grouser boxes can be seen with only one
hole for each of the retaining bars, which we have interpolated would
make this an M7B1. In addition, this particular image is unusual since
it was possible to zoom in on the armored fuel filler cover (inset),
where it appears that the center hinge barrel has no tab but is welded
directly to the hull. If so, according to the theory we presented
earlier, that would also make it an M7B1. The AAR does mention that just
before being deployed to the Continent, the battalion had moved to Lyme
Regis, Devonshire where from 12 to 17 July, it "calibrated the new
self-propelled 105s." Unfortunately, the AAR does not include any
identification hints such as "M7B1" or "Ford engine". The marking "X-8"
(circled) can be seen on the right front fender. We would make a wild
guess that the whole marking might have been "3A [3rd Army]-X [separate
formation]-83 F [83rd AFA Bn]." And of course, the Priest was vehicle "A
9" within Battery A. Note the early type E8543 differential housing
with the cast in steps (1). The cable clamp (2) on the differential
housing became a standard fixture on 1944/45 Priests, although it is not
present on some early 1944 production M7s. "A 9" can be seen with a
siren (3). From the available evidence, we would simply observe that it
appears that the manufacturers transitioned to an automobile type horn
early on.
The
US 7th Army was tasked with the invasion of southern France, code named
Operation Dragoon. The objective was to establish a beachhead east of
Toulon from which the US VI Corps would push north up the Rhone Valley,
while French Army B would capture the ports of Toulon and Marseille. The
VI Corps assault on 15 August 1944 was made by three veteran US
infantry divisions, the 3rd, 36th, and 45th. Each was assigned an
armored field artillery battalion from the 6th Field Artillery Group.
For instance, the 93rd AFA Bn, a veteran of the Italian campaign, was
attached to the 36th (Texas) Infantry Division, which landed on the
"Camel" beaches in Le Dramont, east of Saint-Raphaël. The 93rd's
souvenir history states that their M7s were waterproofed and transported
to the beaches by LCTs. There is no mention of "fire afloat." The
records of the 36th ID note that the division's organic Field Artillery
Battalions that came ashore on D-Day were equipped with towed 105s
lashed to DUKWs, "prepared to fire." In any case, by 1200 hours, the
93rd AFA Bn had one battery in action ashore. It was reported that "only
two [personnel] casualties were suffered in the landing" but further
inland one M7 was destroyed "by a direct hit in the early hours of the
afternoon." We don't know of any photos or film clips showing 93rd AFA
Priests landing on D-Day, but here we have a screen capture from some
raw Signal Corps footage which shows a single M7 making its way down the
street of a town in southern France that we have not as yet been able
to identify. In the succeeding footage, joyous citizens welcome GIs
whose Jeeps have tactical markings indicating the 3rd Battalion of the
142nd Infantry Regiment, 36th ID. We suspect the Priest, which appears
to have a shallow pulpit, may have been a unit of the 93rd AFA Bn.
Another possibility is that the M7 may have been serving with the Cannon
Company of the 143rd IR, 36th ID. The 143rd's AAR for 29 August
records, "some of Cannon Company's M-7 mounts were momentarily cut off
from our troops but were able to regain contact after a fierce fire
fight." There are a few other references in the records of the 143rd IR
that suggest that some M7s were still in service with its Cannon Company
at least up to December 1944. We would note that the M7s which deployed
from Italy would have been 1942 or early 1943 production units.
We have not come across the caption of the photo above but comparing it
to other Op. Dragoon photos, believe it may show a few M7s moving
inland shortly after disembarking on D-Day from the 3rd Infantry
Division's Alpha Beach landing zone in the vicinity of Cavalaire sur
mer. The tactical markings on the lead Priest are partially obscured by
the tow cable, but what can be read appears to be "5A-6_ F Delta" (1).
The name "ANNA" (2) is also visible, along with "A-3" (3). "ANNA" rang
a bell that we were able to cross reference to a Signal Corps photo
(inset) taken in Nettuno [near Anzio], Italy, February 2nd, 1944. The
caption reads in part, “Pvt. Francis W. Maguire, Harvard, Ill.,
of the 69th Armored Field Artillery Battalion, A Battery, washing his
feet during a lull between fire missions." The 69th AFA Bn was one of
the units of the 6th Field Artillery Group (along with the 59th and
93rd AFA Bns) that had served with the 5th Army in Italy. The Group had
been assigned to the 7th Army for Operation Dragoon, but perhaps there
had not been time to change ANNA's "5A" tactical marking to "7A"? In
any case, the 69th AFA Bn was attached to the 3rd US Infantry Division
for the assault. Note that some of the cannoneers can be seen
wearing the American flag armbands that were widely distributed
for the invasion. The smoke on the far left may be a smoke screen
generated at the actual unloading site. The gun emplacement in the
center of the photo may be a dummy. The Priests are carrying quite a
few K-Ration crates, perhaps intended to be dropped off at a dump
inland? The first two M7s can be seen with one-piece differential
housings, shallow pulpits and no field or modification kit armor
protection for the exposed 105mm rounds. We would have expected that a
wading trunk and splash plate might be visible on the lead M7. Perhaps
these units were dewaterproofed immediately upon landing?
Major General Lucian Truscott, the VI
Corps Commander, had requested that a Combat Command from an armored
division be assigned to VI Corps as part of the assault. No US armored
divisions were available, but the French reluctantly agreed to provide
Combat Command Sudre, named for its commander, Brigadier Général Aimé
Sudre, from their 1ère Division Blindée but only until D+3. CC Sudre
landed on 16 August (D+1) in the area of Delta Beach which had been
secured by the 45th ID on D-Day. The major elements of CC Sudre were the
2e Régiment de Cuirassiers [tank regiment], 3e Bataillon de Zouaves
[mechanized infantry], and I/68e Régiment d'Artillerie d'Afrique with 18
M7s. It is thought that the screen capture shows a Priest of the 1er
Groupe, 68ème RAA shortly after coming ashore. The records of the 1ere
DB note that it was "the first artillery unit to debark in southern
France." Maréchal des Logis (Sergeant) Joseph Gonzales states that the
1er Groupe landed at 8:00 am on 16 August at La Nartelle Beach. In the
days that followed, CC Sudre screened the northern flank of the
beachhead "maintaining contact with the American 3rd Division in and
about Brignoles and along Highway 7 toward Aix-en-Provence." It soon
became evident that the Germans were not going to mount a counterattack
against the beachhead, so on 20 August, the unit was returned to the
1ère Division Blindée for the assault on the ports, the highest priority
objective of the invasion. Sorry to say, this image from the film is
the one that shows the most detail, so not much can be seen of the M7
except that it has a deep pulpit. The gun appears to be elevated over a
splash plate (1) that has been noted in a few period photos of M7s
modified for wading in the MTO. The inset shows the plate on "Apollo" of
the 69th AFA Bn during a practice landing in Italy about two weeks
before Op. Dragoon. This sort of thing would directly affect the
fighting capabilities of the vehicle, so it seems likely that the crew
or specialists would have removed the plate along with any other wading
impedimenta at the earliest opportunity. One of the cannoneers is
wearing a French flag shoulder patch or écusson. Maréchal des Logis
Gonzales related "Everywhere the population shows us their immense joy
at being FINALLY liberated, and by the FRENCH." We might note here that
Operation Dragoon was a controversial decision opposed by proponents of a
continuing Italian campaign, led by British Prime Minister Winston
Churchill. Some units of French Army B, redesignated French First Army
on 25 September 1944, were veterans of the Italian campaign, while
others were new units that had been formed and trained in northwest
Africa. In the event, there was no way that the French Army would have
agreed to continue to serve in Italy as opposed to fighting for the
liberation of their own country.
The invasion was accomplished with "an amazing degree of success and a
minimum of casualties." Consequently, the II Corps of French Army B was
ordered ashore several days ahead of schedule. The French Army
commander, General De Lattre de Tassigny boldly determined to expedite
matters by dividing his II Corps so that both Toulon and Marseille would
be assaulted at the same time, each by two divisions. These were
heavily fortified cities whose defenders (13,000 in Marseille and 18,000
in Toulon) outnumbered the attackers. Despite that, with ample naval
and air support, and after much bitter fighting, the French compelled
the surrender of both garrisons on 28 August, weeks ahead of schedule
and with their port facilities mostly intact. The great prize was
Marseille, the largest port and the second largest city in France.
Eventually about 1/3rd of US troops and supplies would come into the ETO
through the port. The photo above shows a scene from a liberation
parade held in Marseille on 29 August. This was filmed in the Vieux Port
area on La Canebière at the intersection of Cours Saint Louis. The 3rd
Algerian Division, Combat Command Sudre and the Forces françaises de
l'Intérieur [FFI] played leading roles in the fight for the city and
proudly passed in review. The M7 in the foreground can be seen with the
"Preparation for Overseas Movement" or "POM" code of "MF42311D" (inset).
French sources have it that this indicates the 1ere batterie, 1er
groupe, 68e Régiment d'Artillerie d'Afrique. Again, it can be noted that
these M7s are not installed with any sort of armor protection for the
exposed 105mm rounds. They do show the loops and fittings for the canvas
cover, although the "top bow" is not present, at least not on the
left-hand side. Step ladders, which appear to have been removable, can
be seen threaded through the rear rungs on these Priests. We would
mention that, in Normandy, Brittany and southern France, unit histories
laud the FFI for the invaluable assistance they provided. General
Alexander Patch, commander of the US 7th Army "estimated that from the
time of the Mediterranean landings to the arrival of U.S. troops at
Dijon, the help given to the operations by the FFI was equivalent to
four full divisions."
Gen. Truscott, the VI Corps Commander, did not have confidence that he
would be permitted to retain CC Sudre, so during invasion planning in
Italy he had his deputy commander, Brigadier General Frederick Butler,
organize an ad hoc mechanized force that would be as close to an armored
combat command as possible using available units of the VI Corps. Task
Force Butler was composed of the 117th Cavalry Reconnaissance Squadron,
the 2nd Bn ("in motors") of the 143rd Infantry Regiment, 36th ID,
Companies B and C of the 753rd Tank Bn, Company C of the 636th Tank
Destroyer Bn and the 59th Armored Field Artillery Bn. The planners had
envisioned a methodical advance north from the beachhead, but Truscott
wanted a mobile force on hand in the event an opportunity for
exploitation should arise. He became privy to an Ultra decrypt that
indicated that the German Nineteenth Army had been ordered "to retreat
and establish a defensive line along more favorable terrain in the
interior." With that in mind, Truscott ordered Butler to advance, and
starting on 18 August, the Task Force set off up the Rhone Valley with
the idea of blocking the Germans' line of withdrawal in a manner similar
to that which was playing out at the time in Normandy. In the
uncaptioned photo above, the unmistakable profile of the mountain, "Le
Rocher de Neuf Heures", overlooking the town identifies the scene as at
Digne les Bains about 75 miles north of TF Butler's starting point at Le
Muy. On 19 August, "General Butler saw an opportunity to encircle the
enemy at Digne by a flanking maneuver and a surprise attack." B troop of
the 117th Cavalry plus a company of infantry supported by medium tanks
and a large contingent of the FFI compelled the surrender of the 600-man
German garrison. By the tactical markings on the differential housing,
it is thought that the photo shows an M7 of B Battery, 59th AFA Bn
making its way west over the "Grand-Pont" [bridge] at Digne on the
evening of the 19th. By last light, most of TF Butler would be assembled
at Sisteron a further 25 miles to the north. The 117th Cavalry
Reconnaissance Squadron comprised the greatest part of TF Butler, and we
would mention here that while the unit was in a staging area near
Naples, their records for 18 July 1944 state that "E Troop received new
guns. The M7 Self-propelled 105mm howitzers were a much needed
replacement for the M8 75mm Howitzers with which we had been operating
throughout the Italian Campaign." This was an unusual arrangement for a
Cavalry unit, but the 117th appears to have been granted "special
authority" to use their M7s to the end of the war. General Butler notes
that on 22 August, the "Assault Gun Troop enjoyed the shoot of the day.
The 105's were delivering aimed fire at enemy columns west of Loriol and
at a range of 2500 yards. Firing high explosive and phosphorous these
guns accounted for hundreds of vehicles setting them ablaze and sending
occupants scurrying." Ultimately, Truscott's bold attempt to surround
and destroy the German Nineteenth Army inside the "Battle Square" at
Montélimar (21 -29 August) was foiled primarily by logistical issues.
The planners did not anticipate that the VI Corps would make such a
rapid advance, and did not have the ammunition, fuel and transportation
necessary to affect the outcome. The damage inflicted on the enemy as a
result of Operation Dragoon was significant to say the least. It is
estimated that the German Armies in southern, central, and western
France lost about 150,000 troops. Patch's 7th Army had advanced almost
400 miles in less than a month. The so called "Champagne Campaign" came
to end on 11 September with the link up of the 7th Army with Patton's
3rd Army near Dijon. At that point, the 7th Army and the French 1st Army
came under command of Eisenhower's European Theater of Operations
(ETO). With thanks to Loïc Jankowiak.
By mid-September 1944, logistical issues brought an end to the Western
Allies' heady pursuit of the Germans across France and the Low
Countries. Despite having suffered catastrophic defeats, the Germans
recovered and managed to stabilize their lines along the entire Western
Front. The 5ème Division Blindée embarked from Oran on 15 September and
landed in southern France on the 21st. The 62ème Régiment d'Artillerie
d'Afrique was a component of the 5ème DB and because of their late
arrival, some of the gunners of the 4ème Batterie were worried, "The
advance of the Allied troops is so fast that, for a moment, we lose hope
of ever fighting." As it turned out these men would see plenty of
action in the Vosges Mountains and in Alsace, where they would endure
mud, snow, and extreme cold while trying to move their M7s and support
vehicles through the mountainous terrain. The 3 Groupes of the 62ème RAA
are reported to have engaged in their first fire missions on 3 November
in support of an attack by Groupement Bonjour of the 3ème Division
d'Infanterie Algérienne against an enemy position near Le Haut du Tôt, a
village in the Vosges Mountains. The Signal Corps photo above shows
what appears to be a 1942 production M7 that the caption identifies as
of the "5th Div. Blindee, 1st French...in Kaysersberg area" on 17
December 1944. As the number of units deployed overseas increased, the
supply of artillery ammunition fell well short of demand, and SC256262
was part of a series aimed at the US Home Front that illustrated "why
ammunition production must be stepped up to supply the needs of modern
warfare." The tactical marking painted on the side of the vehicle and
shown in the inset, identifies this Priest as with the 6ème Batterie,
62ème RAA. Kaysersberg was actually in German hands on 17 December. The
After Action Report of the 2ème Groupe, the parent formation of the 6ème
Batterie, indicates that the unit arrived in Aubure, 15 kms north of
Kaysersberg on 7 December and indeed, we have been able to determine
that the photo was taken in the garden of a house located on the Route
de Ribeauvillé in Aubure. The 2ème Groupe was attached to Combat Command
4 of the 5ème DB and supported attacks on Orbey and Kaysersberg until
18 December.
Here we have the next photo in the "produce more ammo campaign" series,
SC256263. The caption is again dated 17 December 1944 and is identical
to that of SC256262 above. Again, we take the location to be Aubure
based on the group of buildings seen in the background which we have
been able to identify as the Sanatorium Bethel. It is assumed that "les
automoteurs M7" in this series of photos were within sight of each
other, but unlike the Priest in the previous image, this is another
example that can be seen to have been retrofitted with a side door. In
his study of French armor, Pierre-Olivier does not think that the
practice was widespread, "I have only seen "a few" of these side door
jobs in the 62ème RAA, for instance, on Marignan II and Rocroi
II." The inset shows what appears to be the same Priest as in the main
photo judging by several similarities including the lone remaining
(front) section of the Grant type sand shield and the "broomstick" by
the head light. It can be noted that the door was hinged along the
bottom like the one shown earlier in the Base Shop at Livorno. Our
analysis suggests that the inset photo was taken in Riedwiehr, 10
kilometers north-east of Colmar. The AAR of the 2ème groupe
states that the 6ème batterie was in Riedwihr on 27 January, and
that about a week earlier, "the tanks were painted in white to
blend into the snow that accumulates more and more".
This Signal Corps photo is captioned, "An American self-propelled gun
fires on German positions in the Rhine Valley, in the Ribeauville area,
France. 12/9/44 [Dec. 9, 1944] ...RESTRICTED: Cannon Co., 143rd Inf.
Regt." The "Restricted" info was not to be included in the caption
should the photo be published in newspapers, but there it is to our
benefit. We read through the AAR of the 143rd Infantry Regiment, 36th ID
from Operation Dragoon to the end of the war, and it rarely mentions
"M7" in regard to the Cannon Company. However, for 10 December there is
an entry, "An M-7 self-propelled gun of the Cannon Company was reported
to have registered two direct hits on an enemy Mark VI tank at V-709485
[map coordinates]." Thus, we have a little textual confirmation that the
Cannon Company of the 143rd had at least one M7 in the area at the
time. We can't say that we have come across any references to M7s in the
AARs of the 141st or 142nd IRs of the 36 ID. The Priest can be seen to
be an early model with a shallow pulpit, and side hinged stowage boxes
with the "ramps" for the auxiliary fuel tanks. That would put the
production date of this unit as September 1942 or earlier. We would
observe that "The Texas Special" and the M7 next to it photographed in
the Bastille Day Parade in Rabat Morocco in July 1943 both had top
hinged stowage boxes, so this example is neither of those. However, as
with the photo of "The Texas Special" in Italy in January 1944, a
section of armor plate has been very neatly welded to the side to
protect the exposed rounds, and in this instance, it can be noted that
it bends around to the rear. What appears to be a standard pioneer tool
rack as used on many US WWII tactical vehicles can be seen retrofitted
under the pulpit. This is another example where the gun travel lock has
been removed from the fighting compartment and can be seen resting under
the crew gear on the rear deck (arrow.) Most of the gunners are facing
to the rear and looking up at the photographer. We have done a bit of a
digital Cook's tour of the features seen in the photo and have
determined that the photographer was standing on the terrace of the
former "Hôtel Belle Vue" (inset) which appears to have been the Command
Post of the 36th ID at this time.
The
photo above is captioned, "105mm howitzer mounted on M7 mount, fires
its first round at the enemy since going into action on this 7th Army
front in France, 25 Dec 1944...#2 gun section, Battery A., 493rd FA Bn.,
12th Armd Division." This Signal Corps photo appears in the 493rd's
"Pictorial History" where the date is given as December 5, 1944, the
location as Weisslingen, France and the event is described as a
milestone - "the Division's first combat round...the first of over
44,000 rounds of 105 M.M. ammunition expended by the Bn during the next
150 days." The 12th AD arrived in the UK in early October 1944 and was
stationed at Tidworth Barracks where, "Vehicles and other supplies began
to pour in from large warehouses scattered over the English
countryside. Peeps, 6x6's, half-tracks, and M-7's began to roll into
Tidworth with regularity. They were immediately checked and made combat
serviceable. Above all, the sight of Ford tank motors brought great
delight to all and especially to motor sergeants and drivers who well
remembered the old radial motors." We mention this because, although we
have not as yet found definitive supporting documentation, we suspect
that the three AFA Bns of the 12th AD may have been entirely equipped
with M7B1s, at least at first. In the area of "counting heads", we might
observe that we have seen over 20 photos of 12th AD M7B1s in the ETO,
but not a single in theater shot of a 12th AD M7. In any case, the
division landed at Le Havre, France on 11 November, and convoyed cross
country until it arrived in Luneville on 2 December. The 12th AD was
assigned to the XV Corps on the northern flank of the US 7th Army and on
5 December, the division's three armored field artillery battalions
became the first units ordered into action, "the 493rd and 494th went to
an area near Drulingen to support the 44th Infantry Division, and the
495th moved to the vicinity of La Petite Pierre to support the 100th
Infantry Division." This M7B1 is one of the few Priest "combat shots"
that shows the factory sand shields "still" installed. It might be
assumed that the man standing behind the retrofitted .30 caliber machine
gun is the "Chief of Section."
This
Signal Corps photo appears in "Thunderbolt: The History of the Eleventh
Armored Division" with the caption, "Artillery lines the road on the
outskirts of smoldering Obernust, Germany." Unit records indicate that
all three of the division's armored field artillery battalions, the
490th, 491st and 492nd passed through that area on 1 April 1945
supporting the advances of their respective combat commands. The 11th AD
arrived in the UK in mid-October 1944. By the end of November, the
division was almost completely equipped and "Opportunities had been
provided for every unit to fire all weapons newly received, including
the artillery 105's and the 76mm tanks." The 11th arrived in France in
early December. It was intended that the division would go into Brittany
to continue its training under combat conditions by assisting in the
containment of the German garrisons of the bypassed ports such as
Lorient and Saint-Nazaire. However, with the German attack in the
Ardennes, the division's mission was changed, and it raced east to the
Battle of the Bulge. The AFA Bns are reported to have fired the
division's first shots in anger on 30 December. The unseasoned 11th AD
was attached to the 3rd Army and in the eyes of its irascible commander,
George Patton, it did not perform up to his standards. By the spring of
1945, the veterans of the 11th AD had mastered the art of blitzkrieg
warfare, and "became a very fine division" according to Patton. Here we
see a column which includes five Priests towing the older M8 Ammunition
Trailers. The fully enclosed M8 trailer was manufactured by John Deere
& Co. and had the capacity to carry 42 rounds of 105mm ammunition.
It was classified as Limited Standard in November, 1943 and was superseded by
the open-topped M10 Ammunition Trailer. At least three of these Priests
can be identified as M7B1s. The Army considered the Ford GAA V8 engine
to be the best tank power plant and strove to supply its fighting forces
with as many Ford engined Shermans as industrial conditions would
permit. While we don't as yet have any facts and figures, based on
photographic evidence, it would appear that a good number of the 664
M7B1s produced by Pressed Steel Car in 1944 were shipped to the ETO and
issued to the AFA Bns of the later arriving Armored Divisions such as
the 8th through the 14th and the 16th. Furthermore, the evidence
suggests that the earlier arriving ADs, the 2nd through the 7th, were
predominantly issued M7s and later on received both M7s and M7B1s to
replace combat losses. For some reason, 1944 production Priests were
built with sand shields which most crews promptly removed. Note that the
M7B1s in the photo are equipped with extended end connectors which of
course required removal of the sand shields. The 11th AD AARs report
that "Steel “duck bills” were added to all full track vehicles for the
purpose of widening the tracks and providing more traction." In the case of the 492nd AFA Bn these were stated to have been
installed on the 23rd of December during a stop at the Foch Barracks in
Laon, France about 130 miles west of Bastogne.
This
Signal Corps photo is dated "26 Feb 45" and captioned, "A tank [sic] of
the 10th Armored Div., US Third Army, crosses the Saar River over a
ponton [sic] bridge at Saarburg, Germany. CCA." Readers might recall
that M7, SN 2843 at the U.S. Army Field Artillery Museum honors the
420th AFA Bn and indeed all of Combat Command B of the 10th AD which
played a key role in the defense of Bastogne. Of course, the "CCA" in
the SC caption refers to Combat Command A which along with the rest of
the 10th AD defended the right shoulder of the Bulge in northern
Luxembourg while CCB fought at Bastogne. There are no visible markings
on the M7 in the photo, but we may be able to identify the unit as the
419th AFA Bn based on entries in the battalion's After Action Report,
"On Feb 25, the 419 took its place in the column of CCA, and crossed the
Saar River at Serrig on Feb 26. The 419 fired very effectively in
support of the Division’s columns in the attack northward toward Trier."
While the caption gives the location as Saarburg, Pierre-Olivier had no
trouble using Google Street View to confirm that the site of the
pontoon [treadway] bridge was actually 4.5 km south at Serrig, since the
area has hardly changed in the last 79 years. In any case, the "tank"
can be identified as an M7B1. Note the flat block rubber tracks with
extended end connectors. In late December 1944, the 419th AAR notes that
"The steel tracks of our M-7s slid like skates on an ice rink." In
early January 1945, as the unit reorganized and refitted near Metz,
"Steel tracks were removed from the M-7’s, and replaced by rubber
tracks." However, there is no mention of EECs installed at that time. We
would guess that the 419th AFA Bn was equipped with M7B1s either
partially or entirely, but the AAR never hints at it, always referring
to their mounts as "M-7s". The M7B1 can be seen towing an open-topped
M10 Ammunition Trailer. These are generally seen covered with tarps.
Because of the location of the Priest's towing pintle, the ammo trailers
are noted with a downward tilt at the front.
The 16th Armored Division, the last US AD activated during World War II,
arrived at Le Havre, France in mid-February 1945. After drawing
equipment and organizing, the division was placed in theater reserve in
northern France. As the Third Reich collapsed, the
division was ordered forward and was assigned to occupation duty in
Nuremberg. A sizeable German force occupied Czechoslovakia, and in early
May, Patton's Third Army was ordered to advance into the country and
defeat them in tandem with the Soviets attacking
from the east. The Third Army's primary objective was Pilsen (Plzeň),
the most important city in western Bohemia. At the time, the Third Army
was the largest it would ever be with 18 divisions and over 540,000
troops, including a number of veteran outfits
operating at their peak. Nevertheless, from his memoirs, it would
appear that Patton specifically selected the untried 16th AD to have the
honor of taking Plzeň, "We were very anxious to get the 16th into a
fight before the war stopped, and they were very
anxious to get there." We have not been able to identify the source of
the above photo, but would be pleased to hear from any readers that know
of it. Unfortunately it doesn't show any markings other than the
vehicle's name (1) which is illegible, but we asked
our Czech colleague, Ondřej Rott, to give us his impressions. "I am
fairly confident that this indeed is 16AD vehicle seen during the Pilsen
liberation day (6 May 1945). As you can see this is cloudy and rainy
day in this photo, as was during the liberation
of Pilsen. And there are bunches of lilac attached to the vehicle - it
was typical for Czechs to greet their liberators with these flowers
which blossom in early May." Ondřej went on to observe that the
smokestack in the background of the photo suggested that
the scene was shot in the factory suburbs of Pilsen, that is, in the
western part of the city near the bombed-out Skoda works. Each of the 3
Combat Commands of the 16th AD had an Armored Field Artillery Bn
attached. The 393rd AFA Bn was with CCA, the 396th
with CCB and the 397th with CCR. All of the Combat Commands fanned out
across the city and set up blocking positions against counter attacks.
All dealt with pockets of resistance, primarily in the form of snipers
which appears to be the case in this photo.
This was the first and only combat mission of the 16th AD and "Every
May since 1990, Plzeň goes notionally back to 1945.
Liberation festival is held here and people from all over the world
come here to celebrate the liberation by the US Army with the
inhabitants of the town, military veterans and their families together."
A number of books about the liberation of western
Czechoslovakia have been published by Czech authors, and we can observe
that of the six or so known period photos of individual 16th AD
Priests, all can be seen to be M7B1s. All are noted with steel tracks,
either the T49, "steel, cast, parallel grouser" type
seen here (2) or the T54E1, steel chevron type, and all are seen with
extended end connectors installed. In this photo we can just see the
frame of an M10 Ammunition Trailer (3), attached below the standard
sheet metal type exhaust deflector (4). Above this
is a very elaborate, field installed "luggage rack" (5) which we have
also seen on other Priests of the 16th AD photographed around Plzeň.
This photo is dated 4 July 1945 and captioned, "Tankmen of the Second
Armd Div. fire a 48-round salute in Independence Day ceremony in Berlin
marking American Army's occupation of the former Nazi capital." Where
they can be seen, the tactical markings on the M7s indicate Battery C of
the 78th Armored Field Artillery Battalion, 2nd AD. The aptly named
"Coming Home" can be seen as USA 4038604 indicating that it was produced
by ALCO in December 1942. The "S" tacked on to the Registration Number
stands for "suppressed" meaning that the vehicle's wiring had been
shielded so that it would not interfere with the radio. We would note
that it is frequently stated that US Priests were not ordinarily
installed with radios. Earlier we mentioned that period photos showed
that at least some of the M7s of the 2nd AD had had "mine racks" (1)
added to their sides while in the UK before D-Day. We doubt very much
that crews would have continued to store mines in the racks after their
first few days in combat. "Coming Home" is another example like
"Conflict" featured earlier that was retrofitted with what looks to be a
standard pioneer tool rack (2) as used on many US WWII softskins. The
fittings (3) across the middle of the engine access doors on C-6 on the
far right as well as on "Coming Home" indicate that these units were
once installed with wading trunks. This suggests that they had landed on
Omaha Beach on 11 June 1944 and had served until the end of the war and
beyond. Because of their role, M7s did not suffer the high attrition
rates experienced by front line armored units. Just doing a little math,
by VE-Day, there would have been 18 Armored Divisions (including 3
French) each with 3 AFA Bns plus 16 non-divisional AFA Bns in the ETO.
This would amount to a total of 70 AFA Bns with 105mm SP which would
have required 1260 M7s assuming each battalion was always at full
strength. If we throw in the odd cases, such as the M7 equipped Field
Artillery Bns of the 4th ID and E Troop of the 117th Cavalry
Reconnaissance Squadron and perhaps a few more unknowns, we might
generously add another 100 M7s. And of course there would have been
replacements in the reserve pool, maybe 10 %. So, we figure there might
have been around 1500 M7s in theater. For the year that the Priests were
in combat in the ETO, losses appear to have averaged about 12 per month
except for December 1944 when more than 100 were reported lost during
the Battle of the Bulge. This was most likely due to front line infantry
and armored units routing past their supporting artillery during the
early days of the attack. For the most part, the gunners stood fast
until they were overwhelmed. For instance, the long serving veterans of
the 58th AFA Bn lost 8 of their M7s attempting to slow the German
onslaught at Longvilly and Margeret on December 19, and the last 8 on
the 22nd when the battalion was surrounded at Tillet to the west of
Bastogne. The unit's leadership came in for some criticism, "When an
artillery battalion finds itself firing direct fire on approaching enemy
armor with frontline infantry units withdrawing through their
positions, it is apparent the armored field artillery battalion is not
being correctly employed." With their guns and support vehicles lost,
the surviving veterans of the "Five-Eight" feared that they would be
transferred to the infantry, but the unit was rebuilt in the following
weeks and served with honor to the end of the war.
Before we leave the ETO in WW II, we might mention an interesting
modification that was the subject of a series of Signal Corps photos
documenting a demonstration held on 28 February 1945 for ranking
officers of the US Sixth Army Group and US Seventh Army. One of the
official SC captions reads “New 9.75 [inch] mortar shells which are
fired from a mortar mounted on a M.7 motor carriage. White phosphorus
shells on “fire bombs” which contain permananti, can be used as well as
smoke shells. U.S. Seventh Army, Benny, France.” Also known as a “Fire
Mortar” or a “Chemical Mortar”, this weapon was developed by the British
Petroleum Warfare Department (PWD) and fired shells variously described
as being filled with permananti, napalm, or white phosphorus. The
mortar had been demonstrated to British officers on 20 April 1944 near
Barton Stacey, England. In that case, a turretless Valentine tank was
the testbed. We find no evidence that the British adopted the Valentine
based self-propelled mortar for use on D-Day or after. The Priests seen
here have been identified as M7B1s by several internet sources. The
available SC photos show two units, and both can be identified as ALCO
M7s. The "high" headlights seen on the Priest on the left would indicate
an ALCO 1942/43 production M7. Of course, the shallow pulpit seen on
the one on the right would also indicate an ALCO M7. Note that the unit
on the left is installed with rubber chevron tracks while the other has
steel chevrons. The angular design of the lower wading trunk seen on the
shallow pulpit model suggests that it may have been converted from an
ex-British M7. A close examination of the right-side print reveals what
may be further evidence of the M7's origin with what appears to be a
British WD number (2157?4) visible on the rear hull side, which is
within a known range for Commonwealth Priests (215638 to 215937).
Reports vary, with some sources stating that these vehicles were not
accepted for service by the US Army, while others state that three "saw
combat".
Meanwhile, back on the homefront in 1945, Pressed Steel Car finished out
its M7B1 Production order with 150 units manufactured in January and
the final 12 in February. Federal Machine and Welder, a company in
Warren, Ohio with about 950 employees was the smallest manufacturer of
Shermans, producing 540 M4A2s from December 1942 through December 1943.
After that, it was given contracts to remanufacture 317 used M4A2s
(April to November 1944) and to remanufacture and convert 400 "M32 and
M32B1" Tank Recovery Vehicles (November 1944 to May 1945). In mid-1944,
FMW was contracted to produce 259 new M7s at an estimated cost per unit
of $25,000. Production was "expected to start in January 1945." A 1945
monthly Ordnance Production document labels FMW M7s "Critical"
procurement items, but we are not sure why because on 23 November 1944,
the Ordnance Technical Committee had recommended reclassification of
both the M7 and M7B1 as "substitute standard" and this had been approved
on 18 January 1945. With that, one might think that the order would
have been terminated, since the M7 series was intended to be replaced by
a new standard, the M37 Howitzer Motor Carriage based on the M24 Light
Tank chassis. However, series production of the M37 was delayed until
September 1945 and, with the end of WW II, the contract was terminated
at 150 units. Ultimately, FMW manufactured 176 M7s from March to July
1945 when their contract was terminated. Not much has been documented
about the FMW M7s, but the few period photos available suggest that at
least some and more likely all were made with the E9 suspension
modification factory installed. This was a "too late for WW II” attempt
to further increase the floatation of VVSS Shermans by the addition of
spacers that extended the suspension away from the hull by 4.5 inches.
This permitted extended end connectors to be installed on the inside as
well as on the outside of the tracks. Essentially, this increased the
track width to 23 11/16 inches, slightly more than the 23-inch track on
the Sherman with HVSS. As best we can determine, in 1945, the only new
production Sherman based vehicles built with VVSS were the 176 FMW M7
Priests and 162 PSC M7B1s. This was intentional according to Ordnance
Committee Memorandum 24984, "105MM Howitzer Motor Carriage M7 and M7B1 -
Delay in Conversion to Horizontal Volute Spring Suspension and 23" Wide
Track" dated 31 August 1944. "Due to the estimated lack of availability
of sufficient quantities of the new suspensions and tracks to equip all
vehicles at the same time, it is intended to delay this application in
the case of the 105mm Howitzer Motor Carriage M7 and M7B1 until the
third quarter of 1945." The Priests were excepted due to their
relatively light weight. It was noted that with standard 16 9/16-inch
VVSS tracks, the M7 series had a ground pressure of 11 pounds per square
inch, and this could be reduced to 9 PSI "when duckbill end connectors
are used." Above is a view of the 7th FMW M7, Serial Number 4917, USA
40190389, photographed at the General Motors Proving Ground on 2 May
1945. Note that this unit features the "flat" fender braces such as were
provided in the E9 Modification kit. We don't find evidence on any
surviving examples that would suggest that the 162 M7B1s produced by
Pressed Steel Car in January and February 1945 had E9 factory installed.
With thanks to Kurt Laughlin for providing a copy of OCM 24984.
The M7s produced by Federal Machine appear to have differed in a few
minor details from those built by ALCO in 1944. We suspect that they
were assembled with single rear towing lugs (1), and factory installed
T-shaped towing shackles (2) at the front and rear, M4 type hinges on
the engine access doors (3) and short trailer towing pintles (4). A
close look at the previous photo and 2 known surviving examples shows
fuel filler covers where the hinge barrels were welded directly to the
armor (inset), that is, no tabs as on ALCO M7s. Also, the grouser boxes
appear to be the type used on the M7B1. The triangular shaped object
just below the number 5 likely served as a "bumper" intended to keep the
blanket box from being damaged when the lid of the stowage bin was
fully opened. This addition looks to have required an outward
repositioning of the blanket baskets compared to 1944 ALCO M7s. Assuming
as we do that all of the FMW M7s were built with E9, leads us to assume
as well that none were built with sand shields installed.
Here we have an APG photo dated June 1945 that features a trial of a
pintle adaptor for the M10 Ammunition Trailer which raised the "angle of
travel" closer to horizontal. The adaptor was supplied to APG for
purposes of a 200-mile test. It was described as of "three (3) piece
welded construction." We don't have a photo but think it was what is
shown in the inset. FMW built its last 49 M7s in July 1945, and we would
guess that the pintle adaptor project was terminated by the end of the
war. The test M7 was SN 4919, USA 40190391. It would have been accepted
at Federal Machine and Welder in April 1945, two units after the
previous example. Note that both 4917 and 4919 are seen with the
"concave" road wheels (1). "Betty Sue" does not have extended end
connectors installed, but in a side shot such as this, the "E9 recess"
in the drive sprocket (2) is a surefire indication that the vehicle
was installed with the E9 Modification.
Because of their late date of
production, March to July 1945, we doubt if any FMW M7s were shipped
overseas and/or entered combat before the end of the war. The photo
above shows an example that took part in what the caption describes as
the "82nd Airborne Division Parade" in New York City on 12 January
1946. This was actually a World War II Victory Parade in which the
13,000 men of the 82nd marched up 5th Avenue representing all of the
military men and women of the Allied Nations. The parade was 4 1/2
miles long and included Sherman tanks which the newsreels show parading
past the famous statue of their namesake, General William Tecumseh
Sherman on Grand Army Plaza by Central Park. An ESSO Newsreel reported
that "79 flat cars hauled the mobile units to New York from Ft. Bragg,
North Carolina." The M7, named "ABLE'S ACE" carries tactical markings
of the 342nd Armored Field Artillery Battalion, an independent AFA Bn
that arrived in Marseille in late 1944 and first entered combat on 23
January 1945. The unit served in support of various infantry and
armored divisions of the 7th Army until V-E Day. It is assumed that the
M7 in the photo was drawn by the 342nd when they returned to Ft. Bragg
in anticipation of redeployment to the Pacific.
As
best we can tell from the few surviving Federal Machine and Welder
M4A2s and M7s, the company did not stamp the vehicle serial number on
the rear towing lugs or anywhere else on the exterior. Here we have a
photo of what we take to be a surviving FMW M7, one of three that we
know of with the E9 modification and the flat fender braces. Although
the extended end connectors are no longer installed, note the gap (1)
between the tracks and the differential housing and the much wider front
fenders (2). Pierre-Olivier reported seeing traces of the name "Arcole"
and hints of the 5ème Division Blindée flag showing through the paint
layers on the sides. A French post-1947 matricule number "828 148" was
also visible on the differential housing (3) and on the left rear
stowage bin. These markings would suggest that this M7 was provided to
the French in the early 1950s as part of the Mutual Defense Assistance
Program. The Priest also has some distinctly Austrian looking markings
(4) prominently painted on both sides, which at least hints at the
possibility that this M7 may have seen service with the Austrian Army.
Unfortunately, P-O could not find any evidence of the vehicle's serial
number.
The
owner kindly permitted Pierre-Olivier to have a look around his
shop and P-O was able to squeeze around the back and get this shot of a
pair of items not seen in the General Motors Proving Ground photo of SN
4917 featured earlier. The air cleaners were vulnerable to combat
damage, and we have shown a few instances where some units attempted to
protect them by simply welding steel plates in front of them. As a
result of battlefield reports, a "protector assembly" (1) was designed
in late 1944. We don't have any FMW documentation but can cite our
"counting heads" study of the M4A1(76) in which we found that supplies
of the protector assemblies appear to have become available to Pressed
Steel Car in May 1945. If the same held true for Federal Machine, then
perhaps between 100 and 150 of their M7s were built with these
components factory installed. Also not seen in the photo of SN 4917 is
the triangular shaped gusset (inset 1, circled) which is present on both
sides of this unit. The gussets are also noted in a small number of
period photos. We would guess that they were intended to strengthen the
side plates when the protector assemblies were installed. The boxes were
hinged, and these are in the "up" position to permit the servicing of
the air cleaners. Inset 2 shows the assemblies in the intended
protective position as seen on the M4A1(76)HVSS in Griffith, Indiana.
US use in the Pacific Theater of Operations
A number of the regimental cannon companies of the 20 US Army infantry
divisions deployed to the Pacific Theater of Operations were organized
under a modified table of organization and equipment "TO&E 7-14S"
published in February 1944. This authorized the companies to be equipped
with "105-mm Howitzer, Self-Propelled." This would have replaced the
July 1943 TO&E of "six 105-mm howitzers M3 with prime movers" with
"six M7 HMCs with M10 armored ammunition trailers." Exactly when and
which units were issued M7s has been hard to pinpoint, since not much is
written about cannon companies in the Regimental AARs. This screen
capture is part of some raw color footage strung together and cataloged
as "BOMBARDMENT; AMPHIBIOUS OPERATIONS: SCENES AFTER OCCUPATION;
INVASION OF ENIWETOX [sic]" on the National Archives website. The
US Marine Corps history, "Central Pacific Drive", reports that on 18
February 1944, the 22nd Marine Regiment assaulted the island of Engebi
in the Eniwetok Atoll. They were supported by "a platoon from the Cannon
Company, 106th Infantry [Regiment, 27th US Army Infantry Division] with
two 105-mm. self-propelled guns." Neither the USMC history or the
official Army history ever refer to these as "M7s", but the definition
of "105-mm. self-propelled gun" at this time would have been limited to
the M7 and we do see a Priest in the film footage. In any case, at
present, February 1944 is the earliest instance we have encountered of
M7s in combat in the PTO. On Engebi, there is textual evidence that the
M7s fought, "Near Skunk Point...1/22 encountered concrete pillboxes
which were the key to the enemy defenses around the southeastern corner
of the island. Two self-propelled 105mm guns from the 106th Infantry
Cannon Company, weapons originally sent to the aid of Company A, were
withdrawn upon request of Company C and sent to deal with the heavy
fortifications. The self-propelled guns fired almost their entire day's
allowance of ammunition, 80 rounds, in order to destroy two pillboxes,
one of which sheltered 25 to 30 Japanese. Effective as they were, the
self-propelled 105s were not especially popular with the infantry units
which they supported. "They made a very inviting target for mortar and
other small arms," commented a veteran of the Skunk Point fighting,
"and, consequently, were not a very comforting thing to have around."
The 105s, though, had revenge on their Japanese tormentors, for during
the afternoon they wiped out an enemy mortar crew." Engebi was declared
secured at 3 pm, 18 Feb. The 106th Infantry Regiment assaulted the next
target, Eniwetok Island, on 19 February. There are several occasions in
the Marine and Army histories when it is mentioned that "two Army
self-propelled 105mm guns" supported elements of the 106th IR as well as
the 3rd Battalion of the 22nd Marines. There are no mentions of the use
of "self-propelled 105s" on Parry Island the final objective of the
Eniwetok Atoll operation. We think that the screen capture shows an M7
landing on Eniwetok not Engebi, since the soldiers in the scene appear
to be Army not Marines. The
unit is shown debarking without wading trunk(s), although we suspect
that the lower hull was sealed for shallow water fording.
After watching the footage multiple times, we believe that there
is a pintle mount for a 0.30 caliber machine gun (arrow) such as
is seen in the photo in the next caption.
This Army Pictorial Service photograph is captioned, "Saipan. A
self-propelled gun mount and a jeep stop beside American casualty after
an unsuccessful attempt to storm Jap pillboxes." We take "6/20" typed on
the caption to be the date, which would have to be 20 June 1944. On 15
June 1944, the 2nd and 4th USMC Divisions landed on Saipan's
southwestern coast. Resistance was much fiercer than expected and the
20,000 man assault force suffered over 2,000 casualties in the first 24
hours. The 27th Infantry Division formed the reserve of the 5th
Amphibious Corps and was ordered to land the 165th and the 105th
Infantry Regiments on 16 and 17 June respectively. Elements of these
units captured Aslito airfield on the 18th, and after that, their
mission was to trap and "mop up" the enemy troops holed up around
Nafutan Point in the island's southeast corner. It is thought that the
photo shows part of this operation in which the 105th and 165th IRs
attacked "heavily fortified built-in positions over exceedingly
mountainous terrain." By a process of elimination, we would guess that
the M7 was with the Cannon Company of the 165th IR, since the docs note
that, at this time, the 105th was "without their organic cannon company,
consisting of 75mm self-propelled guns [consequently] the regiment was
incapable of suppressing the enemy while the infantry and engineers
rooted them out." In the meantime, the 106th IR was still in floating
reserve offshore. As noted in the previous caption, "a platoon from the
Cannon Company, 106th Infantry with two 105-mm. self-propelled guns"
supported Marine and Army units during the Eniwetok Operation. The
records of the 106th IR for Saipan are a bit more helpful as they
actually state that their Cannon Company consisted of 2 M7s and 6 M8
Howitzer Motor Carriages as shown in the radio diagram in the inset. We
suspect that the 106th had this unusual arrangement during the Eniwetok
Operation as well. It may have been based on the availability of M7s and
M8s at the time. We might assume that the Cannon Companies of the 105th
and 165th were similarly equipped but perhaps not, since it is
mentioned that the cannon company of the 105th IR consisted of "75mm
self-propelled guns." A comment in the 106th's files praises the
performance of "the self-propelled mounts" and adds, "A truck drawn
weapon as prescribed for the armament of the Cannon Company would have
been unable to carry out the missions assigned." In any case, the M7
appears to have "CN 8" painted on the differential housing on the left
side. It can be seen with an antenna (1) and a retrofitted .30 caliber
machine gun (2). A pair of, shall we say, "flaps" (3 & 4), perhaps
part of the waterproofing process, can be seen open on either side of
the 105mm gun. The head lights are in the "high" position indicative of
1942/43 production M7s. We have looked but can't say that we have seen
any 1944 production Priests in period photos from the PTO.
This Signal Corps photo is dated 29 October 1944 and captioned "Troops
of the 381st Inf. Regt., 96th Div., take cover behind an M-7 tank while
advancing on Catman [sic] Hill, Leyte Island, P.I.". The 96th Infantry
Division landed alongside the 7th ID on Leyte near the town of Dulag on
20 October 1944. The 96th was responsible for expanding the northern
sector of the beachhead which was dominated by Catmon Hill. The 381st
and 383rd Infantry Regiments were involved in numerous assaults on the
hill, while the 382nd IR bypassed the position to the west. Since the
initial landings on the 20th, Catmon had been pounded for over a week by
naval, air and land forces. It was finally taken on 28th October by
enveloping attacks of the 1st and 2nd battalions of the 381st IR. The
official US Army history states that the attack of the 1st Battalion was
"supported by the massed fire of forty-five tanks and the Regimental
Cannon Company." Perhaps to their relief, the assaulting units came to
find that most of the Japanese troops had abandoned the hill two days
earlier. It can be seen that the "shallow pulpit" M7 still has the lower
section of a wading stack. It appears to have "CN 22" and some sort of
symbol painted on the stack. Judging by the rounded bottom of the stack,
it may have been from the M7 fording kit produced in the US. This looks
to be another case where the gun travel lock was removed, and in this
instance can be seen stored on top of the wading stack. The Leyte
Campaign fulfilled General MacArthur's promise to return to the
Philippines. After much hard fighting, the island was secured in early
January 1945. The 96th ID along with other veteran divisions of Leyte
next invaded Okinawa on 1 April 1945. The records of the 96th rarely
mention the actions of the regimental cannon companies, although it was
noted that the "self-propelled 105-mm. howitzer [was] extremely mobile
in swamps and mountainous terrain. It was able to go several miles
farther up the mountains than any other vehicles and gave excellent
support in covering the mountain passes." The 96th fought in a number of
key battles on Okinawa. In the final "Comments and Recommendations"
section of their Operations Report, the Priests are at last named -
"105mm Howitzer Motor Carriages, M-7" and numbered - 18, suggesting that
there were 6 in each of the regimental cannon companies. Of interest is
that 36 "76mm Gun Motor Carriages, M-18" are also listed as part of the
division's "combat vehicular equipment." "Due to the addition of
tank-like vehicles to the Inf Regts, it is... recommended that each Regt
be authorized one Heavy Wrecker, M1A1", and that "An ordnance medium
maintenance Co should replace the ordnance light maintenance Co now
assigned to an Inf Div."
Cannon Companies are rarely mentioned in the unit records and
histories of the Infantry Divisions that fought in the PTO, and when
they are, their equipment is mostly described in very vague terms like
"self-propelled guns." Maj. Wesley Curtis'
1950 Infantry School monograph provides some idea of the M7 timeline of
the 27th Infantry Regiment, 25th Infantry Division. He was the recon
officer of the Cannon Company of the 27th IR and he specifically states
that the company "was organized under a modified table of
equipment...[which] was the case with most of the regimental Cannon
Companies in the Pacific area." On 28 January 1945, he reports that his
cannon company was at full strength with 6 M7s with M10 trailers, and
that the Priests had been issued to the regiment "some seven months
prior to this operation." We interpret that to mean circa June 1944,
which would have been while the unit was training in Noumea, New
Caledonia. Curtis' monograph describes the Cannon Company's first combat
with the M7s at Pemienta Luzon on 29-30 Jan. The gist is that the 1st
Battalion, 27th IR set up a blocking position at a crossroads at
Pemienta, which trapped a Japanese column of the 2nd Tank Division. At a
range of 50 yards, Sgt. John Charney's M7 fired an armor piercing shell
that destroyed an approaching enemy tank which blocked the road and
halted the rest of the column. The 1st Battalion including at least 2
M7s attacked the column and repelled several Banzai charges from an
enemy desperate to escape the trap. By daylight 30 January, 8 tanks, 8
10cm howitzers with prime movers, and a number of other enemy vehicles
lay smoldering in the road. There is a Signal Corps photo of the
wreckage, but not of the participating M7s as far as we know. The photo
above is dated 8 April 1945 and captioned, "Men of the 25th Division in
combat with Japs in Balete Pass, fire a U.S. M-7 from its dug-in
position point-blank into a Jap pillbox 250 yards away." Beginning on 21
February, the 25th ID fought its way through the Caraballo Mountains
and finally took the pivotal Balete Pass on 13 May. More grim fighting
remained until the exhausted division was relieved on 30 June 1945 after
"165 days of continuous combat." The M7 can be seen as USA 4039654
indicating July 1943 production. Most photos of M7s in the PTO show them
installed with the US produced hinged armor plate modification, but
this unit, along with a few others of the 25th seen in period photos, is
noted with a field mod in which a plate (1) was neatly welded on. We
count seven men in this photo, although in the course of his narrative,
Major Curtis states, "Each M7 in addition to its normal 5 man crew
carried a radio operator equipped with an SCR-300."
In a written account of his service, Sgt. Donald C. Boyd driver
of #2 Section of Cannon Company, 128th Infantry Regiment, 32nd ID states
that the unit received "6 new M7s" on Hollandia while training for the
Leyte assault. The Priests replaced the 81mm mortars that the cannon
company had used in previous campaigns. This would have been in the
summer of 1944 after Hollandia had been captured and turned into a
naval, air and logistics base in support of the liberation
of the Philippines. The long serving veterans of the 32nd ID, who had
completed operations on Leyte around New Year's 1945, arrived on Luzon
on 27 January, eighteen days after the assault landings of the US Sixth
Army at Lingayen Gulf. The division was immediately deployed by I Corps
whose mission was "to expand the beachhead to the north and east, and
protect the Lingayen base." By 2 February the 32nd had captured Santa
Maria, the western terminus of the infamous Villa Verde Trail. US
planners did not anticipate that the Japanese would defend the Caraballo
mountains with such ferocity. It was expected that the 32nd would
quickly break through the passes and link up with the 25th ID attacking
north along Route 5. As it was, the "Red Arrow Division" fought itself
to exhaustion in the 4 months it took to clear the enemy from the Villa
Verde Trail. The photo is dated 12 April 1945 and captioned,"105mm self
propelled howitzer of the 126th Cannon Co, firing on Jap positions on
the Villa Verde Trail, Luzon, PI." At this time, the mission of the
126th IR was to attack and tie down the enemy positions on Yamashita
Ridge (in the background of the photo), which flanked the trail, so that
the 128th IR could take Salacsac Pass Number 2 without being subjected
to harassing fire from the dominating heights. The Pass was finally
secured on 16 April. In his account, Sgt. Boyd mentions that "The
engineers had scraped out a firing position for us" which was probably
similar to that seen in the photo. The Priest carries the name,
"Shiftless" and appears to have "Cn 3" painted on the right-side stowage
box. The M7's Registration Number can be read as USA 4038389 indicating
December 1942 acceptance. From that we would assume that the "folding
auxiliary armor plate" modification was retrofitted, possibly before the
Priest was shipped from the US. Naturally, the division's vehicles
would have been road bound in this type of environment, and the Villa
Verde Trail at the time has been described as "a goat path in the
clouds." The bulldozers of the 32nd ID's 114th Engineer Battalion became
high priority targets of the Japanese defenders. Sgt. Boyd notes that
while under fire, his M7 retrieved a bulldozer that had slid off the
trail. To their great credit, the engineers did all they could to
improve the trail to enable the movement of supply and combat vehicles,
up to and including medium tanks, specifically, a platoon of Shermans of
B Company, 775th Tank Battalion. One of their M4s, which appears to
have been left in place after it burned, is on display at the Mangili
Tindaan Historical Nature Park not far from the scene of our photo.
This Signal Corps photo is captioned, "Heavy Armor to the Pasig---U.S.
tanks proceed along Sasmarinas [sic] street in Manila toward the Pasig
River, where they will take up positions for the pounding of Jap
positions south of the river." Using "Google Street View",
Pierre-Olivier was able to determine that the photo was taken on the 200
block of Dasmarinas Street because the buildings on the right though
damaged at the time, are still standing. The swift advance of the 1st
Cavalry and the 37th Infantry Divisions caught the enemy off guard and
spared a good deal of the northern sections of Manila the ruination
suffered by the area south of the Pasig, which the Japanese turned into a
fortified zone that they were determined to defend to the last man. We
think that the M7s shown in the photo belonged to one of the cannon
companies of the 37th ID, since the 1st Cav. Div. does not seem to have
had had cannon companies until it was reorganized as an infantry
division at the end of the war. The official caption of this photo is
undated. However, the M18 Tank Destroyer in the background would lead us
to think that it might have been taken on 17 February 1945 as the AAR
of the 637th Tank Destroyer Bn reports "One section, 2d Platoon, Company
C in support of the 2d Battalion 148th Infantry [fighting on the south
side of the Pasig] placed 76mm fire on the SCIENCE and PHILIPPINE
HOSPITAL BUILDINGS, opening large gaps in the walls so that 105mm High
Explosive shells could be fired into the buildings with weapons of the
Cannon Company." There is some SC footage in which the lead M7 in our
photo is seen firing across the river and also shows that the Priest had
a Donald Duck cartoon figure painted on the side (inset). The M7 and
the Jeep in the photo can be seen with some sort of code "6429-S-20-22"
that we have not been able to decipher. We might venture a guess that
the M7s were part of the cannon company of the 148th Infantry Regiment,
37th ID which was engaged south of the river "in bitter hand assault
combat [and] drove the enemy from the Science Building on the Southeast
corner of Philippine General Hospital area by 1150 and secured the two
Eastern wings of the main Hospital building by 1330." As a matter of
minutia, we take this shallow pulpit M7 to be in the "grouser box mod 3"
configuration where the original small grouser box was replaced with
one that was somewhat larger, taller and notched. We
will try to get some comparative measurements in the future, but for
now, note that the 5-gallon jerrycan seen here, would not have been able
to fit inside the original grouser box.
Here
we have some more Signal Corps footage from the US
National Archives website. In it, the photographer, whose name appears to have been "Gae
Faillace", holds up an improvised clapperboard that shows "19 February"
consistently throughout the footage. With the unusual surname, we
believe the scenes must have been shot by Sgt. Gaetano Faillace, who is
reported to have been "General Douglas MacArthur's personal photographer
during World War II and the American occupation of Japan." Faillace
took the well-known "I have returned" photo of MacArthur wading ashore
at Leyte, 20 Oct 1944. However, it would appear that he was working with
a movie camera on 19 February. In any case, by that time, most of the
37th ID and the 1st Cav were fighting on the south side of the Passig
around the campus of the University of the Philippines. Some of the
armor had crossed the river as well. We wanted to show a couple screen
captures of an M7 that is featured in Faillace's footage about 5 minutes
in. On the left is a side shot where the M7 is firing at targets across
the river. This unit can be seen with the rear canvas cover frame
installed with crew gear hanging from it. Also visible is a knapsack
hanging off the right side of the M7. Based on that, we believe that
this is the trailing Priest seen in the previous still photo. Note the
little "stick figure" man painted in front of the star (inset). The
"little man" has been observed on M7s in two SC still photos dated June
1945, one of which identifies the unit as the 145th Infantry Regiment,
37th ID, which suggests that these M7s were in the cannon company of the
145th IR. In the screen capture on the right, it can be seen that some
plates (1), possibly hinged, have been added to protect the air
cleaners. This field mod is noted in a few SC photos of M7s identified
as with the 37th ID. The same "6429-S..." mystery code (2) appears to be
painted on the left rear fender.
Here we have front and rear views of an M7 which, according to the
caption, "plunged 150 yards down the side of a steep hill." No unit is
given, but the tactical markings on the upper rear hull plate can be
read as "6 63...CN 6" which we take to mean "6th Infantry Division, 63rd
Infantry Regiment, Cannon Company #6." The photos are dated 24 April
1945, and the captions state that it "took 8 days and several methods"
to retrieve the M7. From that we take it that this Priest was attempting
to support the 63 IR during its final attacks on Mt. Mataba, a key
objective on the formidable Shimbu Line, east of Manila. Mt. Mataba was
finally taken by converging assaults of the 1st and 3rd Battalions, 63rd
IR on 17 April. The souvenir history of the 6th ID notes that, "During
the final assault, the infantry was supported by self-propelled mounts
and tanks that were able to reach the area only by the herculean efforts
of the 6th Engineers in pushing the supply roads to the very summit of
the mountain." The track (1) on the left side is off the sprocket, but
otherwise the Priest doesn't appear to have been badly damaged and there
were no reports of casualties. This is one of the few examples seen in
PTO photos that is not installed with armor plate ammunition protection,
either by field expedient or from the US modification kit. The antenna
base (2) suggests that the M7 was equipped with a radio. Note that a
hand hold (3) has been retrofitted to the "awning" above the driver's
station. In the "Summary of Lessons Learned" section of their Operations
Report, the 63rd IR states "Cannon Company, equipped with M-7 mounts,
are much better suited for direct fire missions than for indirect. The
personnel of the company is not adequate for the establishment of Fire
Direction Center...and Forward Observer Parties. The 105mm gun on the
mount was found to be extremely effective when fired direct against
caves and entrenched positions." Because
of their vulnerable open tops, it was recommended that the M7s employ
the "shoot and scoot" tactic for which they were well suited, "only four
or five rounds" should be fired from a position, after which the
vehicle should be moved "slightly."
The 77th Infantry Division, veterans of Guam and Leyte, were the
first troops to engage in "Operation Iceberg", the codename for the
Okinawa Campaign. In order to establish an advanced naval base, the 77th
ID assaulted several of the Kerama Islands on 26 March 1945, a week
before the invasion of the primary target, Okinawa, on 1 April. "All
together, the 77th struck in six separate amphibious assault landings
and followed up with nine more to capture the islets and secure the
protected anchorage." Along with their landings at Guam and Leyte,
including their decisive end-run assault near Ormoc, this has to be some
kind of amphibious record. On 16th April, the division invaded Ie
Shima, and secured the island by the 26th, after which it became a US
air base, described by some as "an unsinkable aircraft carrier". The Ie
Shima operation was more or less forgotten in the shadow of the "Typhoon
of Steel" that was Okinawa, but the 77th suffered over 1100 casualties
including 217 KIA taking the small island. The photo is dated 31 May
1945, and captioned, "Shuri Okinawa...A self-propelled 105 mm Artillery
gun, bears the name of Ernie Pyle, in tribute to the beloved
correspondent who lost his life with the 77th on Ie Shima. The carrier
was on its way to the front when photographed." A few days after Ie
Shima, the 77th ID deployed to Okinawa and took its place on the front
lines, relieving the exhausted 96th ID. The 77th was known as the
“Statue of Liberty Division” and their insignia (inset) can be seen on
the helmets of some of the gunners. "Painting of the trapezoid on the
helmets was considered a special ceremony." Reading the Division
history, "Ours to Hold it High", and its Okinawa Operations Report, one
gets the impression that the regimental cannon companies were entirely
equipped with M8 Howitzer Motor Carriages during their campaigns up to
this time. "The SP Gun, 75mm, M-8 was used as well as the M-18 [just
prior to the Okinawa Campaign, the antitank company was equipped with
eight]. Both weapons were used extensively for sealing caves and, in
addition, performed valuable direct support fire for the infantry. The
M-8 was used for both direct and indirect firing and both weapons
delivered flanking support fire and overhead support fire from positions
on high ground." The division preferred "a vehicle of less than 20
tons" for the terrain conditions under which it operated and both the M8
HMC and the M18 TD fit the bill. The first mention of the use of M7s
that we have seen in the 77th ID records is from "Second to None", the
history of the 305th Infantry Regiment. On 17 May 1945, "So far as we
have been able to learn, the 305th in conjunction with the 307th was the
first organization in the Pacific Area to make a night attack against a
strongly held Japanese position...The RCT received excellent support
from our light, medium, and heavy artillery, our M4s, M7s, M8s, M18s,
and flame-throwing tanks." The Division must have had some experience
with the M7, but rejected it for future operations, "The Carriage, Motor
105mm How, M-7, has a turret too open and is too heavy to provide the
flexibility desired." In any case, pending further research, we would
guess that the 77th ID's cannon companies received a few M7s as
replacements while fighting on Okinawa, and "Ernie Pyle" was likely one
of them. Note the added Browning .30 caliber machine gun with shield.
The angle of this photo permits us to see that the grouser boxes are in
"mod 2" configuration with the retaining bars of the outer box running
through the little footman loops.
Period photos suggest that M7s were first used by the US Marine
Corps on Okinawa, site of "The Last Battle." The III Amphibious Corps
selected the 1st and 6th Marine Divisions for the 1 April 1945 assault,
while the 2d Marine Division served as a floating reserve. "Marines in
the Victory on Okinawa", part of the USMC 50th Anniversary commemorative
series, states that "The Marine divisions preparing to assault Okinawa
experienced yet another organizational change, the fourth of the
war...Although the "G-Series" T/O [Table of Organization and Equipment]
would not become official until a month after the landing, the divisions
had already complied with most of the changes. The overall size of each
division increased from 17,465 to 19,176...The most timely weapons
change occurred with the replacement of the 75mm "half-tracks" with the
newly developed [sic] M-7 105mm self-propelled howitzer--four to each
regiment. Purists in the artillery regiments tended to sniff at these
weapons, deployed by the infantry not as massed howitzers but rather as
direct-fire, open-sights "siege guns" against Okinawa's thousands of
fortified caves, but the riflemen soon swore by them." The Marines and
indeed the entire Tenth Army were taken aback when the landings went
virtually unopposed. Almost immediately, the 6th Marine Division was
ordered north to capture the Motobu Peninsula for starters, with the
ultimate goal of conquering all of northern Okinawa, fully 2/3rds of the
island. The photo above is captioned "Tank borne infantry Marines of
the Twenty-Ninth regiment [6th MarDiv] race for the town of Ghuta [sic]
to occupy the Okinawa village before the Japanese forces take it." No
date is given, but we believe that the caption writer was actually
referring to the town of Chuta, which the 29th Marines took on 6 April.
Both M7s can be seen with shallow pulpits which we take to indicate 1942
production, so not exactly "newly developed." It is thought that the
6th MarDiv drew their Priests around the time that the division was
activated on Guadalcanal in September 1944. We suspect that the extended
end connectors, folding armor modification and the track link "armor"
may have been retrofitted at that time. The lead M7 is noted with an
antenna suggesting that a radio was installed. Marine Divisions did not
have cannon companies with 6 M7s like many Army Infantry Divisions.
Rather, 4 were placed in each of the regimental weapons companies. Note
that the rearmost "taxi" in the column is a Sherman tank. It would
appear that shortly after snapping this M7 photo, the photographer, PFC
Robert Keller, took the iconic image (inset) of exuberant Marines
greeting him as they passed.
This USMC photo is simply captioned "M-7 tank destroyers are used as
artillery. May 12, 1945 Okinawa" and PFC Bob Bailey is listed as the
photographer. Bailey was "embedded" with the 1st Marine Division and 2
days earlier had photographed PFC Paul E. Ison, a demolitions man with L
Company, 3rd Battalion, 5th Marines as he sprinted across what came to
be known as "Death Valley" during the bloody struggle for Wilson's Ridge
from the 3rd to the 11th of May. After the "Flag Raising at Iwo Jima",
Bailey's photo (inset) is probably the most well-known WW II USMC image.
From Bailey's photographer credit, we identify the M7s as belonging to
one of the regimental weapons companies of the 1st MarDiv. The 12 May
date would suggest that the Priests were in support of the 7th Marine
Regiment who relieved the exhausted 5th Marines, and captured the next
objective, Dakeshi Ridge on the 12th after 2 days of extremely costly
assaults. Like many USMC AFVs, these M7s are retrofitted with track
"armor." Again, we see 1942 era shallow pulpits. We might mention here
that ALCO produced 615 M7s in November and 566 in December 1942. These
were by far the highest production months and represent fully 1/3rd of
the company's total output of 3314 units from April 1942 through October
1944. Both have antennas which are noted to be installed on US Priests
far more often in the PTO. Both can be seen with forward wading stacks.
The "Deep Water Fording" kit produced in the US starting in late 1943
provided a forward stack to cover the air intake on M4 and M4A1 (radial)
Shermans along with a rear stack. However, on the M7, only a rear stack
was provided. The intakes on the M7's engine deck were simply sealed up
according to both the 1944 and 1945 Technical Manuals. The stacks in
the photo look like ones from the US kit, so perhaps the Marines adapted
the M4/M4A1 kits to fit on their M7s? Or an alternate type was made in
the Pacific Theater, possibly in Hawaii?
For the planned invasion of Japan, it was recommended that Infantry
Division cannon companies be equipped with "M7 Series (or M37) 105 MM
How, Mtr Carriage." This particular document does not specify the use of
Ford engines (M7B1s) although that was the case with the Shermans (M4A3
with wide tracks) slated for "Operation Olympic." We would note that
there is some film footage of the 3rd Marine Division training with
M7B1s (inset) on Guam in late May 1945. They were scheduled to assault
Kagoshima, Japan on X-Day along with the 2nd and 5th MarDivs. At any
rate, despite its "Substitute Standard" classification, the M7 series
continued in service for a number of years after WW II. Here we see a
Priest performing the post war duty of "turning swords into
ploughshares". After the surrender of Japan, a number of US Divisions
occupied the country. One of their assignments was to destroy Japanese
military equipment. The photo shows "The sole Ki-78 [prototype] being
crushed by American forces at Gifu Air Field, after the war, in
1945." The 25th Infantry Division arrived in Japan in November
1945, and the Gifu prefecture was the responsibility of its 27th
Infantry Regiment. Earlier
we featured a photo of USA 4039654 of the 25th Infantry Division in
action on Luzon in April 1945 and noted that it had a field modification
in which a plate was neatly welded on. The M7 "demolition
vehicle" appears to have a similar mod (1) and it can be seen that it
extended across the rear (2) of the fighting compartment. Another field
mod seen in wartime photos of a few 37th ID M7s is the additional
protection for the air cleaners (3).
British Use in China-Burma-India [CBI] Theater of Operations
Earlier,
we cited an April 1943 Munitions Assignment Board document that had it
that 84 M7s were on the way from the US to India. We suspect that this
may have been the total number shipped. While the IWM's collections
include a number of photos and films showing M7s serving in Burma in
February and March 1945, we have not found much detailed information
about the employment of Priests in the CBI. It would appear that their
use in combat was limited to the 18th Field Regiment (Self-Propelled),
Royal Artillery. Originally a towed artillery regiment that fought with
the BEF in France, the unit was evacuated from Dunkirk in 1940.
Subsequently replenished, in February 1941 it was restructured from two
to three batteries (the 59th, 93rd and 94/95th Batteries), before being
transferred to India, arriving in Bombay in November 1942. According to
the "The Royal Artillery 1939-1945" website, the regiment became
self-propelled in December 1943 when it was authorized "24 x 105mm Self
Propelled M7 Priest, 10 x Sherman Observation Post." The same source
states that in January 1945, its vehicle strength was reduced to "16 x
105 mm Self Propelled M7 Priest", which seems significantly
under-strength, but perhaps reflects the limited number of operable
Priests available in theater at the time, or the maximum number that the
Army could support with 105mm ammunition during the upcoming campaign
in Burma. The above photo was taken on 7 March 1945, and shows S-215863,
“DEEPCUT” of D Troop, 93 Battery. We can only assume that this vehicle
was named after the village of Deepcut in Surrey, as some of the other
Priests of the regiment are seen with the names of other British
villages, such as Dunkirk, Docking and Chudleigh. All of the members of
the crew are wearing the standard British issue WWII Bush Hat, pinned up
on one side, and while this headgear is typically associated with
Australian soldiers, the “slouch hat” was also worn by numerous British
units, and we would point out that no Australian Army troops served in
the CBI. The "deep" pulpit and the "plain" sprocket suggest that this
was a 1943 production M7, and likely factory installed with the canvas
cover support frame modification. The recuperator housing appears to
have had the hemp rope wrap-around treatment covered over with a piece
of fabric. Other IWM photos of "DEEPCUT" show the M3 Grant type sand
shield completely intact on the left side. Courtesy of Imperial War Museum Photo
SE3366.
In "My Burma
Campaign"
Rex Wait describes the regiment and its mission, "...equipped with the
American 105mm howitzer on a Sherman tank chassis...At the time we were
sent into Burma, in December 1944, I was a humble subaltern, the Troop
Leader of Fox Troop, 94/95 Battery. Being something of an oddity, our
Regiment was not assigned to any particular Division. It came directly
under the Brigadier, Royal Artillery, at 14th Army H.Q., and we wore
the 14th Army flash on our shoulders. The Regiment could thus be made
available to support the armoured units of any of the Brigades in the
Divisions of 33 Corps and 4 Corps as the Army Commander might require."
As the sole self-propelled artillery unit in the CBI, the regiment was
a 14th Army asset, and its batteries were individually seconded out
amongst the army’s brigades and divisions as required. The above
photo shows a Priest of the regiment headed for Rangoon, after the city
had fallen according to the undated Office of War Information caption,
"Allies in Rangoon. Climax to the brilliant achievements of Indian and
British troops in Burma, was the fall of the capital, Rangoon. Smashed
and disorganized in their flight south, the Japanese gave up the city
without resistance." In conjunction with the attack of the 14th Army
from the north, the Allies launched Operation Dracula, an airborne and
amphibious assault on the city. Heavy resistance was expected from
"a deeply entrenched Japanese "suicide garrison"" but the disorganized
enemy evacuated Rangoon, and the 26th Indian Division liberated it
without a fight on 2 May 1945. The 14th [XIV] Army formation marking
(inset) can be seen on the Priest's upper rear hull plate.
Many of the regiment’s vehicles display names beginning with the
troop letter on the hull side and a close examination of the photo
appears to show this M7 to have a name beginning with the letters
"CE...", hence we believe it served with C Troop, 93 Battery. The first
part of the WD Number can be read as "S-215XXX", so in the same range
as “DEEPCUT”. Like “DEEPCUT”, it strikes us as
a 1943 production M7. Neither is seen with the added ammunition
protection, either done in the field or from the US modification kit.
US use in Korea

The photo above is dated 23 April 1951 and captioned, "Elements of the
19th Inf Regt, 24th US Inf Div and a tank of Co D, 6th Armored Bn
attached to the 24th US Inf Div move into new positions in a
counter-offensive to the enemy's attempt for a push south of the 38th
Parallel in Korea." The Korean War began on 25 June 1950. The first 7
months can be thought of as the "active" period of the war,
characterized by the UN retreat to the Pusan Perimeter, the Inchon
landing and breakout in mid-September, and the "bug out" from North
Korea in the face of the Chinese intervention and attack in November.
After that, there were a series of inconclusive offensives and
counteroffensives, followed by a bloody stalemate in which the conflict
ebbed and flowed around the 38th Parallel. Oddly, the M7 series does not
seem to have been employed in Korea until the Spring of 1951. Indeed,
the photo above is the earliest dated "combat shot" we have found. The
caption is somewhat baffling as it identifies the M7B1 as a "tank" of
"Co D, 6th Armored Bn." The writer was likely referring to the 6th
Medium Tank Battalion, which was detached from the 2nd Armored Division
at Fort Hood and arrived in Korea in August 1950. After a period of
organization and combat readiness training, it was assigned as the
organic tank battalion of the battered 24th ID, the first US Army unit
rushed from Japan to Korea after the start of the war. The 6th MTB was
the first to deploy with the "new" M46 Patton Tank which was basically
an M26 Pershing conversion rebuilt with an 810 HP engine, new
transmission, new gun with bore evacuator, and improvements to the
suspension. On 17 September 1950, the 24th ID's "War Diary and Command
Report" lists the 6th MTB's AFV holdings as 72 M46s, 6 M45s, 2 M24s
(light tanks) and 6 M32s (tank recovery vehicles). The M45 was the 105mm
armed variant of the M26 Pershing, intended to replace the
M4A3(105)HVSS Sherman in the US Army inventory at the end of WW II. The
24th ID records mention the 6th MTB's "Assault Gun Platoon" on numerous
occasions. We believe that the M45s were in the Assault Gun Platoon of
the 6th MTB's Headquarters Company as authorized in a 1949 Medium Tank
Table of Organization and Equipment, the last US Army TO&E that
included 105mm Assault Guns. This configuration appears to have been
unique to the 6th MTB, that is, we don't find evidence that any of the
other tank battalions that deployed to Korea had Assault Gun Platoons.
There are a small number of Signal Corps photos that show M45s with
tactical markings of the HQ and Service Company, 6th MTB fording the Geumho River at
the start of the breakout from the Pusan perimeter in mid-September
1950. In addition, a 1951 Operations Research Office Report entitled
"The Employment of Armor in Korea," has it that a total of 8 M45s were
"fielded" in Korea, with all "Lost" by 21 January 1951. There is no
mention of the use of M7s in the scant records of the 6th MTB that we
have searched, but we might theorize that they replaced the "lost" M45s
in the Assault Gun Platoon. Note the "tiger face" painted on the right
front fender. Before the start of "Operation Ripper", the US offensive
of early March 1951, these sorts of animal faces were instructed (or
perhaps simply authorized) to be painted on the fronts of US tanks in
Korea. It was thought that the sight of such beasts would scare and
demoralize the superstitious enemy. As for other markings, the Priest
appears to have "Annie Oakley" painted under the pulpit and "A24"
painted on the pulpit. To our eyes, it looks like some other tactical
markings were scrubbed from the pulpit and a "6" was painted over top.
Another photo of this scene shows another M7B1 with "tiger face" and "2"
painted on the pulpit. If any readers can shed light on the unit of
these M7B1s, we would be pleased to have a report.
We can document that at least four National Guard Armored Field
Artillery Battalions equipped with M7s were shipped to Korea in early
1951. Most of the information comes from oral or written histories of
individual soldiers. For instance, Sgt. Conrad Grimshaw of Service
Battery of the 213th Armored Field Artillery Battalion wrote a memoir about his 6 months' service in Korea. The 213th "Mormon
Battalion" was composed of guardsmen from small towns in southern Utah.
They shipped out in late January 1951 aboard the USNS General M.C.
Meigs. Grimshaw reported, "Aboard the ship were the following units: 213
Armored Field Artillery Battalion; 300 Armored Field Artillery
Battalion; 987th Armored Field Artillery Battalion" among others. These
three battalions were initially equipped with M7s, and the evidence
suggests that they brought their Priests with them. The Meigs arrived in
Pusan in mid-February and the 213th AFA Bn set up in an assembly area
nearby where the unit continued to organize and undergo combat readiness
training. In early April, the battalion was shipped to Inchon by LST
and finally deployed on the front lines near Kapyong. Battery B fired
the 213th AFA Bn's first rounds in combat on 22 April at the start of
the Chinese Spring Offensive, 22-27 April 1951. In this action, the
213th was placed in support of a number of the hard-pressed units of the
IX Corps including the 27th British Commonwealth Brigade made up of
British, Canadian and Australian troops. UN forces gave way at first and
Sgt. Grimshaw reported that during the "bug out", one howitzer was left
behind when it slipped off the road and could not be recovered. The
Signal Corps photo above is dated 25 May 1951 and captioned, "Men of the
1st howitzer platoon, B Btry, 213th Armd FA, IX Corps, fire into enemy
positions north of KapYong, Korea." This M7B1 is installed with the
armored exhaust deflector (1) which we suspect was retrofitted by
modification kit. A name beginning with "Babe" and a female figure can
be seen painted on the pulpit. The Priest is "ramped up" to obtain a bit
more elevation. GI snapshots show that the 213th had a mix of M7B1s
such as "Babe" along with M7s, including one or two Federal Machine M7s
with E9 suspension. The Chinese/North Korean offensives of April and May
ultimately failed, and UN forces went over to the offensive in late
May. Once again, the 213th AFA Bn found itself back in the Kapyong
Valley which is reflected in the photo. On 27 May 1951, Headquarters and
A Battery were attacked by a "force of more than 4,000 Chinese" who had
been bypassed by the UN offensive and were attempting to retreat back
to their own lines. The 240 Utahns somehow managed to hold off the
Chinese throughout the night, and early the next morning the unit sent
out a combat patrol "using one of its self-propelled artillery guns as a
tank." Ultimately, this action "resulted in the capture of 831
prisoners and inflicted hundreds of casualties on the enemy." Incredibly
the gunners suffered "no significant friendly casualties." HQ Battery
and A Battery were awarded the Presidential Unit Citation. The events of
this epic stand are related by a number of the participants in the
documentary film "Miracle at KapYong: The Story of the 213th." (link) In
October of 1951, the 213th AFA Bn turned in its Priests and was issued
"155mm trail models pulled by tractors." Sgt. Grimshaw reported that
this was due to a shortage of 105mm ammunition. In May 1953, the unit
was issued some of the massive 240mm howitzers and "After that, they
fired both 155mm and 240mm guns."
The 300th Armored Field Artillery Battalion was a Wyoming National
Guard unit that was also shipped to Korea aboard the General M.C.
Meigs, arriving in mid-February 1951. After a period of combat
readiness training, the unit was deployed on the front lines and
conducted its first fire mission on 15 May in support of the 2d
Infantry Division during the Battle of the Soyang River. For the next 7
days, the "Cowboy Cannoneers" "delivered devastating artillery
fire...inflicting thousands of enemy casualties." In this its first
combat action, the 300th was awarded the Presidential Unit Citation.
The caption of the photo is dated 1 July 1951 and is entitled
"Extending Wyoming's Boundaries." The 300th AFA Bn's commanding
officer, Lt. Col John Raper is shown posing with a Wyoming Highway
Department road sign that "his men spirited out of the States. The sign
has followed the "Cowboy Artillery" all over Korea. In the background,
the crew of a 105MM self-propelled howitzer prepares to fire a
mission." The "bucking horse and rider" as outlined on the highway
sign, is basically a symbol of Wyoming that was first placed on
automobile license plates in 1936. It can be seen painted on the
Priest's upper rear hull plate (arrow). Possibly based on this
photo, the highway signs are specially made for units of
the Wyoming National Guard to take with them wherever they
go. The M7B1 carries the name "HELL BOUND" and the Registration
Number can be read as USA 40152831 (December 1944 production) in
another SC photo of this scene (inset). According to that photo's
caption, "HELL BOUND" was with B Battery, and the 5 men pictured
servicing the piece were from Cody, Wyoming. No location is given in
the captions, but based on the date, it is thought that the 300th would
have been in the area around the Hwacheon Reservoir and Yanggu firing
missions in support of the 7th ROK Division or 1st Marine Division on
"Line Kansas" just above the infamous 38th Parallel. According to the Army Historical Foundation, "The 300th remained in Korea for the remainder of the war,
taking part in battles at the Punchbowl, Bunker Hill, Bloody Ridge, and
Heartbreak Ridge. In the final weeks of the conflict, the 300th earned a
second Presidential Unit Citation for actions at Kumsong. In all, the
300th fired 514,036 105mm howitzer rounds in 805 days of combat." From
"fired 514,036 105mm howitzer rounds" we take it that the unit retained
its Priests throughout its service in Korea. A few GI photos suggest
that, at some point, the 300 AFA Bn was issued some "high angle fire"
M7s as replacements.
The 987th Armored Field Artillery Battalion, an Ohio National Guard
unit, was the third AFA Bn listed as having been transported to Korea on
the General M.C. Meigs. Warrant Officer James C. Neely wrote a memoir
describing what happened when the 987th was ordered forward to support a
reconnaissance in force by the 6th Republic of Korea and the 1st Marine
Divisions. It is not clear if this was the unit's combat debut, or if
they had been involved in earlier actions, but on 22 April 1951, the
first day of the Chinese Spring Offensive, the 6th ROK Division routed
under the weight of the massive attack which left the 987th AFA Bn
exposed in an untenable position "trapped on a one-way road" between the
towns of Sachang-ni and Chunchon-ni. In the pandemonium of the ensuing
"bug out", "the battalion was unable to extricate...nine guns, so the
officers ran these over the cliff into the river gorge, preventing the
Chinese from utilizing these as captured artillery pieces". Neely states
that the battalion's surviving M7s supported the 1st Marine Division in
a rear-guard action and "Hold Mojin bridge until all elements are
crossed." The 987th continued to use M7s until they were reportedly
replaced with M43 8-inch self-propelled howitzers in October 1952. An
item in a "Combat Information Bulletin" submitted by the 987th and dated
September 1952 is headed "Use of Modified 105-MM Howitzer" and states
"Approximately 75% of the fires of the battalion were high-angle fire.
No difficulties were experienced using the modified 105-mm howitzer,
self-propelled, M7 (with well). Frequent shifting of the carriage is
necessary because of the limited traverse at high angles". The unit,
which had lost 9 or 10 of its original M7s, appears to have received
some replacements that were rebuilt at the Tokyo Ordnance Depot and
specifically modified for high-angle fire. The insignia of the 987th, a
red bull on a yellow triangle (inset) is noted to have been painted on
the sides of their M7s. This Priest can be seen as USA 4040215,
indicating that it was produced by ALCO in October 1944, their last
month of M7 production. Note the fitting on the gun cradle (arrow) which
we take to be a recognition feature of an M7 modified for high-angle
fire as explained in the next caption. This Priest has also been
retrofitted with extended end connectors. The louvers on the stowage box
seen here are not in the standard 1944 M7 configuration, suggesting
that the original may have been damaged and replaced, perhaps at the
TOD. James Neely's memoir includes an internal link to the personal
photos of MSgt John Engel of B Battery which appear to have been taken
throughout 1952 in the central sector of the front. A pair of high-angle
modified M7s named "Brown Noser" and "Brown Bomber" are featured. In
addition, there is a photo of an M43 HMC that is dated "Oct 1952." Photo
courtesy of the Ohio National Guard Heritage Center.
The photo above is dated 15 March 1951 and simply
captioned, "A self-propelled 105MM Howitzer M7 modified to permit high
angle fire." No location is given, although we suspect the photo may
show the pilot model on a firing range, possibly in Japan. Note that the
gun travel lock (red arrow) has been modified and repositioned from the
fighting compartment to the front of the vehicle. Two male fittings
(blue arrow) have been added to the gun's cradle to secure the travel
lock. It is thought that the rear half of the false floor in the
fighting compartment was removed in order to facilitate high angle fire.
That might explain the meaning of "with well" in the previous caption.
Of course, this would have necessitated a rearrangement of the
ammunition stowage. The caption does not include the nomenclature
"M7J1", but we would assume that is what this unit is - an M7 rebuilt
and modified for high angle fire at the Tokyo Ordnance Depot. If they
can be seen in photos, we take the gun travel lock on the front and the
fittings on the gun cradle to be recognition features of the high-angle
modification. This is an early production M7 with the side hinged
stowage bins. We assume that it was retrofitted with the folding armor
and canvas cover mods, probably during WW II. It can be seen that the
original small grouser box was replaced with the one that was somewhat
larger and taller and "notched". This M7 would have been built with a
siren, not the automobile type horn seen here. The M4 bogies with the
"final" type of track skids were likely retrofits as well. The placement
of the stars appears to have been typical of M7s rebuilt by the Tokyo
Ordnance Depot.
We do not know when the nomenclature "M7J1" was adopted but assume
that the "J" refers to Japan. The Signal Corps photo above is dated 29
September 1954 and captioned, "Combat vehicle storage in Tokorozawa
Ordnance sub depot storage area in Japan." The sign on the left reads
"Carr Motor M7J1 105mm How" (inset) and there are at least 8 Priests in
the shot. We suspect that the 105mm guns are attached to the front
travel locks. All of the M7s appear to have Extended End Connectors
installed, which, judging by their presence in period photos, may have
been a requirement for M7s rebuilt at the Tokyo Ordnance Depot. The unit
in the center can be seen as USA 40190456 which indicates that it was
produced by Federal Machine & Welder in May 1945. We consider the
flat fender braces and the "E9 hole" in the sprocket to be recognition
features of FMW M7s. Thus, we take it that there is another example off
to the right. Note the size and placement of the stars with a small
divergence on the shallow pulpit jobs. The Ordnance Technical Committee
recommended that the M7 and M7J1 be declared obsolete on 20 April 1955.
In the discussion, it was noted that, "The M7J1, a modified M7
authorized in FECOM [Far East Command], was later disapproved by OCAFF
[Office of the Chief of Army Field Forces]. The vehicle incorporated an
emergency fix to allow for high angle fire." The number of M7J1
conversions is not given, although the doc does state that there were
1254 M7s and M7J1s on hand in the US inventory worldwide, with most in
depots in "Unserviceable" condition. Although the OCM does not express
it outright, the implication is that all M7J1s were converted from M7s,
that is with radial engines. We wonder about that since we have shown
that there were a number of M7B1s deployed to Korea and can't help but
think that some might have been shipped to the Tokyo OD for rebuild. Of
interest is that the M7B1 was not being declared obsolete at this point.
Instead, it was recommended that the remaining M7B1s be rehabilitated
and rebuilt for high angle fire to M7B2 standard. This appears to have
been done to satisfy US Army requirements while waiting for the long
delayed T98E1/M52 105mm Self-Propelled Howitzer to enter production.
The 176th Armored Field Artillery Battalion was a Pennsylvania National
Guard outfit that had only 6 weeks of training at Camp Carson, Colorado
before being shipped out to Korea. The 176th arrived at Pusan in
mid-February 1951 and underwent an additional 5 weeks of training at a
nearby camp, after which it was shipped by LST to Inchon where it was
attached to the 25th Infantry Division. According to an account by Capt.
M. W. Goss, battalion S-3, "On 7 April 1951, the battalion fired its
first round of 105mm in anger. They were attached to the 25th Division,
reinforcing the fires of the 159th FA Bn in support of the 24th Infantry
regiment." If the date is accurate, that would be the earliest use of
the M7 in Korea we have encountered. The battalion supported the 25th ID
and the 1st ROK ID throughout the Chinese Offensives of April and May
1951. It would appear that, like the 300th AFA Bn, the 176th fought with
Priests to the end of the conflict. The photo is dated 17 July 1953,
which was 10 days before the armistice/cease fire. The caption reads,
"Tank Retriever towing self-propelled gun carrier that is being
reclaimed by "A" Btry, 176th FA Bn, Eighth Army, Korea. Equipment was
destroyed prior to evacuation of area during heavy fighting with Chinese
Communists in Korea." We've zoomed in on this M7 which can be seen with
tactical markings of B Battery, 176th AFA Bn. The Registration Number
can be read as USA 3034675 indicating an M7 produced in August 1942. The
early side hinged stowage bins are still present although they have
been topped with the "blanket baskets" typical of 1944/1945 production.
The placement of the stars and the addition of EECs strike us as
indicative of a Tokyo Ord. Depot rebuild job. We would speculate that
this M7 and other AFVs of the 176th AFA Bn were abandoned during a "bug
out" when they came to an impassable, rain swollen creek. This would have been at some point between 13 and 20 July 1953
during the final Chinese push of the Battle of the Kumsong Salient. In a recorded interview with
his son in 2004, Corporal William Didycz says of the debacle, "We had
lost everything: tanks, trucks, tents, everything but our skins, the
clothes on our backs, and our rifles." Cpl. Didycz, who stated that he
arrived as a replacement two days before the start of the final Chinese
Offensive (ca. 11 June 1953), describes the M7s in an interesting way as
"105 mm howitzers [that] were mounted on tank chassis. Howitzers are
unique in that they could fire at a high trajectory, like over hills
that Korea was full of. Being mounted on tank (M4A3 E8) [sic] chassis
meant that we were mobile over terrain that trucks pulling howitzers
couldn't negotiate. It was a great idea for a tactical weapon, but a
lousy one for the men in it. Tanks themselves were death boxes; this was
a death box without a lid." He goes on to relate how the battalion was
quickly re-equipped in Seoul, "I couldn't believe that they had more of
those ancient M4A3's [sic], but sure enough, they did. I was given a new
deuce and a half (2-1/2 ton truck) loaded with supplies, and in short
order we had formed a convoy of tanks, trucks, jeeps, and half-tracks
and were on our way back north." We would observe that the gunners in
the various accounts consistently refer to their M7s as "tanks."
Here we have a photo of another M7 of the 176th AFA Bn being recovered.
This Priest looks to be damaged but certainly not "destroyed" as
written in the caption. Since no towing cables are visible, this unit
appears to be moving under its own power. From this angle, the 1944 M7
configuration of the engine deck can be seen. Further inspection shows
louvers on the sponson stowage box. The high mounted grouser box is
just visible on the glacis, which indicates a unit with "low"
headlights. This combination of features surely identify this Priest as
a 1944 production ALCO M7. However, an interesting oddity is visible in
this photo - a notched upper rear hull plate, typical of 1942/43
production M7s. As mentioned previously, the notch was eliminated from
the 1944 design and the upper rear hull plate went straight across. We
have shown that some surviving 1944 M7s are seen with upper rear hull
plates with the notches filled in, which appears to have been an effort
to use excess parts from 1942/43 production. We have zoomed in on the
engine deck in the inset, where it is possible to see the filler pieces
used to blank off the rectangular holes of the "fuel tank compartment
ventilating grilles" of 1942/43 production M7s, so the change was made
there. We might hazard a guess that the notched upper rear hull plate
slipped through the cracks when this M7 rolled off the line at
ALCO. Some 105mm rounds can be seen stowed in a horizontal
orientation (red arrow) on the left-hand side and there is a vertical
metal plate visible, which we assume was installed to prevent the
rounds from sliding forward. We believe that this was part of the
reconfiguration of the ammo stowage when an M7 was converted for high
angle fire. Although we can't document it, we would guess that most or
all of the M7s rebuilt at the Tokyo Ord. Depot would have been modified
for high angle fire, simply because that was what was wanted/required
in the mountains of Korea. It is mentioned that the Tokyo Ordnance
Depot was almost self-sufficient and was able to provide 75% of the
materials it needed in house. Another possible explanation for the
notch may be that the original upper rear hull plate was damaged and
was replaced by another plate cannibalized from a 1942/43 M7. We would
note that this M7 is not installed with the Barber-Colman type exhaust
deflector or its fittings as used on 1944 M7s, but appears to have the
earlier curved exhaust deflector. In any case, a pair of Tank Recovery
Vehicles, one radial engine M32B1 and one Ford engine M32B3, can be
seen involved in the recovery operation. It is thought that the armored
field battalions would have been equipped with at least two such
retrievers in the Service Company. The Chinese and North Koreans became
masters of the art of infiltration, and artillery units were prime
targets of their attacks since they accounted for perhaps as much as
3/4 of the casualties they suffered. An 8th Army Command Report states
that "the enemy infiltrated to the rear of the artillery positions and
placed a fire block on each side of the road, making it impossible for
the artillery to move its vehicles and weapons through the road. As of
May 1951, "The loss by US Artillery units has been 212 weapons and by
Korean [ROK] Army units 196 weapons." Since the front lines in Korea
were for the most part not continuous, UN artillery units had to
learn the hard way how to "fort up" and provide for their own defense.
This Signal Corps photo is dated 28 May 1950, about a month before
the start of the Korean War and is captioned, "Red River Arsenal Helps
on MDAP [Mutual Defense Assistance Program] Parking Area: One of the
vast parking areas of the vehicles that were returned to the United
States upon cessation of hostilities of World War II. The vehicles have
been "cocooned" and are periodically inspected. From these "stockpiles"
the vehicles go through the process of being torn down and completely
rebuilt. When leaving the paint shop after their final coat of paint,
the vehicle is as serviceable and complete as a new one." Red River Army
Depot is located near Texarkana, Texas and according to the US Army
webpage, "In 1946, the depot was assigned the responsibility of storing
combat vehicles returned from the war. Over 58,000 vehicles were stored
on the depot and is believed to be one of the largest numbers ever
stored at one installation." The Mutual Defense Assistance Act was
signed into law on 6 October 1949 "To promote the Foreign Policy and
provide for the defense and general welfare of the United States by
furnishing military assistance to foreign countries." The act was
primarily intended to provide assistance to members of the North
Atlantic Treaty Organization which was established in April 1949. The
treaty provides that each member state will come to the defense of any
other member states that are attacked by third parties. MDAP was
expanded to include assistance to other states whose defense was deemed
important to the defense of the US. In the photo, the M36 series Tank
Destroyers appear to be sealed or "cocooned" but the first two rows of
Priests, which look to be M7B1s, can be seen with fighting compartments
open to the weather, which would likely have made them much more
difficult to refurbish. Some of the units in the far-right rows may be
sealed. The high headlights and a few shallow pulpits visible would be
indicative of M7s. The list is far from complete, but countries known to
have received M7 series HMCs as MDAP include Belgium, France, Germany,
Italy, Turkey and Yugoslavia. The MDAP documents we have scanned only go
up to 31 January 1954, and as of that date, 561 "Carriage, Motor,
105mm, How. (all models)" had been shipped to the above-named countries. Most
would have to have been M7 series, since the M37 HMCs meant to replace
them were only produced in small numbers.
The
photo above is dated 6 September 1955 and has the brief caption,
"Repaired vehicle park at Tokyo Ordnance Depot, 8160th AU [Army Unit],
Tokyo, Japan." There is what we take to be a Federal Machine and Welder
M7 in the center of the photo. The vehicles can be seen sealed for
overseas shipment such as was done at US Tank Depots. Note the cut down
HVSS Sherman being used as a tractor. Starting in 1948, the Far East
Command in Japan hired thousands of workers to repair and rehabilitate
"Mountains of materiel collected from the battlefields of Guam, Saipan
and Okinawa" as part of "Operation Roll Up." The salvaged guns,
ammunition, trucks and Armored Fighting Vehicles may have provided the
margin that saved UN Forces from defeat in the first 7 months of the
Korean War. For its part, the Tokyo Ordnance Depot, which grew to be a
huge, and pretty much self-sufficient operation, rebuilt hundreds of
AFVs during the course of the Korean War. It was reported that the Depot
could turn out two rebuilt Patton Tanks a day at a cost of $700 each.
After the truce, the depot repaired and rebuilt tanks and other AFVs
that were supplied to recipients of MDAP.
We don't have the MDAP figures for the Republic of China (Taiwan), but
the island nation has received a good deal of military equipment from
the US since the 1950s. The photo which was taken in Taipei during the
"Double Ten" [October 10] Parade in 1956 shows a Federal Machine and
Welder M7 sans EECs. The front mounted gun travel lock and the fittings
on the gun cradle suggest that it had been converted to M7J1 in Japan.
FMW M7s were produced from March to July 1945 and would have been built
with the later E8543 "sharp nosed" type differential housings, but this
unit has had that replaced by an earlier E4186 diff with a step in the
middle that is typical of the M10 Tank Destroyer series. A
bit of a 1942/1943 production M7 can be seen in the photo as well. This
unit also had its original differential housing replaced, in this case
with an E8543 "sharp nosed" diff. Photo courtesy of https://taipeiairstation.blogspot.com/2012/04/double-10-parade-taipei-1956.html
We believe that there may be a surviving M7J1 conversion on display in
Taiwan at the Armor Academy and Military Base, HuKou, Hsinchu. We base
that ID on the hinge fitting visible on the front deck, which was for
the front gun travel lock. Indeed, there is an older photo of this M7 on
the net which shows the gun travel lock still installed. The cradle of
the 105mm gun appears to be made of lumber, so no male fittings there.
The Priest can be seen as another example with what we call, for want a
better term, "melted rivets" on the lower hull. The E8543 differential
housing is noted to be the early type with the cast in steps. So, this
may be an early 1944 production (March or April) ALCO M7, like SN 2843
at Ft. Sill. There
are some weld scars on the side which may or may not have been for a
retrofitted side door? Our Canadian friend, Jim Goetz, has a "bucket
list" goal of seeing all of the surviving Shermans and variants in the
world, and there is what appears to be an ALCO M4 at this museum as
well. During his visit to Taiwan, Jim was disappointed to find that the Armor
Academy was closed to foreign travelers due to the sensitive political
situation in that area of the world. In any case, if any readers in
Taiwan would be in the position to take a few photos of the upper rear
hull plate, the engine deck and the fighting compartment, we would be
happy to have your report. Photo courtesy of 玄史生 on Wikipedia Commons.
Meanwhile, back in the US, both the M7 and M7B1 continued in service
with US Army training units. The photo shows an M7 of the 98th AFA Bn,
1st AD during the joint Army-Air Force Exercise Longhorn at Ft. Hood,
Texas, 30 March 1952. The "Chief of Section" is identified as Sgt Glen
Walls of Marion, Virginia. The M7 carries the name "CASSINO" and can be
seen as USA 4040048, indicating ALCO August 1944 production. After
nearly 8 years, this Priest still looks pretty close to "as built"
although we would think that the original "plain" drive sprocket had
been replaced with a sprocket typical of those made by Chrysler (1). The
T-shaped towing shackles (2) begin to appear in Sherman production in
October 1944, so these are likely postproduction retrofits as well.
Judging by this photo, the larger grouser boxes appear to have been
capable of holding 5 track blocks (3).
This photo is dated 17 August 1954, "Bouncin Betty Fires Away--Battery
B, 161st Armored FA Bn, Liberal's unit of Kan [Kansas] National Guard
fires off a round during a two-week field training session at Camp
Carson, Colo." "Bouncin Betty" can be seen as 40152404 indicating PSC
June 1944 production. The M7B1 has been retrofitted with an armored
first aid box (arrow) attached to the rear of the right-side stowage
bin, but "still" has the original sheet metal exhaust deflector. The
road wheels are "mixed" with the first three being the "welded spoke
with small holes" type, the next being the concave type and the last two
being the original type welded spoke wheels. The men in and on the M7B1
are identified from left to right as "Sgt Darrel Hickey, Cpl John
Leaming, Cpl Al Flores, Cpl Ronald Puliam, Sgt Dwain Dyson, 1st Lt Cecil
E. Davis and behind Lt Davis is Cpl Wallace Molin." The two men in the
lower right are unidentified, but there are a total of nine men in the
shot. "FM 6-74, 105-mm Howitzer M2A1 on Motor Carriage M7B1 and M7B2"
dated March 1954 appears to have changed the number of men in the crew
of the M7B1 and M7B2 from seven to eight. It describes a "section" as
the "personnel required to serve one gun and its equipment." And defines
the makeup of the gun section as "Chief of Section (CS), A Gunner (G),
assistant gunner (No. 1), Four cannoneers, numbered from 2 through 5,
and A motor carriage driver (D)." The inset from the Field Manual shows
the positions of the crew when the section is mounted.
Pressed Steel Car produced a total of 826 M7B1s, which was less than a
quarter of the 3314 M7s manufactured by ALCO and 176 by Federal Machine.
Even so, the Ford engined Priests represent the largest number of
survivors with about 34 M7B1s and 58 M7B2s recorded to date. We use
"about" with the totals because almost half of the surviving M7B1s
appear to be backdated M7B2s, done no doubt because restorers prefer to
own or present a WW II era Priest. Ordnance Committee Item 35296 dated 6
May 1954 includes some historical reference including a request on 21
November 1952 by Army Field Forces No 1 "for the rehabilitation of the
105-mm Howitzer Motor Carriage M7B1 to include high angle fire." Rock
Island Arsenal designed a pilot model "of an M7B1 incorporating,
primarily, a +65 degree elevation. This was done by raising the Mount,
M4A1 15 inches and depressing the floor 4 inches. Elevating arcs from
the 105-mm Howitzer field piece were used [and] adequate armor shielding
for the raised mount was provided." The RIA pilot was found acceptable
after some modification by Army Field Forces No 1 at Ft. Bragg. "A
second pilot was then produced by a commercial rebuild facility who
modified the vehicle in accordance with the test and also incorporated
some additional changes and refinements. Some 78 vehicles have been
modified by this facility and additional vehicles will be modified in
base shops." No dates are provided and the "commercial rebuild facility"
is not named. Reading between the lines of the reference sections of
the OCM, we would guess that RIA produced the pilot model in early 1953,
and that the commercial facility produced 78 units sometime in 1953 and
1954 before 6 May 1954 when OCM 35296 designates them as "M7B2" and
reports that there are 78 "units on hand." From our study of Shermans,
we have found that there were two commercial facilities rebuilding AFVs
in the 1950s: Bowen-McLaughlin in York, Pa. and Brown and Root in
Houston, Texas. Except for "Brown and Root" dataplates on a few
surviving Shermans, we have not come across any documentation about
B&R. We did scan a contract card for Bowen-McLaughlin
showing that they were engaged by the Government to rebuild 98 "105MM
How. Carriage M7B1." The company signed the contract on 12 December
1952, and if we have read it correctly, the cost per unit was about
$7500. This contract could have just been for the rebuilding of straight
M7B1s, or Bowen-McLaughlin may have been requested to perform a high
angle conversion before the "M7B2" nomenclature was adopted. We are not
aware of any period factory photos, so
here we have a front shot of the M7B2 on display at the National Guard
Post in Tullahoma, Tennessee. The most obvious change is the heightening
of the pulpit (1), followed by the multi-part shield (2) for the raised
gun mount. Note that this shield covered over the transmission oil
filler cap. The curved gun shield can be seen to have had some material
(3) welded on to raise it up as well. We consider the location of the
cable clamp (4) on the differential housing to be in the M7B1 "as built"
configuration. On the other hand, we consider the footman loops (5) to
be retrofits and would observe that these have been noted on a number of
surviving Ford M4A3s that we have determined were rebuilt by
Bowen-McLaughlin in the 1950s. Of course, as built, this diff would have
had little strip steps (6) which are now missing on both sides. The
item (7 and inset) attached to the grouser box appears to be the comb
device typically seen on AFVs processed through the Lima Tank Depot in
Ohio.
The Transportation Corps did not disagree or "non-concur" with OCM 35296
which described the military characteristics and designated the high
angle conversion as "M7B2". However, they did note for the record that
"this modified version of the M7B1 is both wider and higher than the
reported dimensions of the M7B1" and that this would affect overseas
rail and US highway movement. According to the 1944 M7 and M7B1
Technical Manuals, the pulpit protruding from the side gave these models
an overall width of 113 5/16 inches. The M7B2 OCM lists the width as
"Irreducible - 115-1/2 inches". We don't see how the M7B2 conversion
widened the vehicle, but there it is. The height of the M7B1 is listed
as 100 inches, and that is for "vehicle only" without the antiaircraft
machine gun or fittings installed. We have not had the opportunity to
measure an M7B2 for ourselves but can note that an M7B2 information
plate, which might have been mounted below the dataplate, gives
the overall width as 113 1/2 inches and the "lowest operable height" as
117 inches. We take this to be the "vehicle only" height without the AA
MG mounted, and if so, would indicate that the pulpit was raised 17
inches. The plate also provides the "overall height" as 131 inches which
we take to mean with AA gun installed. The drawing above from the March
1954 "FM 6-74, 105-mm Howitzer M2A1 on Motor Carriage M7B1 and M7B2"
provides some of the dimensions of what is obviously an M7B1. This field
manual appears to have been written for the M7B1 with reference to the
M7B2 added as an afterthought. There are no photos or drawings of, or
specific references to the M7B2 in this FM.
"Thanks for your service." The Tennessee National Guard’s 1175th
Transportation Company is headquartered in Tullahoma. In this left rear
view of their M7B2 one can see the armored exhaust deflector (1) with
the rods holding it in the "up" position. With one or two exceptions,
the surviving M7B2s, are seen installed with the armored deflector (or
its fittings). This would lead us to think that it was a "must"
modification of the M7B2 program. A new stowage box (2) is noted on
almost all survivors to the extent that this strikes as a "must" mod.
From what is seen on a few surviving examples, it may have held a
communications wire spool (inset). The pyramid shaped objects (3) on the
stowage bins were obviously "door bumpers". As best we can determine
they were not factory installed on 1944 production ALCO M7s or on PSC
M7B1s, but they do show up in a few photos of FMW M7s. The baskets may
have been moved over or resized a little when the bumpers were added. Of
course, our subject is missing the blanket baskets, but we are certain
they would have been factory installed when this unit rolled off the
line as an M7B1 at PSC. Since this Priest has single rear towing lugs,
we would judge that it would have been produced in either January or
February 1945. Earlier we mentioned that we "think" that the M7B1s were
built with the later "short" trailer towing pintles, but this example is
seen with the earlier "long" pintle (4). We would observe that most of
the surviving M7B2s in the US have the long pintles and the armored
exhaust deflectors, as if a conscious effort had been made to install
the longs in conjunction with armored deflectors. The few period photos
available suggest that most of the M7B2 conversions simply retained
their M7B1 Registration Numbers, either in the 40152XXX range or
40172XXX range for the last 198 units. The RN of the Tullahoma can be
seen as USA 40233533, which is off the M7B1 "radar screen" of Ordnance
assigned RNs. So, at first, we wrote off this RN as made up which is
often the case with surviving US WW II AFVs.
We like to record readable USA Numbers from period photos when we
see them, and the 1956 3rd Armored Division souvenir yearbook shows a
few photos of M7B2s with 40152XXX and 40172XXX Registration Numbers. In
addition, there are two photos showing USA 40232698 and 40232708 as seen
above. USA 40232708 on the left can be seen with the heavy engine deck
doors open and perhaps illustrates how the little door bumpers protected
the blanket baskets from getting smashed in. We would note that the
bumpers are present on some but not all surviving M7B2s. The photos
appear to have been taken at Ft. Knox in the winter of 1955/56. In the
Spring of 1956, the 3rd AD deployed to Germany, and it seems that their
Armored Field Artillery Battalions brought some M7B2s with them since
it is mentioned that "Sixty-three flat cars carried 100 pieces of
equipment, ranging from amphibious armored personnel carriers to
self-propelled 105mm howitzers, to Hampton Roads Army Terminal, Norfolk,
Virginia, where they were placed on vessels for overseas shipment." In
any case, we have recorded one other 40232XXX number from a photo that
was for sale online, showing USA 40232712 at APG, date unknown. So,
perhaps some M7B2 conversions were assigned new Registration Numbers? As
for "USA 40233533" on the Tullahoma M7B2, the range between the lowest
number seen in a period photo, 40232698 and 40233533 encompasses 835
units which is more than the total number of M7B1s produced. This would
lead us to think that the RN on the Tullahoma is unlikely to be
authentic.
This photo is dated 7 August 1956 and captioned, "Men of the 54th AFA
Bn. 3rd Armd. Div. on 105 SP. Howitzer waiting for order to fire while
on the Grafenwohr [Germany], Range." There are eight gunners visible in
this photo and some of them are blocking the pulpit and the gun, but we
think enough of the pulpit is visible to identify this as an M7B2. There
is also what we think was one of the "additional changes and
refinements" added to the M7B2 - a stowage box that held a
communications wire spool. On the other hand, such a spool is mounted
just behind the box, perhaps for convenience, but it can be seen that
the spool would fit inside the box, resting on the cradles shown in an
inset in a previous caption. We recorded the Registration Number from
the original print as USA 40152826, so this one retained its M7B1 RN,
indicating it was accepted at PSC in December 1944. This unit can be
seen with the armor plate exhaust deflector, but rather than relocate
the crowbar up 3 1/2 inches to clear the deflector hinges, it has been
relocated to the left rear side. This is observed in the photo of USA
40232712 at APG mentioned previously and on a few surviving M7B2s in the
US such as at Camp Shelby and Starkville, Mississippi. Again we see a
mix of roadwheels including a convex example at the rear. Most or all of
the track end connectors appear to be the "wide guide horn" type
(circled). These are thought to have been castings produced post WW II.
Here we count at least 10 M7B2s photographed at the railhead in
DeRidder, Louisiana on 31 October 1955 in preparation for "Exercise Sage
Brush [31 October-15 December 1955], the largest joint Army-Air Force
maneuver since World War II." Ominously,
the maneuver featured the use of the "atomic cannon" and "began with a
simulated atomic bomb set off at Fort Polk." The caption identifies the
M7B2s as belonging "to the 94th Field Artillery of the 4th Armored
Division, Ft. Hood, Texas." However, the tactical markings on the
foremost Priest are for the 22nd Armored Field Artillery Bn, 4th AD.
Both the 94th and the 22nd, along with the 66th AFA Bn were organic to
the 4th AD. As in WW II, each battalion would have been equipped with 18
self-propelled guns. "C20" can be seen with the "long" pintle (1)
jutting out below the armored exhaust deflector (2). Most or all of
these M7B2s are installed with armored first aid boxes (3) on the
right-side stowage bins. These are present on some of the surviving
M7B2s in the US. The first two M7B2s don't seem to have the little "door
bumpers" protecting the blanket baskets. The M7B2 was classified as
"substitute standard" with the conversion program designed to meet the
Army's requirement for a 105mm self-propelled howitzer with a minimum of
+ 65 degrees elevation. It was intended to be used until it could be
replaced by the M52 105mm Self-Propelled Howitzer (inset) in which the
entire crew operated in a fully enclosed turret capable of rotation 60
degrees left or right. In mid-1955, it was anticipated, optimistically
perhaps, that the M52 would "be classified as Standard type and issued
to troops during the last half of calendar year 1955." Some internet
sources have it that the M7B2 was used during the Korean War. We have
not found any evidence that that was the case and think that M7B2s
are/were being confused with M7J1s.
The Federal Republic of Germany (West Germany) joined NATO on 6 May 1955
during the height of the Cold War. A few months later, to the alarm and
objection of many, the Bundeswehr was established. The US provided a
good deal of the military equipment required to build up the nascent
armed force. According to a "Status of MDAP Operations" document,
Germany was allocated 162 "Carriage, Motor, 105mm How (All Models)" of
which 105 had reportedly been shipped as of 31 January 1954. Of interest
is that the document reports that 1229 "Tank, Medium, M46, M47, M48
series" had been allocated and shipped to Germany as of 31 January 1954.
This would have been before the country joined NATO, so possibly
represents the negotiation and planning process that was taking place at
that time. Various internet sources have it that Germany received a
number of M7B2s starting in 1956 and used them until 1966, when they
were replaced by M52 105mm Self-Propelled Howitzers and M109G SPHs. The
"conventional wisdom" on the internet appears to be that a total of 127
M7B1s were converted to M7B2s. This seems a bit low to us, but the only
figure we can document comes from Ordnance Committee Item 35296 dated 6
May 1954, where it is stated that "Some 78 vehicles have been modified
by this facility and additional vehicles will be modified in base
shops." Some internet sources state that Germany alone received 127
M7B2s. Be that as it may, the largest number of surviving M7B2s appear
to be former Bundeswehr vehicles. They are noted to have been
retrofitted with a pair of large headlights with brush guards on the
transmission housing (outlined in yellow). The electrical cable for the
lights came out of the outermost bolt holes for the transmission housing
and then the cables went down to small plates located underneath the
headlights. The left-side light was right where the cable clamp would be
located on a regular M7B1/B2, so the cable clamp (1) was moved up the
transmission housing to just below the grouser box. The rear view shows a
few other retrofitted items. The brackets outlined in red held an
interesting addition. The illustration photos are undated and come from
the Hunnicutt collection. It is thought that these modifications were
made starting in the early 1960s. Readers might be interested in
"Panzerhaubitze 105 mm M7B2 Priest", a Bundeswehr training film
dated 1957. Four M7B2s are seen in the footage and in this case, they
look to be nearly as built, without the retrofitted lights and
reflectors. We wouldn't be surprised if these were the only Priests in
service at that time. In 1957, the total number of soldiers in the
Bundeswehr appears to have been about 10,000.
Here we have a photo of the upper rear hull plate of a Bundeswehr M7B2
on display at the Panzermuseum in Munster, Germany. It can be seen that
the shovel (1) was relocated outboard from its M7B1 factory position.
This new location is seen on most but not all surviving M7B2s, both in
the US and abroad. It is also on a few surviving M7B1s in the States, so
we would guess it was a modification done post war in the US. Item 2
strikes us as distinctly German. It is the Bundeswehr "Leitkreuz", a
convoy fixture which has a light in the middle that reflects off the
white cross. It serves as a point of reference for trailing vehicles
during black-out driving at night. This is probably the only surviving
M7B2 that still has this object intact. The Leitkreuz appears to have
been installed on Bundeswehr vehicles starting sometime in the 1960s. We
are told that items 3 were "blackout stop lights", and items 4 were
"reflectors". The standard factory taillights (5) appear to have been
replaced on this example. Counting heads suggest that the fittings
numbered 6 were installed as part of the M7B2 conversion, and we are
informed that they were intended to hold a machine gun tripod. Indeed,
the fittings are similar if not the same as the tripod fittings seen on
the left front of the hull on many Grant and Lee Medium Tanks. With
thanks to Michel Van Loon.
This
photo shows the rear of the M7B2 on display on the grounds of the
School of Artillery and Museum in Draguignan in southeastern
France. A pair of what we take to be reflectors (1) can be seen installed on
the lower rear hull, along with the additional lights and reflectors on
the upper hull. We think that fitting 2 would have held the Leitkreuz.
The hinges (3) indicate that this M7B2 was once installed with the
armored exhaust deflector. The fitting for the towing pintle (4) can be
seen in what we have previously described as the "two tiered" mounting
configuration, thought to have been intended to locate the short pintle
further out from the hull when the armored exhaust deflector was
installed. This Priest is noted with a French 1942 era "matricule"
number and is named "La Nartelle". Earlier in the piece we mentioned that Maréchal des Logis Joseph
Gonzales stated that the 68ème Régiment d'Artillerie d'Afrique, 1er
Groupe landed at 8:00 am on 16 August at La Nartelle Beach. Perhaps the 68ème RAA named one of their WW
II M7 Priests in commemoration of that moment? We have
assumed that the additional fittings were German modifications, because
a number of surviving M7B2s with them have been seen with traces of the
"Eisernes Kreuz" under the paint layers before restoration. This was,
of course, the insignia adopted by the Bundeswehr. However, according
to a "Status of MDAP Operations", France was allocated 140 "Carriage,
Motor, 105mm How (All Models)" of which 109 had reportedly been shipped
as of 31 January 1954. Furthermore, most of the surviving M7B2s in
Europe have little plates attached to the front indicating that they
were rebuilt by ABS (Atelier de construction de Bourges) in France
(inset). The surviving tags have dates from 1961 through 1964. So, one
might get the impression that these were French M7B2s. Our preferred
theory is that the Germans contracted with ABS to rebuild a number of
their M7B2s. If any readers can shed light on this subject, we would be pleased to have your report. One of the happy consequences of the ABS
rebuild program from a research standpoint is that the serial numbers
of the various Shermans and Priests, etc. were stamped on the fronts of
the vehicles. So, for example, this M7B2 is stamped with "4527" (inset)
indicating that it was built by PSC in January 1945 and was about the
75th out of 150 M7B1s produced that month. As far as we can determine,
PSC did not stamp the SN on the exterior of any of the AFVs it built,
so the "SN in a box" is a great help. Comparing SN 4527 with the
stampings recorded from other surviving examples would lead us to
conclude that 4527 would be about "ground zero" for the change from
double to single rear tow lugs (5).
Earlier
we mentioned "the multi-part shield for the raised gun mount."
Pierre-Olivier was able to get a photo of the Panzermuseum M7B2 showing
the pieces (1 and 2) added to the top of the shield and cut to follow
the contours of the curved gun shield. The "awning" (3) of the original
design was also cut to follow the contour. Note the curved plate (4)
added to the gun shield. This is observed on all of the surviving M7B2s.
Ordnance Committee Item 35296 dated 6 May 1954 provides a brief
description of the M7B2 conversion process which states that the gun
mount was raised 15 inches, and the floor was depressed 4 inches. The
photo on the left shows the fighting compartment of the M7B1 on display
in Missoula, Montana. Note the way the trails (1) were welded to the
sponson sides. This was the standard configuration used on M7s and
M7B1s. The photo on the right is of the M7B2 in Tullahoma, Tennessee and
shows how "spacers" (2) were welded on to the tops of the original
trails which raised the gun by 15 inches. The heightened gun travel lock
appears to have been fashioned by inserting and welding in a section
from another gun travel lock right in the middle. The depression of the
floor by 4 inches is a bit subtle, but the drop can be seen below the
I-beam as indicated by the arrow. The vertical ammunition containers
look to be unchanged on the M7B2. The depression of the floor by 4
inches doesn't seem to have greatly affected the number of rounds
carried. In the military characteristics section, OCM 35296 lists the
ammunition capacity of the M7B2 as "68 rounds". This is but one less
than the 69 rounds given in the August 1944 M7 Technical Manual. Oddly, we could not find a listing
of the 105mm ammunition capacity in the August 1944 M7B1 Technical
Manual. Quite a few surviving Priests are missing the box (3) just to
the left of the driver's door. The inset shows that this served to
protect the Panoramic Sight from water and other types of damage when
not in use.
A description in OCM 35296 suggests that the M7B2 conversion
required a bit of cannibalization: "Elevating arcs from the 105-MM
Howitzer field piece were used..." The photo on the left shows the left
side elevating arc (1) as seen on the M7B1 in Helena, Montana. The photo
on the right shows the much higher elevating arc (2) required for the
M7B2 as seen on the example on display at Camp Shelby, Mississippi. The
inset drawing is from the M2/M2A1 Howitzer Tech Manual and shows what we
believe were the arcs that were used for the M7B2 conversion.
We would note that a number of the "M7B2 back to M7B1" conversions are
seen to have retained the higher elevating arcs. The photos above show a
pair of backdated M7B1s and provide a good view of the higher arcs,
which are characterized by 4 holes, assumed to be lightening holes
intended to reduce the weight of the component.
The M7 Technical Manual refers to the "Identification and Speed
Data Plate." The plate lists the maximum speeds in the five forward
gears and one reverse and advises that "The engine is equipped with a
governor to limit the road speed in all gears, as shown on the plate on
the front hull wall. CAUTION: Do not permit the vehicle to exceed these
speeds when driving downgrade, to avoid damage to power train and
engine." It has been noted that some mechanically inclined crew members
disabled the governors on their AFVs. The main photo shows the standard
location of what has come to be called the "dataplate" (1) in US WW II
"tank circles". The dataplates are mostly missing from surviving M7
series, but Pierre-Olivier noticed this on one of the two M7B1s in
Helena, Montana and took a few photos. It can be seen that the Priest is
identified as an M7B1, manufactured by "Pressed Steel Car Co. Inc."
Unfortunately, the "Serial No." stamping (2) is not readable. Judging by
a few PSC Sherman dataplates, the year of manufacture should be stamped
into the box (3) at the lower left. We have seen the surname "GRUHLKE"
stamped into the box (4) at the lower right on a couple PSC Shermans.
(Leonard Gruhlke was the head of the Inspection Department at PSC.)
Sorry to say, none of that is readable in this case. The "Vehicle
Cruising Speeds" are readable as 2 MPH in first gear, 6 in second, 10 in
third, 16 in fourth, 25 in fifth and 3 MPH in reverse. (These speeds
are about 1 MPH more than those seen stamped on ALCO M7 dataplates.)
This M7B1 has "USA 40152523" painted on the sides and rear. This is a
valid M7B1 Registration Number corresponding to Serial Number 4060,
built in August 1944. However, the other M7B1 in Helena has the same RN
painted on, which throws the whole thing in doubt. Unfortunately, PSC
and Federal Machine and Welder did not stamp the Serial Number on the
rear towing lugs (or anywhere else on the exterior as best we can
determine) of their M7s and M7B1s, so the SN on the dataplate or the
French ABS stamping on the front is the best shot we have of getting a
Serial Number from these models.
Earlier, we showed the dataplate of the ALCO M7 that went down with its
LCT on D-Day and was recovered and is now on display at the museum in
Port en Bessin. The examination of a few surviving examples suggests
that ALCO stamped the Serial
Number on the left rear towing lug (only) of the M7s it manufactured.
The photo is of the stamping as seen on the M7 SN 958 that Jim Goetz
examined at the Philippine Military Academy in Baguio, Luzon. At
present, we think there are about 30 surviving ALCO M7s in the world
and we have been able to record the SNs of around half of them.
Pakistan appears to have what we take to be a former M7J1 on display at Ayub National Park in Rawalpindi. A description with the
photo states that "Pakistan received 150 units in 1955 under the MAP
program which went on to serve the army throughout the cold war." Should
any readers have occasion to see this Priest, we would be happy to have
your report.
PAGE 2/2
Go to page 1