In the 1930s, as the United
States struggled through the Great Depression, the country was overwhelmingly
isolationist. These conditions were not conducive to the development of a
costly offensive weapon like a Main Battle Tank. The Ordnance Department had
designed a few Light Tanks to support the infantry, and similar "Combat
Cars" to support the [still] existing horse cavalry. Late 1930s efforts to
develop a Medium Tank resulted in the T5 / M2 series (above, left, T5 Phase III
in 1938), which were essentially enlarged versions of the M2 series Light
Tanks. It was soon realized that the T5's 37mm main gun would be inadequate on
the modern battlefield, but the engineers appear to have lacked the knowledge,
resources and technical ability to come up with a design that could mount a
larger caliber weapon in a revolving turret. As an expedient, in 1939, the T5
Phase III was modified to mount a 75mm pack howitzer in the right front of the
hull (above right), in the manner of the French Char B1 bis. The Fall of France
in June of 1940 changed the political landscape, and created a sense of urgency
that the United States begin mass production of a Medium Tank as soon as
possible. A design was needed immediately that could meet the Army's
requirements for mobility, protection and firepower, and this resulted in the
M3 Medium Tank.
Aberdeen Proving Ground in
Maryland was the Ordnance Department's Research and Development
facility for armor projects in the inter war years. Rock Island Arsenal
in Illinois was tasked with producing the few Light and Medium Tank
designs that were approved on the Army's very limited budget. RIA
basically hand made these tanks, using "tool room methods." The
culmination of the inter war Medium Tank program was the M2A1. The tank
was equipped with the same 37mm gun as the latest Light Tanks, which
essentially rendered the design obsolete. However, production
went ahead at RIA simply because the Army desperately
needed some Medium Tanks to equip its
newly created Armored Force. There was also a sort of educational aspect
to the order, since the government and private business had very little
experience in what would be required for the mass production of tanks. In any case, RIA
manufactured 94 M2A1s from December 1940 through August 1941. In the
Summer of 1940, the Ordnance Department had begun work to redesign the
upper hull of the M2A1 to mount a 75mm gun. In an unusual move
reflecting the sense of urgency of the time, the nascent, drawing board
concept was actually standardized on 11 July 1940 as the "Medium Tank,
M3." The photo above was taken at Aberdeen and shows an M2A1 beside the
original wooden mockup of the M3 Medium. Note that the M3 can be seen
mounted on the lower hull of an M2 series tank. The M3 was designed
around the same 9-cylinder Wright Radial aircraft engine and a similar
type of VVSS suspension. It
is assumed that the M2A1 seen here was the prototype, since this photo
is dated October 30, 1940, about a month before M2A1 production
commenced at RIA.
On 15 August 1940, the Chrysler
Corporation was contracted to produce 1000 M2A1 Medium Tanks. For this
purpose, the US Government financed construction of a dedicated tank
plant in Warren, a small township outside of Detroit, Michigan. The
original designation as the "Detroit Ordnance Plant," was somewhat
confusing, so the name was changed on 29 May 1941 to the "Detroit Tank
Arsenal." Before the end of August, the Ordnance Department abandoned
plans for the mass production of the M2A1 with its 37mm gun, in favor
of the M3 "design concept" with its 75mm main gun. Unfortunately, in
the Summer of 1940, the Army engineers did not have the technical
ability to mount such a large gun in a revolving turret. Instead, they
came up with an interim design which mounted the 75mm gun in a sponson.
The M3 pilot was completed at Rock Island Arsenal in March 1941, and
photographed at Aberdeen Proving Ground, Maryland shortly
thereafter. The riveted construction harkened back to World War I.
The sponson mounted 75mm gun along with the turret mounted 37mm,
evinced such descriptions as "land battleship" and "rolling fortress."
The tank stood over 10 feet tall, causing one tanker to remark, "It
looked like a damn cathedral coming down the road." Although
originally intended to be a limited run model, the geopolitical
situation forced its mass production, so that ultimately, 6258 M3
series Medium Tanks were manufactured from June 1941 through December
1942. 4373 were supplied to the Allies as Lend Lease.
In
this front view, we see the familiar "3-piece differential housing"
typical of all production M3 series Medium Tanks. This item certainly
played a prominent role in creating the overall "steam punk" look of the
M3's design. Three separate castings with raised flanges were bolted
together to form the armor cover which protected the transmission and
final drives. In the Summer of 1940, the Ordnance Department turned to
The Spicer Manufacturing Company, which had experience with the Light
Tank, to design the "M3 Medium Tank Transmission." The design was
accepted, and a few months later, the Mack Manufacturing Corp. was
contracted for the production of 1508 units for the US Army and 900 for
the British Purchasing Commission. These figures were inadequate to meet
planned Medium Tank requirements, but it was not until after the
passage of the Lend Lease Act in March 1941 that another manufacturer,
the Iowa Transmission Company, was contracted to produce additional
powertrains starting in September 1941. Chrysler retooled its Dodge Main
Plant for the production of M3 powertrains, and it is thought that they
provided these for all of their Lees and M4A4 Shermans from start to
finish. The M3 Medium Transmission and Final Drive unit weighed 7600
pounds, including the 3600 pound 3-piece armor casting that protected
the front. The transmission had 5 forward speeds and 1 reverse. The
"Maximum Speed" listed on surviving M3 dataplates is 19.3 M.P.H. An
item of note seen here is the dust cover (1) over the gunner's
periscope. This was secured by "snaps" or "press studs" (2) which can
also be seen around the 75mm gun, suggesting that it was intended to
provide a dust cover for the main gun as well. It was intended for the
M3 to be equipped with a siren near the right head light, but it is not
present in the March 28 APG walk around photos. An additional bolt hole
(3) is visible in the righthand piece (Part Number E1230) of the
differential housing. A single bolt was obviously the default
configuration, but a few early diffs can be seen to have had two.
The M3 Medium stood so high primarily because it was designed around the
Wright 975 Radial, an aircraft engine with a proven history in the
aviation industry. (An earlier version of this engine powered the Spirit
of St. Louis on its epic flight across the Atlantic in 1927.) Wright
Aeronautical only produced 750 tank engines up to the end of 1941, after
which its production capacity was devoted entirely to the Army Air
Corps, which had a higher priority rating than the A-1-G assigned to the
Tank Program. In the meantime, the Continental Motor Company was
contracted to set up its Detroit facility for the manufacture of
license-built Wright 975 tank engines at the initial rate of 20 per day
and increasing to 1000 per month by January 1942. At the outset,
shortages of machine tools and other fixtures hampered production,
which, of course, affected the Medium Tank program. The photo above is
dated 8 July 1941 and shows a pair of Wright Radials awaiting
installation into the first Grants at the Pullman Plant. There is some
confusion about the nomenclature, but as built by Continental Motors,
these engines were labeled "R-975-EC2". For our purposes, we shall use
this designation to refer to the engines that ran on 91 octane aviation
gasoline and were fitted with what is described as a "low outlet exhaust
collector ring." In this view, the exhaust manifolds can be seen with
their exhaust pipes in the so called "low" position (arrows). These were
connected to a pair of mufflers mounted on the lower rear hull plate.
In
this left rear view from the 28 March walk around series we see the M3
Medium's original exhaust and muffler configuration. This has come to be
known informally as "the pepper pot exhaust." The Oxford English
Dictionary defines a "pepper pot" as "a small container with several
holes in the top that contains pepper." The "holes in the top" of the
muffler can be seen in inset A. The air cleaners were mounted on either
side of the radial engine. The original cleaners were rectangular in
shape and had three oil sediment cups screwed on to the bottom as shown
in inset B. While these air cleaners were protected inside the engine
compartment, they were hard to service within the confined space.
Indeed, several reports note that it was often found that the sediment
cups were "put on the filter[s] but not rotated far enough to lock them
in place so they soon shake off." The problem with the pepper pot was
that the hot exhaust vented up, directly under the engine deck. This
created an intense heat buildup in the engine compartment which degraded
the performance of the engine. Furthermore, the engine deck often got
so hot that it became a danger to the crew (or riders). In early 1942, a
"Quick Fix" modification was devised that replaced the pepper pots with
a pair of fishtail exhausts that directed the exhaust out and away from
the vehicle. At the same time, the internal air cleaners were replaced
with new externally mounted cleaners. These were vulnerable, but the
tradeoff was that they were much easier to service. The "Quick Fix" was
factory installed starting in the Spring of 1942. A Field Service
Modification Work Order G104-W16 was released on 4 July 1942. This was
the most important and the most widely distributed of the M3 Medium
FSMWOs. Note that the pilot and a few early production Lees were
equipped with a very simple, fabricated antenna base (1), as seen here.
The machine gun cupola (2) of the M3 was designed with direct vision
ports on both sides, but the visor on the left side is conspicuous by
its absence on the RIA pilot.
This overhead view from the 28 March walk around series shows a somewhat
quirky feature of the M3 design - the reinforcing struts (1 & 2)
atop the fighting compartment. The struts helped to support the weight
of the 2-ton Lee and 2.75-ton Grant turrets, and also served as bullet
splashes, protecting the turret ring area from being jammed by small
arms fire or shrapnel. The turret ring had a diameter of only 60 inches,
and 3 men were crammed into the relatively small Lee turret - the tank
commander, the 37mm gunner and the loader. The fighting compartment crew
consisted of 4 men - the driver, the radio operator, the 75mm gunner,
and the loader. The initial positions of the pioneer tools and tow cable
(3) are shown. (The engine crank and 5 ft. crowbar apparently had yet
to be included.) The engine air intake was unprotected and simply
covered with a screen (4). The M3 with radial had 4 fuel tanks. Two were
mounted vertically in the forward corners of the engine compartment,
just below the armored fuel filler covers adjacent to the engine air
intake. Two were positioned horizontally in the sponsons at locations 5
and 6. Each fuel tank was provided with a shut off valve (we've circled
one). Total fuel capacity is given as 175 gallons. As best we can tell
from counting heads, the armored fuel filler covers on the M3 Medium
series used the "short and straight" hinge pins (7) shown here from the
start of production to finish. The pilot was provided with a dust cover
(8) for the 75mm gunner's periscope. However, at present we have found
no evidence that this or dust covers for the guns were ever issued as On
Vehicle Materiel. A report on the pilot notes that "During rain, tank
leaks very badly all over." Production units were sealed with caulk at
the joints, but we suspect that they too leaked "very badly all over."
The Technical Manual notes that a 12 by 12 ft "Paulin" was provided "In
tank." The same equipped the Sherman, and there were many complaints
regarding its insufficient size. Note the little catch (9) that locked
the top hatch when in the open position.
On 24 April 1941 a demonstration of "the Army's new Medium Tank" was put
on at APG "for the benefit of high ranking army officers, members of
the Office of Production Management, British Representatives, and
engineers of the firms which will fill $250,000,000 worth of orders for
huge fleets of the mechanical monsters." In this view on the test
course, the USA Registration Number can just be made out as 304191. The
APG Daily Log for 31 March to 5 April refers to the vehicle as "Medium
Tank M3 #1 (R.I.A.)." For "counting heads" purposes, we interpret this
to mean that the pilot was assigned Serial Number 1. During this week,
the tank was installed with a gyrostabilizer for the 37mm gun. In the
photo, note the counterweight (1), which looks to be a capped plumbing
pipe. It had been decided that the M3's guns would be equipped with
gyrostabilizers, and it is mentioned that during a firing practice on 3
April, the "Stabilizer was not used because of repairs in progress." The
inclusion of gyrostabilizers in the M3 and M4 Mediums strikes us as an
unfortunate decision, simply because we find no evidence that it was
effective enough to warrant the money, time and training spent on it,
not to mention that it was "in the way" in the already cramped turret.
It was a great idea, but the technology was not yet "there" to make it
practical. A much better decision was the inclusion of power traverse.
This was one of the best features of US Medium Tanks, since it enabled
rotation of the turret with a good deal more speed than hand traversing.
On 4 April, the log reports "Had demonstration for manufacturers and
personnel from Washington using all guns on the tank. Later used for
taking personnel around test course." We would have been interested in
any comments about the use of the gyrostabilizer during the firing
demonstration, but none were made. Note that a siren (2) was
retrofitted. The gleam of it (stainless steel?) seems a bit out of
place. Perhaps it was borrowed from the local police or fire department?
In
this photo, the man in the commander's hatch dressed in civilian
clothes is Major General Charles Wesson, Chief of Ordnance from 1938-42.
Note that the Registration Number, W [War Department] 304191, appears
to have been painted on in black, not blue drab. Here we are afforded a
closer view of the capped plumbing pipe (1) used as counterweight for
the 37mm's gyrostabilizer. In the realm of "minutia," we would observe
that the rivets on the pilot can be seen with "round heads" (2) and two
appear to have been "flattened" (flush riveted?) on this example
(circled). If there was any protective padding on the top hatch (3) of
the pilot, it was paper thin compared to what was fitted on production
units. The tracks can be seen fitted with grousers (4) in this photo,
but not in some of the others. We would assume that they were installed
at some point during the demonstration on April 4th. The M3 series
Technical Manuals are not very helpful regarding the On Vehicle
Materiel." They do not list the number of grousers provided, and simply
state that they are stored "In tank." (We would guess the number was 26
as on the Sherman.) Per the TM, "the grousers are attached to every
eighth track shoe by steel pins and a cap screw in a hole provided in
the end of the pin in the track block" [sic]. Note the M2A1 Medium Tank
in the background.
With
the nearly immediate contract change from M2A1 to M3, engineers at APG
and RIA scrambled to provide Chrysler with the enormous stacks of the
necessary blueprints. In the 30 January 1941 DTA photo above we see that
the blueprints have been converted to full size wooden models or
patterns of various components. Most of the items seen here would serve
as the basis for production of the real things by casting. It had been
determined that the M3's turret would be cast, and it can be seen to
have its Part Number, D 38530, (circled) written on with something like a
magic marker. Other items include the bogie bracket (1), the 37mm gun
shield (2), various pieces of the 75mm sponson gun mounting and housing
(3), the transmission housing (4), and the final drive (5). Since
Chrysler and the other manufacturers had never built any tanks,
according to an RIA history, the firm "did everything short of setting
up these contractors in business. The arsenal provided descriptions of
manufacture route sheets; copies of tool, die, jig, gauge, and fixture
drawings; machine-tool requirements; and updated component and assembly
drawings."
From the beginning, the M3 was
thought of as an interim design. Its major shortcoming was, of course, the
limited traverse of the sponson mounted 75mm gun. In August 1940, even before
the M3's design was finalized, the Ordnance Committee, Technical Staff emphasized
that the next step in development would be "modification of the Medium
Tank, M3" by "relocating the 75mm gun in the turret." It was
intended to replace the M3 in production as quickly as was practical. However,
the press of world events created an urgent need for tanks, and Chrysler's
original contract for 1000 M3 Medium Tanks was increased several times so that,
ultimately, the company produced 3243 M3s and 109 M3A4s from July 1941 to
August, 1942. Chrysler more or less hand built the first two tanks, which are
shown above on "Presentation Day," April 24, 1941, a little over a
month after the M3 pilot was completed at Rock Island Arsenal. Chrysler
President K.T. Keller presented General Charles M. Wesson, Chief of Ordnance,
the first M3 (Serial Number 2, USA 301000, the scuffed up tank on the right in
the photo) as a gift from Chrysler employees. This
gift tank created a "one serial number short" bookkeeping problem that
does not appear to have been resolved until near the end of M4A4
production in September, 1943.
During
a "Sherman spotting" trip years ago we encountered an M3 Lee with
Serial Number 2 stamped on the rear tow lugs. We were a little surprised
that it was on display as a monument at a VFW Post in Newark, Delaware.
This was the first tank built at the Detroit Tank Arsenal and is the
scuffed-up Lee shown alongside SN 3 in the previous caption. SN 2 was
received at Aberdeen Proving Ground on 5 May 1941 and SN 3 on 31 July.
Both served as test tanks there during WW II. We would observe that
while the RIA pilot was built with "press studs" around the main gun and
gunner's periscope, SNs 2 and 3 were not. Both can be seen with a pair
of small rivets (circled) on the side. These seem to have "disappeared"
on subsequent units. Speaking of rivets, SN 2 and the rest of the few
surviving Lees identified as Chrysler built are noted to have
"pyramidal" shaped rivets as opposed to the "round heads." As might be
expected, some changes were made to SN 2 over the years. For instance,
it would not have been built with the "plain" sprockets (1) or the
pressed metal idler wheels (2). The replacements probably reflect the
fact that this tank was used in a number of track tests at APG. The
original front fenders may have been replaced during service. At least
the present ones (3) look like they were fashioned in a metal shop. The
faux fixed machine guns (4) possibly illustrate the irresistible impulse
of many to "arm" their monument tanks with plumbing pipes.
Here
we see the first Chrysler-built Lee sans guns on 4 May 1942 involved in
one of the many APG test projects for which it was used. In this case,
an evaluation of "Trailer T32, Armored." Note that the tank has been
installed with "Experimental Sprocket with resilient teeth" (inset). As
the M3 was distributed, reports began to come in regarding worn or
broken sprocket teeth. The "Experimental Sprocket" with its replaceable
teeth appears to have been an overly complex solution to a fairly simple
problem. The teeth, which were affixed with nuts and bolts, moved back
and forth a little, losing their ability to engage and drive the tracks,
and the project was dropped. The Ordnance Department observed that
problems experienced with sprockets appear to have been the result of
poor manufacturing techniques. Indeed, after the early failures, there
is no evidence that sprocket failure was a major issue with Medium
Tanks. In many instances, APG painted the vehicle Serial Number on its
test subjects as seen here. Just visible in a light paint color is the
USA Registration Number 301000. This is not seen in the numerous photos
taken on presentation day as the tank put on a show knocking down a
telephone pole and busting through a wooden "house." Perhaps it was
painted on at APG? In any case, as researchers, we are always happy to
have textual listings or photographs that provide known good Serial and
Registration Numbers together.
An
unidentified woman in a "vintage" flower print dress waves to the crowd
on "Presentation Day," 24 April 1941. If any readers can identify "our
lady of the tank," we'd be pleased to add her name. This Lee can be seen
with "USA W-301.001" painted on in black, identifying it as the second
Chrysler-built M3. The Army Ordnance people were expecting the premier
of only the first Lee, but President K.T. Keller and company surprised
them with two. We would point out that these tanks were not officially
accepted until July. The armor surface of the open side door appears to
have been painted olive drab, but the protective padding (1), the pistol
port/protectoscope (2) and the handle (3) are painted white and stick
out like the proverbial sore thumb. The interior surfaces of the doors
and hatches were painted olive drab on the pilot, but apparently
Chrysler didn't get the memo. As a matter of minutia, we would point out
that the bogie bracket castings seen here in the bright sun have
"raised lines" running across the top and sides (arrow). Such variations
in the castings are generally typical of a particular supplier. As it
sits today, SN 2 has a full set of these castings, but they do not a
have logos (that we could see) that might identify the producer. SN
3/USA 301001 was installed with a Guiberson diesel engine in late 1941.
At the same time, the RIA pilot was installed with "Chrysler engines"
which we take to mean the first A-57 Multibank. It is not known what
became of these tanks afterwards, but a part of the second Chrysler Lee
survives, since "3" (inset) is stamped on the tow lugs of the
differential housing of SN 2 in Newark. (This is why we always "trust"
the rear tow lugs first when looking for the Serial Number on a Sherman,
variant or predecessor.) For a little timeline of the events before and
after "Presentation Day" 24 April 1941, the German Blitzkrieg had
overrun the Netherlands, Belgium, and France by June 1940. By October
1940, the Luftwaffe had been defeated in the Battle of Britain, and
Hitler turned his attention to the Soviet Union, which the Germans
invaded on June 22, 1941. In the US, the Lend Lease Act was signed into
law on 11 March 1941, and the Japanese attacked Pearl Harbor on 7
December 1941.
On
20 February 1943, SN 2 was the target of a demonstration firing "using
shot A.P., M70, fired from 57 mm Gun, M1." It is not known if a
conscious effort was made to preserve this tank, but as it sits now, it
shows these two hits and no others. As can be seen on the right, the
upper hit penetrated completely while the lower glanced off the bottom
edge. One would think the penetration might have caused harm to the
mechanicals, but the quartermaster at the VFW said that the Lee was
driven in parades for years until the city of Newark asked them to stop
because it was damaging the roads. M3 Mediums were built with welded
spoke road wheels (1) from start to finish except at Chrysler, where
pressed metal wheels were introduced into production around March 1942.
The pressed metal wheel (2) seen here, which was obviously a
replacement, became the most common type of road wheel used in Sherman
VVSS production. A bit of the open side door (3) can be seen, and we
would note that it is "still" painted white. According to a Chrysler
history, SN 2 was next "turned over to the Ordnance school for the
training of tank-recovery companies. These lads gaily rolled it over
cliffs and into ditches in order to pull it out and patch it up again."
The
photo on the left shows the "gift tank," Serial Number 2, USA 301000, on
a railcar with officials holding a sign that reads, "No-1 M3 Tank
Returned to CTA May 17th 1945." Of course, "CTA" stood for "Chrysler
Tank Arsenal." (The US determined to avoid brand name advertising in its
contracts, and the official name of the Government owned,
Chrysler operated plant was "Detroit Tank Arsenal.") The arrow shows
what appears to be a pepper pot exhaust still present when SN 2 was
returned. We suspect that Chrysler restored the tank to running
condition by retrofitting the new engine, exhaust and air cleaner set up
it has now. In 1951, the Government financed a new tank plant in
Newark, Delaware to be run by Chrysler for production of the M48 Main
Battle Tank and other Cold War era designs. It is assumed that SN 2 was
shipped to Newark to serve as a sort of mascot, and the photo on the
right shows it there as "The First Production Tank Built By Chrysler
4/24/41." The occasion celebrated the white M48 as the "30,001st Tank
Built By Chrysler 11/3/53." In April 1957, most of the plant was
converted for the production of Plymouth and Dodge automobiles. At some
point after that, we would guess that SN 2, which was meant to be "a
permanent exhibit" at Chrysler, was given (or loaned?) to the VFW
located a few blocks away from the Newark plant, which was shuttered in
December 2008. Comparing the Lee, once described as "a damn cathedral
coming down the road" with the Patton, we can only conclude that the US
Army liked tall tanks.
The
Ordnance Dept. documents are somewhat confusing with a number of gaps,
typos and downright errors regarding the Serial and Registration Numbers
assigned to the M3 Lee series. We hope readers will indulge us in a
little "thinking out loud" math exercise, while we try to establish a
base line. As stated previously, Chrysler's initial contract was for
1000 M3 Medium Tanks. From counting heads, we are quite certain that the
Serial Numbers assigned ran from 2 though 1001 (2 + 999 = 1001).
Baldwin's contracts called for the production of 685 Lees and 685
Grants. The Lees were originally assigned the next available block of US
Army Ordnance Serial Numbers - 1002 through 1686. However, in the Fall
of 1942, 150 diesel Lees were diverted from the contract to be converted
by Baldwin to T2 Diesel Tank Recovery Vehicles. Thus, in the end,
Baldwin officially produced 535 M3 Lee series tanks. We interpolate that
the highest Serial Number assigned to a Baldwin Lee would have been
1536. This leaves us with "orphan" Serial Numbers 1537 through 1686.
ALCO's contract originally called for production of 685 M3 Lees, but
this was soon changed to include 300 M3A1 (cast hull) models. Again,
these were assigned the next available block of Serial Numbers - 1687
through 2371. As far as we can tell, all of the M3 Medium series Serial
Numbers higher than 2371 would have been assigned to the additional 2352
M3s and M3A4s that the Government ordered from Chrysler. From this, we
interpolate that the highest Lee Serial Number would have been 4723. The
highest SN we have recorded is close at 4718 as shown above during an
Acceptance Test at the General Motors Proving Ground on 30 September
1942. Again we see the USA Number, 3058309, painted on in black. The
evidence is that Chrysler used black paint, as opposed to the prescribed
blue drab, for the Registration Number on its M3s from start to finish.
This tank would have been accepted in August 1942 as the M4A4 Sherman
completely replaced the M3 on the production lines at the Detroit Tank
Arsenal. Unlike the Grant, the Lee design underwent a few modifications
which we shall discuss going forward. The most obvious changes seen here
are the elimination of the side doors (1), and the addition of
ventilators (2). Like the M3 pilot, this unit can be seen with a dust
cover over the gunner's periscope (3). A dust cover can also be seen
over the 37mm gun (4), but not the 75mm. We regret to say that we have
not been able to confirm if dust covers were ever included as On Vehicle
Materiel on the M3 series. Indeed, this is the only Ordnance or factory
type photo we've encountered that shows a dust cover on one of the main
guns.
The
American Locomotive Company, or ALCO, had been engaged in the
manufacture of locomotives at their plant in Schenectady, New York for
more than 100 years. In November 1940, the Government contracted with
the firm for production of 685 "medium weight tanks, M3." Originally,
the production order provided for additional plant and facilities
designed to enable a monthly capacity of 575 medium tanks. ALCO
engineers also assisted APG in the design of the 105mm Howitzer Motor
Carriage, M7 [Priest], a conversion based on the M3 Medium. When all is
said and done, the M7 was actually a more useful addition to the arsenal
than the M3. It certainly remained in service longer. ALCO manufactured
3314 M7s from April 1942 through October 1944. Just because it is
mentioned in a report, we thought we'd add, "The starting wage for
workers is 74¢ an hour. Semi-skilled workers receive from 90¢ to
$1.00 an hour, and skilled mechanics receive $1.25 an hour." The photo
above shows "Presentation Day" of the first M3 at ALCO, 19 April 1941.
According to the US Army History, "The Ordnance Department: Procurement
and Supply," "In April, when American and Baldwin were about
to complete their first tanks, the Mack Manufacturing Company had only
one power train available. It was delivered to American, and completion
of that company's first tank was heralded with a demonstration before
Secretary Patterson and other high-ranking Army officials. The
power train was then quickly removed and delivered by truck to the
Baldwin Locomotive Works so that company could celebrate completion of
its first tank a few days later. Meanwhile Chrysler, which built its own
transmissions, had completed its first tank on 11 April but the
acceptance ceremony did not take place until 24 April." In the photo,
note that the righthand piece of the differential housing has two bolts installed where it joins to the hull.
The
"Presentation Day" Lees were far from complete and most served as test
vehicles at Aberdeen Proving Ground and other Ordnance facilities. The
photo above provides us with both the Serial and Registration Number of
the first ALCO M3 - 1687/USA 305757. Note that the Registration Number
appears to have been painted on in black. As can be seen here on 8
August 1941, the tank was subjected to a bit of "Caliber .30 Aimed Ball
Ammunition." It would appear that two shots were directed at the side
door to test the strength of the hinges. A few other rounds were aimed
at the lower edge of the turret. This was likely done to determine if
there was a susceptibility to the turret jamming, since this area was
unprotected by any sort of bullet splash. The area circled showing 2
missing rivets and a small and large hole was the mounting point for the
antenna base on the Lee series. It is thought that this early unit
would have been built with the fabricated base that was replaced with a
casting a few months into production.
At
some point before 29 November 1941, SN 1687 was installed with "Remote
control" which we take to mean that it could be driven around the target
range like a drone. The tank was painted with white aiming crosses and
subjected to 37mm armor piercing fire. A number of penetrations can be
seen, and we can't help but think that 1687 may have been permanently
immobilized at this point. Perhaps it ended up as a stationary target?
This interior view of 1687 shows how round 10 penetrated the shutter of
the "Driver's Indirect Vision Device." The prop (1) for this device is
hanging down here, but when not in use, it was actually held by a clip
across the bottom of the driver's vision hatch. The junction where the
75 mm sponson casting attached to the front of the hull was a large shot
trap, and the penetration of the casting by round 11 is circled. We
suspect that some of the rivets were circled with chalk because they had
been completely or partially detached by shock, sending shrapnel flying
around the interior. The brown paper (2) was installed for the firing
tests to help determine the trajectory of shrapnel. The conclusions
reached from these tests were published in February 1942, and were
extremely negative, "It was recommended that all rotor clearances
[around guns] be provided with shields and splash proofing; that armored
air intake grilles be provided; that side doors and pistol ports be
permanently welded shut; and that the production of riveted hulls be
discontinued." Note the protective padding (3) around the Driver's
Indirect Vision Device and on the "ceiling" of the hull (4). The M3
Medium appears to have had its combat debut with both the Soviets and
the British in May 1942. In both cases, reports came in that the padding
was highly flammable, and it was ordered to be removed. Except for the
side doors, the padding is rarely seen on surviving M3 Mediums. This
photo provides us with the opportunity to show the location of the
dataplate (5) on Lees and Grants.
Baldwin
Locomotive was the only company that manufactured both Lees and Grants.
In late 1940, the firm was awarded contracts at a little over $40
million dollars each for the concurrent production of 685 Grants and 685
Lees. The first Baldwin built Lee was accepted in June 1941, while the
first Grant was not accepted until October. A Baldwin History attributes
this delay to the "radical changes" (radio turret, etc.) the British
had negotiated for the Grant, "which were at variance with the design
adopted by our own Government." Right up to the start of production, the
British continued to push for additional modifications, until
"ultimately it became necessary to freeze design changes on the British
vehicle in order to secure quantity production." This "design freeze"
explains why the last Grant was built with features nearly identical to
those of the first. However, it should be noted that a few "radical
changes" were in fact introduced into Grant production at Baldwin. In
particular, the "GM Model 6046" twin diesel powerpack completely
replaced the radial engine on both the Lee and Grant production lines by
early 1942. The photo above shows "Presentation Day" at Baldwin, 24
April 1941, and the caption reads in part, "One of the new tanks that
came off the assembly line here today..." We would point out that this
Lee can be seen with 10 rivets running vertically where the side plate
meets the 75mm sponson casting (arrow). Additionally, the righthand
section of the differential housing has two bolts installed where it
joins to the hull. This is likely the power train that was reportedly
removed from the ALCO Lee and delivered to Baldwin. A "General Steel"
water tower can be seen in the right background, as this foundry was
right next door to the Baldwin plant in Eddystone, Pennsylvania.
This fine
photo was taken at the Baldwin Locomotive Works and is dated
5 June 1941. The "U.S. Army War Department Number," 305072, can be seen
painted on in a bright white "railroad" style font. This Lee was
pictured in various newspapers of the day. It garnered a lot of
attention, as it appears to have been driven the 60 miles from
Eddystone, Pa. to Aberdeen, Md. It is described as "The first M3 Medium
Tank to be delivered to the U.S. Army." Judging by the single
bolt on the righthand section of the diff, and
the "missing" rivets (circled) on the side, this is NOT
the same M3 as shown in the previous caption. Three, as seen here, is
highest number of "missing" rivets we've encountered;
two is more common and seems to have been scattered randomly on
early production Lees and Grants. Ten vertical rivets
were obviously the default. "Counting heads" suggest that
Chrysler-built Lees were produced with 10 rivets from start to
finish. Like the first Chrysler Lees, 305072 does not have
the "press studs" around the 75mm gun and has the
two small rivets (1) on the side. No doubt, these
similarities and/or differences can be attributed to the still evolving
nature of the design at the time. Lee production utilized T41 flat
block tracks with reversible rubber tread (2). On the other hand,
the British ordered WE210 non-reversible rubber tracks with a 'double
I' tread pattern for their Grants. The drive sprocket (3) is what we
call the "M3 sprocket" for want of a better term, since it appears to
have been factory installed on all M3 Mediums from start to finish. USA
305072 can be seen with a painted over "Mack Medium M3 Powertrain"
identification plate (4) affixed to the center of the differential
housing. These plates were soon repositioned to the interior,
where they were mounted above the transmission. The Grant on
display at the Tank Museum at Bovington, which is thought to be the
first tank built by Pressed Steel Car, still has its Mack SN 7 ID plate
on the outside. For the purpose of "counting heads," we would note that
USA 305072 was used as a test tank at APG where it is listed as Serial
Number 1002. So, while this was not the Lee trotted out
on "Presentation Day," it would have been the first M3 accepted at
Baldwin.
This
photo appeared in newspapers on 18 June 1941 with the caption," A new
M3 medium tank, the first completed at the Baldwin locomotive plant for
the United States army, is shown rolling through Broad street traffic
in Philadelphia enroute to the dedication of a new armor plant. From
Philadelphia it will be taken to Aberdeen, Md." At first glance, we
thought that this Lee might have been 305072 of the previous caption,
but a close examination of the print shows the Registration Number to
be USA W-305073, painted on in white, but not in the railroad style
font of 305072. Furthermore, the casting marks on the left section of
the differential housing are not in the same location as on 305072, and
of course, this unit was shipped with a 75mm gun. Note the 3 "missing"
rivets on the left in front of the side door (arrow). Photos show that
this was also the case with 305072. Again, it is obvious that a full
row of rivets was the default, but "missing rivets" show up in period
photos from time to time, and present us with an interesting mystery.
In any case, we have 3 different Baldwin built M3s where the captions
imply that they were "the first." USA 305073 was not reported to have
been received at APG until 25 June 1941, so it may have done a
week's tour around the Philadelphia area before arriving at its
destination.
USA
305073 was used in various track and grouser tests at APG. On 15 May
1942, nearly a year after it was delivered, the Lee, identified as
"#1003," was photographed with guns removed "stuck in rectangular
ditch." This tank and SN 1002, are the only examples we have encountered
that have 3 "missing" rivets (arrow) in the vertical row where the
side plate meets the 75mm sponson casting. We can only guess that the
missing rivets may have had something to do with internal interference
issues. The removable "short and straight" hinge pins (arrows) securing
the armored fuel filler covers can be seen to have worked out of their
sockets, but a bit of chain prevents them from being lost.
According
to the M3 series Technical Manuals, the "Ammunition carried" in the Lee
was 50 rounds, 75mm and 178 rounds, 37mm. The above drawing from the TM
shows the quantities of the various rounds with their locations
throughout the turret and fighting compartment. For instance, the "box
on floor crew compartment, right side, directly behind the 75mm gun"
(Item 23, highlighted in red) held 41 rounds of 75mm ammo. Not shown in
the drawing are 9 rounds of 75mm which were reportedly stored "loose" in
three 3-pack cartons. With 2 gunners and 2 loaders, the Lee had a large
crew of 7 men. Their seats are numbered 1 through 6 in the drawing. Not
shown is the seat for the loader for the 75 mm gun. He was provided
with a bench-like pad (inset) attached to the top of the (red) 41 round
75mm ammo bin. The
Lee's radio was located on the hull wall to the left of the radio
operator's seat (Item 2, highlighted in blue). The British were able to
reduce the number of crew members to 6 by housing the radio in the
bustle of the larger Grant turret and having the loader of the 37mm gun
serve as radio operator as well.
The original M3 Medium transmission featured something called a “Hycon
Steering System.” This was basically “hydraulic control power steering,”
designed to make it easier for the driver to push and pull the steering
levers. This system strikes us as similar to the gyrostabilizer, in
that it was ahead of its time, but complicated and undependable. The
British were aware of this issue and required that the steering levers
on their Grants be made 3 inches longer in order to provide the driver
with additional leverage in the event that the Hycon failed. At
Chrysler, it was reported that the Hycon System was shipped on "Serial
Nos 2, 4 - 45 incl, and 47...All subsequent tanks to have manual
control." If accurate, it would mean that Chrysler eliminated, or
perhaps at first just disconnected, Hycon on its transmissions in August
1941. ALCO, which like Chrysler only built Lees, reportedly shipped
"Serial Nos 1687 - 1803 incl." with Hycon, indicating a change to manual
control in November 1941. Baldwin was reported to have shipped "Serial
Nos 1002 - 1042 incl" with Hycon. After that, "First 250 M3 Tanks to be
equipped with modified Hycon." Since Baldwin built both Lees and
Grants, we would assume that "modified Hycon" would have been installed
on both for a time. From a British report of December 1941, “U.S. are
dispensing with Hycon control and are fitting five (repeat five) inch
longer lever on gearbox to increase leverage. This permits steering
without Hycon.” On the other hand, “British tanks...retaining Hycon with
improved valve.” However, by February 1942, straight manual control was
described as “present production,” which we interpret to mean that the
manufacturers, Mack, Iowa and Chrysler were making only that, including
the transmissions for the new Shermans. In fact, in early 1942, the
Ordnance Committee recommended "That the Hycon steering brake control
system not be employed on Medium Tanks M4." The photo above shows what
appears to have been an ex Australian 1942 production Chrysler M3 Medium
that had had most of its superstructure removed in order to convert it
to some sort of farming or logging type tractor. It provides a good
illustration of how the driver sat astride the transmission. Here we see
the presumably elongated steering levers (1), along with the clutch
pedal (2), brake pedal (3) and gear shift lever (4). The inset shows a
Chrysler "Medium M3 Power Train" identification plate. It can be seen
that this particular P.T. was Serial Number 2679, manufactured in 1942.
The arrow indicates where it was affixed to the top of the differential
case.
Here
we have an example of the distinctively shaped Mack Medium M3 Power
Train plate. As mentioned previously, only a few of the first Grants and
Lees were built with the Mack plates attached to the exterior of the
differential housing. They were immediately moved inside and fixed to
the differential as seen above. This plate does not appear to have been
made of brass, but it held up to the elements pretty well before the
power train was scrapped a few years ago. Company records report that
the Mack plant in New Brunswick, New Jersey produced a total of 2652 M3
Medium Power Trains plus 361 spares from February 1941 through Feb.
1943. This one can be seen as Serial Number 2136. By the monthly
production figures, we'd calculate that this power train was accepted in
August 1942. It probably took a month or so before it was delivered to a
factory and assembled to a tank. By that time, Grant production had
ended, and only Baldwin Locomotive was still making M3 Lees, and all
were diesel models - M3A3s and M3A5s. So, this powertrain was likely pulled from one of those. Just
behind the serial number are the initials "WPB" (inset). Of course, New Jersey
was in the New York Ordnance District which was headed by General Walter
Putney Boatwright at the time, so he accepted this power train on
behalf of the Ordnance Department. Photo courtesy of Midwest Military.
Lees in the US
The troops of the
Armored Force were anxious to get their hands on the new M3 Medium
Tanks, but some time was needed for the Ordnance Department to work out
the bugs, finalize stowage arrangements and allocate units for US Army
or Lend Lease issue. Only about 100 Lees had been accepted by the end of
August 1941. They appear to have made their "combat debut" during the
Louisiana Maneuvers in mid-September, possibly at "the Battle of Castor"
when the Lees of C Company, 1st Battalion, 69th Armored Regiment (M),
1st Armored Division overran the Blue Army's infantry and anti-tank
positions in the town. It can be seen that the attack on Castor had air
support in the form of A-20 Havocs. We have not had access to the 1st AD
records for that period, but one caption has it that the Division had
13 M3s "which came off the production line less than three weeks ago."
Going by the photos from this period, we would assume that all of the
available Lees were issued to C Company. In the rush to supply the "Old
Ironsides" Division with the new M3s, some were shipped without their
75mm guns, such as the lead tank, C-6 seen here. On 4 December 1941,
Captain Sedgley Thornbury submitted "Report of Medium Tank, M3" to The
Armored Force Board regarding the condition of the Lees of the 69th AR
that he had examined in late November during the Carolina Maneuvers. In
the Report, C-6 is listed as 301018, indicating it was built by Chrysler
in August, overall, their 17th Lee. Thornbury reported that the Hycon
System had failed, and that after 231 hours, the engine was burning oil
and needed replacement.
Sledge's Store at the intersection of
E. Pine St. and Front St. appears to have been the point where the Blue
Army set up its main line of resistance in Castor. Note that the trees
seen here are obviously the same as those on the left in the previous
caption. The lead tank, C-2, can be seen with the Armored Force
triangle painted on the glacis as well as on the hull "roof" just
behind the driver's visor. Of course, the "1" indicates 1st Armored
Division. Due to a lack of photos, we suspect that Patton's 2nd
Armored Division did not have any Lees during the 1941
Louisiana Maneuvers. One account states that the Division was
issued 32 just prior to the start of the Carolina Maneuvers which began
in October. Counting heads from repair reports and such suggests
that, as production ramped up, the 1st AD was issued exclusively with
early Chrysler M3s. It struck us as odd that there are absolutely no
early Chrysler entries for the 2nd AD. Rather, counting heads suggests
that the 67th AR of the 2nd AD received its first Lees from Baldwin and
ALCO. This may have been a function of the geography of the
manufacturers in relation to the locations of the home bases of
the 1st and 2nd ADs, Ft. Knox, Kentucky and Ft. Benning, Georgia
respectively. From
Captain Thornbury's Report, we would interpolate that C Company was
issued the first allotment of Chrysler Lees starting at USA 301005
(July 1941) and running nearly consecutively up to 301018. For instance, C-2, seen in this
photo, is listed as 301011 (August 1941). Thornbury interviewed the
Motor Officer and the Commanding Officer of the 69th AR, who stated that
the schedule of the maneuvers did not "permit adequate time for 1st and
2nd echelon maintenance." His notes reveal that, before the end of
November 1941, nearly all of C Company's Lees had had their radial
engines changed out after less than 200 hours and/or 1000 miles of
operation. Most of us think in terms of the engine life of our cars, but
this was actually not that bad. Despite the numerous improvements made
by the Ordnance Department and Continental Motors, the average service
life of the radial engine never greatly exceeded these parameters.
A
photo caption has it that "The [1st Armored] Division utilized 17
medium tanks and 13 light tanks in the attack" on Castor. Thus, we might
assume that 4 M2 series took part along with the 13 M3s mentioned
previously. In
this view, at least 3 M2A1 Mediums of A Company are shown on Front St.
rumbling past Sledge's Store. We would observe that Rock Island Arsenal
had just completed its production order for 94 M2A1s in August 1941. The
caption of this photo reads in part, "This column of tanks followed a
wave of M3 Medium Tanks which waded into streams of anti-tank fire by
stubborn defending troops." While the "umpires ruled the attack
successful," in combat, US tankers quickly learned to avoid such
tactics. As with C-2 in the previous photo, the lead tank, A-6, can be
seen with a few "jerrycans" on its rear deck. In 1939, the Quartermaster
Corps at Camp Holabird, Maryland got its hands on a German 5 gallon
fuel can, and more or less copied it for mass production. A number of
the Light and Medium Tanks in the maneuvers photos can be seen with
racks holding 6 or 7 of these cans. However, this was not a practice
that was generally adopted for combat conditions. Partly as a result of
the various maneuvers, the US Army learned a thing or two about
logistics, and developed a supply system during WW II that was second to
none.
As the
Lees began to roll off the assembly lines, they were issued to the
Medium Tank Regiments of the 1st and 2nd ADs - the 69th and 67th Armored
Regiments respectively. Captain Sedgley Thornbury 's primary mission
for the Armored Force Board "was to check on the operation of two sets
of steel tracks under service test in the [69th Armored] regiment"
during the Carolina Maneuvers in November 1941. He listed USA 301046
(DTA, August 1941) with B Company, but did not provide a tank number.
The Lee had had its power train replaced, and it was stated that after
107 engine hours and 710 miles, the engine was being pulled due to
excessive oil consumption. Thornbury noted "Steel track rubber
shoe...Bolts coming loose." In addition, USA 301051 was listed in
Company D with "Solid steel track...wearing very well...Support rollers
break (4)." We take B-10 shown above to be 301046 with a track that
appears to be similar to the T47E1 described as "Steel, cast,
rubber-backed parallel grouser." In another document, 301051 appears to
have been scheduled originally for test by the 67th AR. The tracks are
described as "T37," an all-steel type not approved for production. The
Ordnance Department was no doubt seeking solutions to improve the Lee's
off-road traction, but in addition, they may have been anticipating a
rubber shortage brought about by potential Japanese aggression in Asia.
Bear in mind that Thornbury's report was made a few days before the
Japanese attack on Pearl Harbor, 7 December 1941.
C-2
was featured in a previous caption during the Battle of Castor. Here we
have another view of the tank taken in early November 1941 as it
disembarked from a rail car in Rock Hill, South Carolina. A crowd
gathered as the tanks of the 69th Armored Regiment arrived at the
station. At some point after the Louisiana Maneuvers, it would appear
that many of the 69th AR's tanks were painted with a series of light
colored dashes around the base of their turrets, as seen here. It is
thought that the Lees of the 67th AR, 2nd AD made their "combat" debut
during the Carolina Maneuvers, and a few photos show them with a solid
light color painted around the base of their turrets. They may have been
driven from Ft. Benning as one account has it that "At one point, a
line of more than 2,500 military vehicles stretched from Fort Benning to
Rock Hill, a distance of 425 miles." While it can be seen in our
previous photo, this one of C-2 provides a clearer view of what we
consider the "standard" cast antenna base. Recall that Captain
Thornbury's Report listed C-2 as USA 301011 indicating August 1941
acceptance, and counting heads suggests that Chrysler transitioned to
the use of the cast antenna base during that month. We haven't been able
to do an effective head count of its introduction at ALCO and Baldwin
but believe it came a month or two later.
An
Inspection Report of December 1941 lists some of the Lees of the 67th
Armored Regiment (M). From it we would interpolate that D Company of the
2nd Battalion may have received the first allotment of Lees most of
which were produced by Baldwin Locomotive in August or September 1941.
In the report, it was stated that D-1, USA 305092 [Baldwin, Sept. 1941]
"fell through a bridge" on November 29th. We assume that the scene is
depicted in the photo above. Note that this tank still has the
fabricated antenna base (1) and is one of the few Lees photographed
during the Maneuvers in 1941 that actually had an antenna installed,
presumably indicating that it was equipped with a radio. The inset
provides four views of the fabricated antenna base on SN 2 in Newark. It
can be seen as a steel stamping with rounded edges and few curves, open
underneath and on the inside side. The antenna mounting would have been
unprotected, and as a consequence this part was replaced with an armored
casting, although it strikes us that the additional protection offered
would have been minimal. Some of these castings have been noted to carry
the Part Number C85029. In the photo it can be seen that the antenna
was mounted on an angle with the fabricated base, whereas it was mounted
straight up on the casting. In attempting to "count heads," we would
simply note that USA 305096, a test tank at APG, would have been the
first Lee accepted at Baldwin in October 1941, and the photos show it
with the cast "antenna pot." A
few late 1941/early 1942 photos show that the Lees of the 67th AR had a
solid stripe (2) painted around the base of the turret. This can be
contrasted with the dashed stripe seen around the turrets of some 69th
AR Lees. Furthermore, 67th AR tanks can be seen with Air
Corps type roundels (3) painted on the front and sides. Finally, the
company tactical markings (4) were painted rather prominently on the
sides of the turret.
Another
bridge mishap was filmed during the Carolina Maneuvers on 21 November
1941. This left some children stranded, and a crew member is shown
helping them cross so that they could get home from school. We believe
that the tactical markings, "1-1," seen on this Lee would denote tank 1
of the Headquarters Section of the 67th AR's 1st Battalion, which would
have been made up of Companies A, B & C. This unit can be seen with
the solid stripe around the base of the turret, and we would note that
the roundels were also painted on the rear of the turret as well as on
top. The padding (1) on the top hull hatch looks to be non-standard. The
gunner's periscope appears to have a small, well-fitting cover (2)
protecting it, although such an item is not listed as On Vehicle
Materiel in the M3 Technical Manual. This Lee is installed with the
standard cast antenna base (3). Unfortunately for counting heads, we
don't have a listing with corresponding Registration Number for Tank
1-1. Note that the antenna is mounted straight up. The antenna or aerial
consisted of several sections joined together with ferrules (4) like
some fishing rods.
In anticipation of combat under desert conditions, in March 1942,
General George Patton was ordered to establish a training facility in
the Mojave and Sonoran Deserts in southern California and western
Arizona. The "Desert Training Center" was the largest US Army
installation ever, described in one account as over "18,000 square miles of nothing, in
a desert designed for hell." During the 2 years it was in operation, 13
Infantry and 7 Armored Divisions along with a number of independent
Tank and Tank Destroyer Battalions trained there. Ironically, none of
them fought in any sort of desert conditions. The above is dated 29 May
1942, the earliest DTC photo we have found with some "Lee" content. It
is the practically mandatory "so hot you could fry an egg" photo. No
unit information is provided, but the "chefs" are named in the caption:
Sgt. Tom Kuka of Havre, Montana and Sgt. Edwin B. Cowan of Hood River,
Oregon. Bob Holt of "752nd Tank Battalion in World War II" was able to
confirm that these men served with the 752nd. Bob told us, "My dad and
the rest of the 752 went to DTC in April 1942. They were part of the
first wave of troops to train there...from April through July 1942 in
preparation for combat in North Africa." Despite the obvious extreme
heat, the Sergeants are wearing full tanker uniforms, including the
Rawlings pattern helmets. This was probably at the insistence of General
Patton, well known as a stickler for such details. This Lee can be seen
with a 75mm gun, but Bob Holt informs us that "Half of them arrived
with no main guns." At that time, a Tank Battalion was charaterized as
either "(Medium)" or "(Light)" and was entirely equipped with its type.
We came across a Feb. 1942 Products Correction Report (Defective
Generator Drive Bushings) which provided the Registration Numbers of 51
of the 54 new M3 Lees received by the 752nd as they converted to a
Medium Tank Battalion at Ft. Lewis, Washington starting in November
1941. By the Reg. Numbers, these tanks were produced October through
December 1941. The British had ordered the 75mm guns for their Grants
from the Empire Ordnance Co. There were some quality control issues with
these at first, so guns produced for the US were substituted, since
many of the Grants were shipped to the combat zone in North Africa. The
first Soviet Lend Lease Lees were produced in October 1941 and of course
these were shipped with guns. As a consequence, the US Army had to make
do with some Lees without 75mm guns until production caught up with
demand.
The
evidence suggests that it was common practice for units to leave their
tanks behind once they completed their tours at the Desert Training
Center. After their stint at the DTC, the 752nd Tank Battalion shipped
out for the United Kingdom in August 1942. The photo above shows an M3
Lee with the unusual name of "Buturlinovka." According to Wikipedia,
Buturlinovka is "a town in Voronezh Oblast, Russia." We suspect the town
had some sort of significance to Russian born Captain Peter Meshkoff,
the commander of B Company, 752nd at the time. The Registration Number
can be seen in the original print as USA 304367, indicating October 1941
production at Chrysler. This RN is on the list of 752nd Lees in the
Feb. 1942 Products Correction Report [PCR] previously cited. The photo
is dated January 1943, long after the 752nd had departed. This Lee would
have been built and shipped with the original "pepper pot" exhaust, but
it can be seen to have been retrofitted with the "Quick Fix"
modification where the internal air cleaners were replaced with new
externally mounted cleaners (1) and a pair of fishtail exhausts (2) were
added through the pepper pot holes. This modification became available
in the Summer of 1942 and was widely retrofitted to Lees already "in the
field." The US/British invasion of Northwest Africa [Operation Torch]
in November 1942 highlighted the urgent requirements for tank
transporters, such as the Diamond T Heavy Tank Retriever M19 seen here,
along with tank-based recovery vehicles. The Desert Warfare Board was
established at the DTC to test and evaluate such equipment. Photos
suggest that the 302nd Ordnance Regiment conducted trials of the M19
using "Buturlinovka" and at least one other former 752nd Lee, USA 304506
(inset).
In
keeping with the theme of "so hot you could fry an egg," here we have a
Desert Warfare Board trial of an interesting concept "Air cooler mounted
on a tank." The idea appears to have been to install something similar
to a "Car Cooler," also
called a "Swamp Cooler," through the left front pistol port. Note that a
pair of 5 gallon(?) water bags can be seen hanging from the 75mm gun.
In a nutshell, the swamp cooler held a sponge like pad inside a
container. The pad was saturated with water, so when air was forced
through the unit, either by the vehicle's forward motion or, optionally,
the use of a fan as seen here, the water would evaporate and provide a
mild cooling effect that was directed into the passenger compartment
through a vent. Swamp coolers work best in dry, desert like climes,
where water, their "fuel," is often at a premium. Indeed, excessive
water consumption was the primary reason this project was terminated. In
the meantime, the British simply observed "Temperature Recordings in
Tanks" in late August 1942 in the combat zone around El Alamein. "The
purpose is to determine the temperatures under the worst conditions
likely to be encountered by the crew." The Alamein temperatures reported
ranged from 87 to 93 degrees Fahrenheit (30 to 34°C), perhaps a bit milder than
those in the Mojave and Sonoran Deserts. Inside a few Grants, with the
engines off, the temps recorded were 10 or 12 degrees hotter than the
outside air - "definitely hot, and perspiration was moderately profuse."
With the engines running, temps were about 5 degrees warmer than the
outside air - "moderately comfortable, and noticeable perspiration
ceased." "When the tanks were moving, conditions were reasonably
comfortable." We suspect the definition of "reasonably comfortable" has
changed a bit since then. At any rate, this photo is dated July 1942,
but it can be seen that the twin .30 caliber machine guns are "still"
installed in the bow of the tank. The effectiveness of these guns was
severely limited, since they were fixed forward, so that the driver was
required to move and point the tank in the direction of any targets
before firing. In June 1942, the Ordnance Committee recommended their
elimination, but ultimately it was decided to retain one of the guns.
Dated
August 1942 and taken at the Ordnance Depot at Camp Young, this Signal
Corps photo heralds the arrival of the first Shermans at the DTC, in
this case diesel M4A2s. Of course, as they became available in quantity,
Shermans replaced Lees in the US Army. In the meantime, soldiers of the
302nd Ordnance Regiment are shown changing tracks on one of the Lees.
This tank (A) can be seen as USA 304586 (Dec. 1941 production) another
Registration Number listed on the 752nd Tank Battalion PCR list. "C-15"
is painted on the upper rear hull plate. Aside from the track change,
304586 appears to have been in the process of being retrofitted with the
"Quick Fix" exhaust and air cleaner modification. Only the fishtail
exhausts are present, but it is assumed that the external air cleaners
and the supportive side and rear plates would have been added, so that
eventually it would have the appearance as on tank B. Tank B can be seen
as USA 304506 (Nov. 1941 production) with "C-10" painted on the rear.
This Lee was widely photographed in September 1942 as it was loaded onto
a Heavy Tank Retriever M19. Note the horizontal rib on the left rear
bogie bracket, the only such bracket on this tank as best we can tell
from the photos. November 1941 is the earliest we have seen one of these
ribbed brackets on a Chrysler Lee. Counting heads suggests that they
completely replaced the non-ribbed brackets in Chrysler production
around February 1942. Tank C probably arrived at about the same time as
the M4A2s. This Lee can be identified as an M3A4 primarily by the
radiator blister (1) on the engine deck. M3A4 series production
commenced in June 1942 and the evidence suggests that all of them were
built with what we call "M4 bogies" typified by the trailing return
roller (2). The Lee (not Grant) series incorporated ventilators (3) and
eliminated side doors (4) in production around mid 1942.
This photo shows what appears to be an entire battalion's worth of Lees,
that is 50 odd tanks. It is dated simply "August 1942," and has the
terse caption, "View of tanks covered [sic] with tarps." As mentioned
previously, M3 and M4 Mediums were provided with a 12 by 12 ft "Paulin"
as original equipment. There were many complaints regarding its
insufficient size, since it did not cover the whole tank. However, as
best we can determine, a larger tarp was never provided either as "On
Vehicle Materiel" or as a Depot modification. The Lee in the foreground
appears to have a larger tarp, or perhaps two of the 12 X 12 tarps. It
seems to be unique in that it looks to have been repainted in a lighter
color with perhaps some splotches of the original Olive Drive left in
place. Also, we would note that the overwhelming evidence suggests that,
with the exception of the M3A4 Lee, all M3 Medium Tanks were factory
installed with M3 bogies with the return roller directly over the bogie
bracket (1). M3A4 Lees were elongated and had a gap between the
roadwheels of approximately 10 inches, whereas the gap was more like 3
inches (arrow) on other models as seen on this M3. The first production
M3A4s were accepted in June 1942, and we would guess that at the same
time that an M3A4 was shipped to the DTC, a set of "M4 bogies" was sent
there for test on a "regular" Lee. There are a few other photos in this
series. No Registration Numbers are readable, but the tanks can be seen
as early production units, that is with working side doors, M2 75mm
guns, no gyro stabilizer counterweights, twin fixed MGs installed and so
forth. As best we can determine, from April through at least 10 August
1942, the only Lees at the DTC were those of the 752nd TB. So, we would
think that they left these tanks behind when they departed on 29 July
1942. No doubt the unit would have had to turn in "Tally Out" sheets
regarding the condition and the exact equipment inside of each these
tanks. We came across a small number of such sheets at the US Archives,
but we suspect most were discarded as historically unimportant red tape
when the records were turned in to the Pentagon.
One
of the Registration Numbers listed in the 752nd Tank Battalion PCR
document is "USA W-304512," indicating November 1941 acceptance at
Chrysler. As a matter of minutia, we would point out that 304512 is the
RN that can be seen on the M3 Lee "LULUBELLE" in the 1943 film "Sahara."
While the tank's name was likely painted on for the movie, the RN
strikes us as real, that is to say, the one that was painted on at the
Detroit Tank Arsenal. According to Wikipedia, film production began on
29 January and wrapped on 17 April 1943. It was filmed at the
Anza-Borrego Desert State Park near the Salton Sea. The 4th Armored
Division reportedly provided equipment, along with 100 extras. The 4th
AD was posted to the DTC from November 1942 thru June 1943. It is
probable that the Lees in the film, including a few cast hull M3A1s (*),
would have been replaced with Shermans by then. At obsolescence, a good
number of the Lees here and at other bases in the US would have been
rounded up, reconditioned, and converted to T2/M31 Retrievers or Canal
Defense Lights and so forth. It can be seen that "LULUBELLE" was
retrofitted with 2 open grouser boxes (1), rear stowage bins (2), and
the "Quick Fix" exhaust and air cleaner modification (3). The Quick Fix
was Field Service Modification Work Order G104-W16. We suspect the other
mods were also provided from kits, probably in the range of FSMWOs
G104-W31, W32, W36 or W38. Unfortunately, these are listed but not
described in the M3 Medium Modifications documents we have come across.
We would assume that the FSMWO kits included instruction pamphlets as
was the case with Sherman modification kits. Should any readers have the
relevant pamphlets, we'd be pleased to have a report.
The
records of the 751st Tank Battalion list a Field Exercise on 24 June
1942 at their station at Ft. Jackson, South Carolina. The Exercise was
"for British Prime Minister Winston Churchill, General George C.
Marshall, and other notables...The demonstration was in the form of a
coordinated attack, using infantry, artillery, mortars, air support and
tanks. The tank attack was made in close support of the infantry
following the artillery preparation and air attack. The entire battalion
of tanks was used, and the demonstration was effected with great
success. Mr. Churchill commended the troops involved and expressed
satisfaction at their state of training." Another viewpoint regarding
this demonstration is described in a 2019 article by the
Churchill
Project. "Toward the end of events, Churchill turned quietly to his own Chief of
Staff General Sir Hastings Ismay. “What do you think of it?” Ismay’s
reply was blunt: “To put these troops against German troops would be
murder.” “You’re wrong,” he told Ismay. “They are wonderful material and
will learn very quickly.” Nevertheless, he impressed his American hosts
with the maxim: “It takes two years or more to make a soldier.”" The
photo above was included with the 751st's report of the event. We were
able to read the Reg. Number from the 2nd Lee as USA 304585 (Dec. 1941
production), built one unit before C-15 shown at the DTC in an earlier
caption. In this case, the right front bogie bracket can be seen to be
"ribbed."
Lees in the United Kingdom
As the US Army began to receive the new Lees in the late Summer and Fall
of 1941, others were set aside for Lend Lease. The British were very
impatient to receive some M3 Mediums, the Grants in particular, for
examination and evaluation. Their internal correspondence even includes a
little verse/song entitled "Where Are the Tanks?" In August 1941, it
was reported that 3 of the first Pullman Grants (T-24190-92) had been
shipped to the Middle East. The fighting front was given top priority,
and all but 3 of the 309 radial based M3 Grants produced in 1941 were
supplied to the Middle East. The buildup was slow since many of the
early production Grants shipped were incomplete, missing guns and radios
and so forth. On December 16, 1941, 10 "Mediums" were listed in the
Middle East - "five of which are at Schools...five in workshops awaiting
issue." These "Mediums" would have been Grants, since the first 7 M3
Lees were reported "On Ship Awaiting Sailing...as at December 19, 1941."
The first M3 Mediums with "American turrets" ("AT" as opposed to "BT")
that the British actually received were shipped to the UK, and it would
appear that, initially, mostly ALCO Lees were set aside for the UK,
while mostly Baldwins were allocated to the Middle East. The first 20
units to the UK appear to have encompassed the entire July production at
ALCO (SNs 1695 - 1711) with a few more from August. In the absence of a
Tank Depot system, they were processed for Lend Lease shipment at
Aberdeen Proving Ground. It is thought that the first 11 sailed on the
Empire Faith in mid-September. A clue about when they arrived may be had
from a Department of Tank Design Field Trials Report on one of the Lees
shipped, SN 1708/USA 305778, where the earliest results are dated 20
October 1941. The photos above were taken at the DTD test facility at
Farnborough and provide two views of 305778. It can be seen that the
tank was received as built, and in the rush, it appears to have been
shipped without pioneer tools. General Steel provided the 2-ton Lee
turrets to ALCO and Baldwin, and these castings featured the most
prominent "bump" (1) just below the commander's cupola. USA 305778
"still" had the fabricated antenna base (2). The fire extinguisher pull
handle housing (3) is either covered over or mounted facing down. The
Lee design did not incorporate sand shields. It featured rubber mud
flaps (4) from start to finish. Of course, the British requested that
the same type of sand shields that had been designed for their Grants be
installed on to their Lend Lease Lees before shipment. The US would not
agree to incorporate sand shields in production but did agree that they
could be retrofitted at Tank Depots when they came online and got up
and running.
By
the end of 1941, a total of 59 M3 Lees and 3 Grants had been exported
to the UK. The 5th Canadian Armoured Division arrived in England in late
November 1941. The intent was to equip the Division with "Canadian M.3
Med." [Rams]. The Ram, like the Sherman was designed with the main gun
mounted in a revolving turret, thereby correcting the major flaw of the
M3 Medium. Ram production commenced in December 1941, and it was
estimated that 382 would be completed by June 1942, all of which were
allocated "to United Kingdom for 5th Canadian Armoured Division and
training." In the meantime, a few of the mechanically similar Lees were
on hand to serve as substitutes. The 8th New Brunswick Hussars may have
been first to receive the new tanks. The first notation of "Tank (Medium
M.3)" in their War Diary comes on 2 December 1941 when USA 305768 and
USA 305781, both ALCO, July 1941 production, were reported to have been
allotted to A Squadron. USA 305826 was issued to A Squadron on 31
December, and USA 305828 and USA 305815 were issued to B and C Squadrons
respectively on 5 January 1942. These 3 would have been ALCO, September
1941 production. On 5 January, the Diary contains the list (inset)
reporting that replacement of the USA Registration Numbers with British
War Department Numbers (in the T-788XX range) "has been completed." In
general, US vehicles allocated to British Lend Lease had their War
Department Numbers assigned and painted on in the US during processing,
but here we have a rare instance in which the T-Numbers were only issued
after the tanks had arrived at their destination. In any case,
combining the USA Numbers on the list with 305826, 305828 and 305815, we
can assume that the 8th NBH had at least 9 Lees in early January 1942.
Note that there is a single Baldwin M3 on the list, USA 305104
(October 1941 production), renumbered to T-78864. Except for USA 305817
assigned to B Squadron and 305475 to A Squadron on 6 January, there are
no apparent further allotments of M3 Mediums through to the end of
February 1942. Our interpretation of the records is that the "War
Establishment" for "cruiser tanks" would have been about 54, but the
8th NBH never had more than a dozen M3 Mediums including one or two
Grants. Towards the end of February, it is mentioned that 40 Canadian
"Ram" tanks "would soon be made available to the division" [5th Canadian
Armoured]. The photo above is dated 21 February 1942, and captioned in
part, "A Canadian Armoured Division are finishing [sic] their training
in this country with American M3 Medium Tanks manufactured in Detroit
[sic]." The lead tank can be seen as USA 305811, indicating that it was
accepted in September 1941, and built by ALCO whose plant was in
Schenectady, New York. Again, we see a few "missing rivets" on 305811.
The
Library and Archives of Canada
holds an extensive collection of photo albums detailing the WW II
activities of the Canadian Army. In one series dated 25 February 1942,
five "as built" Lees are shown. The notations at the bottom of the
album pages read, "American Tanks used by G.G.H.G. 3.Cd. N.B.H.
Frensham Hants." We translate this as "Governor General's Horse Guards"
which at the time was the 3rd Canadian Armoured Regiment of the 2nd
Armoured Brigade, 5th Canadian Armoured Division. "N.B.H." is also
tacked on, and we translate that to be "[8th] New Brunswick Hussars"
which at the time was the 5th Armoured Regiment, 2nd Armoured Brigade.
The location is given as "Frensham Hants" which we interpret to mean
that the tanks were photographed on Frensham Common, a recreational
area situated mainly in the County of Surrey in southeast England.
During WW II, the Common was converted to a military training ground,
and its two lakes "were drained as otherwise they would have provided
markers for German bombers." On 24 February 1942, their War Diary
reports, "8 NBH will supply 4 M.3. Med Tanks for the demonstration...at
Frensham Common." The detachment would be under the command of "Capt.
Olgilvie of GGHG." We would theorize that the Lee in the foreground was
Capt. Olgilvie's tank and was USA 305811, and that the other 4 were
those supplied by the 8th NBH. Both still and motion picture footage
was shot on that day, and part of the idea was to create the impression
that the maneuver featured a large number of tanks, although as best we
can determine, only 5 Lees took part. We have examined quite a few of
the images, and only one Lee appears to have had a USA Registration
Number, while the others had British WD Numbers painted on as seen on
the two tanks in the rear on the right. For a little background, note
that at the urgent request of the British, the Canadian Army deployed
to England, and with most of the British Army serving on the fighting
fronts, "From the autumn of 1941 to early 1944 the defence of the UK
and particularly the Sussex coast was largely in the hands of the 1st
Canadian Army."
As the shipping situation improved, the UK received additional M3
Mediums starting in late February 1942, around the same time as the
commencement of the first exports to India and Australia. Ultimately 119
new production radial engine Lees and 97 Grants
were shipped to Great Britain as Lend Lease. The Canadians don't appear
to have been issued that many of these, but there are very few photos
of Grants or Lees in British service in the UK. Textual listings suggest
that some were issued to the (British) 52nd
Training Regiment at Bovington Camp and the AFV School Gunnery Wing at
Lulworth Camp, both in Dorset. Counting heads suggests that most of the
Lees shipped to England were allotted WD Numbers in the range from
T-78847 up to about T-78957, but a few have been
noted in the T-26XXX range. The photo shows a pair of Grants and a Lee
being offloaded at a port in the UK, 29 June 1942. The M3 Lee can be
seen as USA 309884, indicating April 1942 acceptance at Chrysler. It
seems pretty certain that the Lee was intended
for Commonwealth Lend Lease as it was shipped without the machine gun
cupola as the British requested. Thus, it would appear to be another
example where the tank arrived without having a British War Department
Number painted on in the US. This Lee can be seen
with the longer M3 75mm gun, and the air cleaner and side plates of the
"Quick Fix" modification. The suspended Grant is T-24595, which would
have been accepted in May 1942. Both it and the other Grant "still" have
the original pepper pot exhaust. IWM H 21046
via Peter Brown.
The
Department of Tank Design in Great Britain introduced an extensive
series of interior and exterior modifications to the M3 Medium, both Lee
and Grant. The sketch above shows the external mods for the Lee. The
British attempted to use "friendly persuasion" and request that a number
of these changes be introduced into Lee production. They had some
success in that, toward the end of production, the US did provide and
install the Grant type commander's hatches, sand shields and driver's
periscopes to Commonwealth Lend Lease Lees. In the back and forth, US
Ordnance at least indicated a willingness to install some of the other
items on the condition that the British provide them to US Tank Depots
as free issue. Of course, the Brits were not in the position to do that.
In
the end, changes such as armor protection of the air intake on the
engine deck (highlighted in red), auxiliary petrol tank (highlighted in
blue), smoke dischargers and the various stowage bins, including one
that held "Cover, 75mm Gun & Mounting," would have
to be added in Britain. Period photos show that some of the 97 Grants
and 119 Lees in the UK were modified with these changes, although the
exact number is not known. Furthermore, some of the UK modifications are
noted to have been retrofitted to Lees in India and Australia.
A
modification not shown in the "General Lee I Stowage Sketch" is
"Camouflage Net Bin" on turret. This appears in a few photos as seen
above, but, in late May 1942, it was directed to be removed, "In view of
damage caused to wireless aerials through fouling by the camouflage net
bin mounted on the rear of the turret of modified General Lee tanks."
Note the two wire-like pieces that join to the box. It is assumed
that these were to deflect the aerial(s) before they were fouled by the
box when the turret was rotated. Apparently, that didn't work, so the
box was ordered removed. We would point out to readers that the stowage
sketch does include a camouflage
net bin on the right front fender. Oddly, in most of the few photos we
know that show the turret bin, the right front bin is also present.
According
to The Library and Archives of Canada album notation, this photo was
taken in Pembroke, Wales on 23 July 1942, and is described as "General
McNaughton watches tanks firing guns. Andrew McNaughton was commander of the 1st Canadian Army
then building up in the UK. In those dark days for the Allies, his
declaration that "the Canadian Army in England is a dagger pointed at
the heart of Berlin" earned him a cover story in Time Magazine on 10
August 1942. This was followed a few days later by the debacle at
Dieppe, where, within the space of 10 hours, over half of the raiding
force of 6000 men, primarily Canadians, were killed, wounded or taken
prisoner. In the meantime, according to "Fifth Canadian Armoured
Division: Introduction to Battle," "Equipping the division was a slow,
drawn out process. By the end of July 1942, 5 CAB had received only 40
per cent of its tanks, a motley mixture of American General Lees and
Stuarts, along with a few Canadian-built Rams which were to be the
formation's main battle tank. Not for another year were sufficient Rams
available to fill the divisional establishment and, as a result,
training suffered." The photos in the McNaughton series primarily focus
on a few Ram Is with 2 pounder guns. The subject photo appears to have
been the last on the film roll and strikes us as the best composition of
the lot. It was actually released for publication. It seems likely that
General McNaughton wanted to see a demonstration of the 75mm, since
there would have been combat reports regarding the performance of the M3
Medium in North Africa by that time. The tank in the foreground is
T78860, reported in the War Diary of the 8th NBH for 5 January 1942 as
renumbered from USA 305821. We would assume that, at some point, it was
sent out for UK modification, including the full suite of stowage bins,
the auxiliary petrol tank and mud chutes. The bin on the left sponson
would have displaced the Lee's antenna base, and it can be seen that the
aerials have been repositioned to the left front just above the
location of the radio. By the single aerials and the ferruled look of
them, we would guess that these tanks were outfitted with US radios. The
rather large tarp draped over the 75mm gun sponson is present in a few
more period photos of Grants or Lees in the UK. We would assume that
this is the "Cover, 75mm Gun & Mounting" listed in the Lee diagram
of the "Stowage Sketch" caption. Based on their absence in photos, it
would appear that the British were not able to produce such mods as the
Grant type commander's hatch, sand guards and the armor protection of
the air intake on the engine deck. The Lee modification program seems to
have commenced in earnest in the Spring of 1942. In the Canadian photo
albums, the earliest appearance of a UK modified Lee is at Aldershot on 7
April 1942.
As the Sherman became available in 1942, the British ordered thousands
of them as Lend Lease. However, they were not quite finished with the
Lee. The final allocation of the M3 Lee (specifically) to the Brits was
in March 1943 for 252 units. These would have been used or unissued
units available at various Army facilities in the US. Officially, they
were not remanufactured. However, according to an Ordnance Dept.
Memorandum dated 23 July 1943, "252 reconditioned Medium Tanks M3 have
been received at Chester Tank Depot." Between 15 June and 22 July, 150
were reported to have been shipped overseas. The British must have
really wanted these by then obsolete tanks, since they would have had to
sacrifice some of their limited shipping capacity to place this order.
We can only assume that the Lees were desired for the "Most Secret"
Canal Defence Light conversion program. The "Tank State (United Kingdom)
...as at 31 December 1943" lists "123 Grant/Lee 75mm" with 21st Army
Group. An additional 241 were with Training Units, 6 in Establishments,
and 36 in Ordnance Depots. Thus, we have a total of 406 "Grant/Lees" in
the UK at the end of 1943. This figure should include the 119 Lees and
97 Grants shipped new to the UK in 1941 and 1942, minus "wastage," plus
most or all of the final 252 Lend Lease Lees. At that time, the British
reported that they had about 4000 Shermans in the UK as part of the
buildup for the Normandy Invasion. Here we have one of the few known
photos of a British converted CDL. The presence of the "comb" or "pawl"
device (circled) typical
of those designed and used by the Chester Tank Depot starting in late
1942, would lead us to suspect that this unit was converted from one of
the 252 "reconditioned" Lees, since there is no evidence that the new
production M3 Mediums that were shipped in 1941 and '42 ever had such
combs. The M4 bogies are a curious addition, particularly because they
feature "upturned" return roller arms, which did not enter the Sherman
production pipeline until late 1943, well after the final 252 Lees had
been shipped. We suspect that this unit was shipped with M3 bogies and
the M4 type were retrofitted by the British during the CDL conversion.
The photo above shows what is thought to be the world's only surviving,
intact Canal Defence Light based on an M3 Medium Tank. It is on display
at the Armoured Corps Museum in Ahmednagar, India, and was photographed
by our world traveling friend Jim Goetz. We have included it in the
"Lees in the United Kingdom" section because, no doubt, this would have
been one of the 36 CDLs of the 43rd Royal Tank Regiment that arrived in
India from the UK in August 1945. It was planned that the unit would
take part in the final offensive in Southeast Asia, the recapture of
Malaya and Singapore. However, the Japanese surrendered shortly after
the Regiment arrived. As with "Giraffe" in the last caption, this tank
can be seen with the Chester Tank Depot "comb" (1) along with a metal
strip (2) that the Depot added to hold a "zinc tag" stamped with
instructions on how to use the comb. The tag is reported to have read,
"NOTICE - Do Not Open Door - Unlock Cable to Release Brakes - Reset
cable when tank is in position." Again, the comb suggests that it was
another unit converted to CDL from one of the 252 "reconditioned" Lees. A
memo to the Commanding General at Rock Island Arsenal dated 29 March
1943 with the subject "Overhauling of Tanks, Medium, M3" provides
"guidance in the modifications to be applied on the 126 Tanks, Medium,
M3, to be overhauled and shipped from your arsenal." The RIA location
suggests that this work was being carried out for British Lend Lease and
not for other conversions involving M3 Lees such as T2 Tank Recovery
Vehicles [M31s] or US built CDLs labeled "Shop Tractor, T10." Perhaps
coincidentally, 126 is exactly one half of the 252 Lend Lease Lees that
the British requisitioned in early 1943. The memo lists a number of
Field Service Modification Work Orders that were to be applied to these
tanks. The FSMWOs included extension of the driver's control levers,
application of spacers to raise the return rollers, exhaust deflector
shields, blackout driving light, the "Quick Fix" exhaust and air cleaner
mod and FSMWO G104-W27 which "Installs No. 25 jet in carburetor to
permit use of 80 octane fuel." The implication is that R975-EC2 engines
would have been used, with the above modifications added if needed, and
we can't help but think that, where necessary, the engines would have
been reconditioned or taken from new old stock. As best we can
determine, the only M3 Mediums built with R975-C1 engines would have
been Lees from the last few months' production at Chrysler, and there
are a couple of mods listed in the memo that apply to the R975-C1. Note
that the blackout driving light (3) is seen on this example, but not on
"Giraffe" in the previous caption. This item was released as Field
Service Modification Work Order G104-W45 on 4 May 1943. It has been
noted on US built CDLs but not on T2 Tank Recovery Vehicles. Even though
Commonwealth forces in Burma fought with M3 Mediums almost to the end
of WW II, we doubt if any of the blackout light mod kits were shipped
there, since we haven't been able to find any period photos that show
them retrofitted.
In this view of the right side of the CDL, there is another
modification that was listed in the RIA memo. G104-W15 was released on
23 February 1943 "To increase the clearance between the track support
roller and the suspension bracket by installing a spacer A295847 [Part
Number]." The inset on the left is from the FSMWO and shows the
instructions for adding the spacers, one of which we have highlighted in
red. The inset on the right is a close-up view of the original return
roller configuration alongside the modification. Although no reason is
given in the FSMWO for retrofitting this mod, which required 12 hours to
complete, it can be seen that, in the original configuration, there is
very little space between the bottom of the return roller and the bogie
bracket. It seems likely that mud and debris could get lodged in and
freeze up the return rollers. This particular FSMWO applied to M3s and
M4s that were outfitted with M3 type bogies. A similar Modification Work
Order was released in July 1943 that applied to all AFVs that used M4
type bogies with track skids and trailing return rollers. The spacers
rarely show up in period photos of M3 Mediums, probably because of the
late date of the FSMWO. They do appear to have been mandated on T2 Tank
Recovery Vehicle conversions. The turretless ex-CDL on display in La
Hore, Pakistan strikes us as another example of a conversion based on
one of the reconditioned Lend Lease Lees, and we would observe that it
also has the blackout light and spacer modifications. Jim Goetz was not
able to read the serial number of the Ahmednagar CDL, but by the
appearance of the bogie brackets we would guess it was a 1941 production
Chrysler Lee.
In this rear view of the Ahmednagar
CDL, we can see another modification that was listed in the RIA memo,
G104-W23 released November 1942, "To install a deflector shield to
eliminate the danger of brush fires." Before seeing the FSMWO, we
thought that this might have been a substantial exhaust deflector such
as used on M4 and M4A1 Shermans, but it turns out that it was just a
pair of 9 3/4 inch wide plates that were welded to the bottom of the
"fishtail exhaust tubes" as shown in the inset. We can't say that we
have seen these in any period photos, but then they wouldn't be the
easiest things to pick out. In fact, as far as we can tell, the
Ahmednagar CDL is the only surviving M3 Medium that has the kit
supplied exhaust deflector shields. Of course, the RIA memo directed
the installation of the "Quick Fix" exhaust and air cleaner
modification, G104-W16 released 4 July 1942. No doubt this was the most
widely distributed of the visible M3 Medium FSMWOs. The kit included a
pair of door stops (1) to prevent the engine access doors from damaging
the new air cleaners. Fittings 2 and 3 appear to have been for a
vertical mounting of the British leaf spring towing pintle. This was
likely installed in the UK during the CDL conversion. Additionally,
what little evidence there is suggests that the armor protection of the
air intake (4) was retrofitted during the CDL conversion. The
small square plates (circled) are seen in a few period photos and on a
few surviving M3 Lees, but their purpose has eluded us.
Anyone? With thanks to Kurt Laughlin for providing the M3 Medium
FSMWOs.
Germany
declared war on the United States on 11 December 1941, four days after
the Japanese attack on Pearl Harbor. Shortly thereafter, Prime Minister
Winston Churchill and President Franklin Roosevelt got together at the
"First Washington Conference," code-named "ARCADIA." Major issues like
strategic goals ("Germany First") and Allied Command structure were
addressed, but along with these, it was agreed that 3 US Infantry and 1
Armored Division would be deployed to Northern Ireland. As with the 1st
Canadian Army stationed in southern England, this would free up British
troops for overseas service, while providing for local defense and
continued training. The 34th Infantry Division was the first to arrive
on 26 January 1942. On 16 May, initial elements of the 1st Armored
Division arrived, "including over 200 tanks." The Division was ordered
"to occupy Dundrum Bay, Ballykinler and Newcastle in County Down." By 13
June 1942, "the 1st Armored Division in Northern Ireland has received
the last of its tanks." At this time, the 1st AD was a "heavy armored
division," which on paper had 232 Medium Tanks (M3 Lees) and 158 Light
Tanks (M3 Stuarts) in 2 Regiments (1st and 13th), each of which had 1
Light and 2 Medium Tank Battalions. The photo above is dated 28 June
1942 and shows a training exercise at Ballykinler Camp. The
evidence suggests that the Lees shown here were serving with the 13th
Armored Regiment, since they were stationed at Ballykinler from May
through October 1942. These are not the same early production Lees seen
with the 1st AD in the stateside Maneuvers photos. Rather their
appearance, with counterweighted M2 (1) or the longer M3 guns (2),
"ribbed" bogie brackets (3), and at least one example with pressed metal
road wheels, suggests February through April 1942 production. For
instance, the tank in the foreground can be seen as USA 309554,
indicating a March 1942 Chrysler. Since the stateside Maneuvers, the 1st
AD had adopted tactical markings of geometric shapes, but these have
been censored out in this image. However, in some
Movietone footage of
this scene, the symbol was not censored and corresponds to H
Company, 3rd Battalion, 13th AR as shown in the inset of our next
caption. The infantry men can be seen with WW I type "doughboy" helmets.
Note that this exercise included the use of gas masks. Poison gas was
not employed by the combatants during WW II although stockpiles were
maintained for deterrence, a kind of "mutually assured destruction"
deterrent.
The photo above was "Not to be
published before evening papers of Saturday August 15, 1942." It is
captioned, "A combined U.S.A. and British exercise was carried out in
Northern Ireland in which General Grant and General Lee tanks took
part." If there are any photos showing Lees with Grants
in Northern Ireland, we have not come across them. Anyone? The
tactical markings used by the 1st AD at this time and into the campaign
in Northwest Africa have been a subject of interest among restorers and
modelers. It was not censored in this case, and this particular
symbol (inset) has been identified by author George Bradford to have
been that of E Company of the 2nd Battalion of the 13th Armored
Regiment. The Lees of D and E Companies were famously photographed
with their crews in Tunisia in late November 1942. Perhaps this
tank, with the addition of rear stowage bins, was one of
them? The ribbed bogies suggest that this Lee was produced
by Chrysler. We take the counterweighted guns to be an indication of
the fitment of gyrostabilizers. These are said to have been factory
installed on Lees around the beginning of February 1942. This example
can be seen with both fixed machine guns installed.
Elements
of the 13th Armored Regiment, including the 1st Battalion (M3 Lights)
and 2nd Battalion (M3 Mediums) were assigned to Combat Command B, 1st
Armored Division, which was slated to take part in Operation Torch, the
invasion of Northwest Africa. The Regiment left Northern Ireland in
October 1942 and deployed to a staging area in England near the port of
Liverpool. In his memoir, then Col. Paul Robinett, commander of the 13th
AR, records that, "The days in the staging area were ones of intense
activity. Our tanks had seen hard service and were not in good
mechanical condition. The men worked hard overhauling engines, changing
tracks, and doing many other things that had to be done to put the
vehicles in the best possible mechanical condition." Furthermore,
Robinett states that "our vehicles would have to traverse salt water
during the landing...Waterproofing was therefore mandatory, but the
United States Army had not developed the technique." (Robinett was
apparently unaware that techniques were developed for Operation Torch
vehicles shipped from the US.) In any case, his tanks, etc. were
"waterproofed" under the supervision of British Army specialists from
their Amphibious Training Center. We don't know of any photos showing
the unit's waterproofed Lees, but above are 1st AD documents detailing
the materials required and a "Primary De-Waterproofing of
Vehicles...Tanks" instruction handed out to crews on the day before the
assault landings. From these, our impression is that the air intakes on
the engine decks were simply covered and sealed, and that "exhaust
chutes" were affixed to the rear of the tanks. The chutes apparently
required 3 and 3/4 steel sheets measuring 1/8 inch by 3 ft. by 6 ft. An
extended engine hand crank was needed, which suggests that the chutes
were at least as high as the upper rear hull plates. Indeed, in his
notes, then Captain Henry Gardiner of HQ, 2nd Battalion states that
"Civilian workers were brought in to assist in welding "stacks" to the
back decks of all tanks. These served to carry the exhaust gasses up to a
level above the deck of the tank so that the motor would not be
affected by submerging to a depth of eight feet. The ports, hatches and
gun embrasures were all sealed up to make the tanks waterproof to the
point that they could be landed in the water and driven ashore under
their own power." A CCB HQ Report dated 22 December 1942 states that
during the landings, "One medium tank was put into water which lapped
the bottom of the turret, (about 9 feet) and made the trip to the beach
successfully." It was stressed that the "oil silk" or rubber over the
engine air intake must be removed immediately upon landing, otherwise
the engine would be damaged by overheating, and/or fires might ensue.
This Signal Corps photo is dated 5 December 1942 and shows a heavily
armed Santa Claus arriving on an M3 Lee named "Buccaneer" in order to
deliver presents to some English children. Santa is played by Sgt. Hiram
Prouty of Baltimore, Maryland, described in the caption as "a member of
the 175th Inf." The 175th Infantry Regiment was a Maryland National
Guard unit that was federalized in early 1941. It became part of the
29th Infantry Division composed of Guard formations from Maryland and
Virginia. The Division arrived in the UK in October 1942 and trained
there for the next 20 months. The Division's 116th Infantry Regiment,
composed of Virginians, has the distinction of having been part of the
first wave on Omaha Beach on D-Day. The location is given in the caption
as "Perham Downs [sic], England." (Perham Down is a village in
Wiltshire, England, in Tidworth parish.) The tank commander is not named
but it is stated "M.3. Tank of 1st Tank Group." As best we can
determine, the 1st Tank Group included the 751st, 752nd and 755th Tank
Battalions (Medium), all of which arrived in the U.K. in August 1942 and
took up training in the area around Tidworth Camp in the south of
England. At that time, a Medium Tank Battalion consisted of 54 tanks, 3
in HQ Company, and 17 each in 3 Companies, generally A, B and C.
"Buccaneer" can be seen to have "B-17" painted on the left side of the
differential housing. We would remind readers that, on a tank, left and
right are determined as if one were sitting in the driver's seat.
In this view, the tank "driver" is named in the caption as Sgt. Claud
Brunes of Seattle, Washington. Sgt. Brunes is listed in a B Company
roster in the souvenir history of the 752nd Tank Battalion. Combining
this photo with the previous, we were able to determine that the
Registration Number of "Buccaneer" was USA 3028835 indicating June 1942
acceptance at Chrysler's Detroit Tank Arsenal. A March 1942 stowage
diagram has it that item 1 was a "Box for 13 grousers." No quantity is
given for a similar grouser box on the hull roof (2), but it appears to
be about the same size, so we would assume that it held 13 as well. This
would put the M3 Medium in line with the M4 which carried 26 grousers.
We have yet to learn exactly where they were stored before the advent of
the external boxes in May or June 1942. Recall that the Technical
Manual does not give the number of grousers and simply states that they
were stored "In tank...in the most convenient places available." Note
that the factory installed grouser boxes had lids.
Here
we have another photo of "Buccaneer" with a different man in the
commander's hatch, identified in the SC caption as Capt. Peter Meshkoff
of Rockford, Illinois. Earlier we mentioned that Russian born Captain
Meshkoff was the commander of B Company, 752nd at the time. It can be
seen here that there was no pistol port on the left side of a "no doors"
Lee. Several of the press photos describe the "action" at Perham Down
as a "radio training exercise" but oddly, "Buccaneer" does not have an
antenna mounted, and Capt. Meshkoff is "going old school" by "waving
flag signalling [sic] tanks to begin maneuvers."
We
first encountered the unusual name "Buturlinovka" on M3 Lee USA 304367
at the Desert Training Center. Here we have "Buturlinovka III," USA
3028826 a June 1942 Chrysler like "Buccaneer." In this case, the Signal
Corps caption does not name the tank commander. He might be Capt.
Meshkoff without his spectacles or perhaps Meshkoff was in command of
"Buccaneer" on that day as suggested by more than one photo. At any
rate, the tank directly behind can be seen with the "Speed Number" 6
(arrow) painted on the rear of the turret. In another photo in the
series (inset) "Buturlinovka III" is seen with a "2" painted on the rear
of the turret, and in still another, where Capt. Meshkoff is standing
on her, she is seen with "B-2" painted on the left side of the
differential housing. There are a fair number of Signal Corps and press
photos that depict the tank exercise at Perham Down on or about December
5. After analyzing them, we would conclude that the first line of Lees
seen here with what we might call "the final features," were serving
with B Company of the 752nd TB, while the M3s behind were with B Company
of another Tank Battalion.
The photo above shows what we believe were the "other" B Company Lees
seen behind the 752nd's tanks in the previous photo. In this shot, note
how the "Speed Numbers" are brightly painted on the rear of the turrets
of the Lees in the front row. Also, notice that, unlike the back row,
the front row Lees do not have stripes around their turrets. "Baby Boy"
can be seen as USA 309689 indicating March 1942 Chrysler production. The
back row tanks are somewhat earlier Lees with working doors and no
ventilators. It has been difficult to "count heads" on the factory
introduction of the rear stowage boxes because of photos like this, but
our interpolation is that they were not introduced in production until
June 1942. Thus, it is our theory that the boxes seen on the 2nd row
Lees are retrofits from a modification kit or alternatively, they were
fabricated in theater from an Ordnance Dept. supplied pattern. Wooden
crates are mounted and tied down on top of the stowage boxes. These
appear to have held 20 five-gallon jerry cans. This strikes us as an
awful lot of weight to put on these sheet metal stowage boxes, assuming
the cans were filled. In the event the crew would need to access
something in a stowage box, the jerry can crate would present a great
obstacle. We suspect this was more of a traveling or shipping
configuration with empty cans. "Baby Boy" can be seen equipped with a
single, "no lid" grouser box affixed to the hull roof. We believe that
the grouser boxes were retrofits on the back row Lees as well.
In
this view, we see "doored" Lees with striped turrets. The lead tank
appears to be named "Blitzen" and have "B-6" painted on the center of
the differential housing. The Registration Number may be USA 309652
(March 1942), but it is not entirely clear due to "motion blur." Note
the wooden crate atop the stowage boxes. A single, "no lid" grouser box
is mounted on the hull roof. A single, open grouser box is also present
on B-7, but it is mounted on the front plate. Other photos in the series
suggest that the location of the grouser box was one or the other, but
not both. As researchers trying to identify the units, we regret that
the participating Battalions didn't simply paint on unit IDs, like "752
Δ" on their tanks. Instead, they are seen with the infamous
"Preparation for Overseas Movement" unit serial number and bar code
(circled) stenciled on the right side of the differential housing.
Not
to belabor the point, but to show that there were indeed elements of at
least two Tank Battalions of the 1st Tank Group present at Perham Down
on December 5th, here we have "B-7" of what we believe was the 752nd TB.
The location of the company letter and tank number on the left side of
the differential housing, and the overall later "look" of the Lee can be
contrasted with the B-7 shown in the previous photo. The caption of
this photo reads in part, "It can now be revealed that the General Grant
[sic] tanks, which played so large a part in the recent rout of Rommel
are now in England in vast numbers. Many of these American tanks, manned
by American crews, were seen in action "somewhere in England" last
week." No doubt the "vast numbers" were meant to reassure the British
people, but a second purpose would have been to deceive the enemy. The
1st Tank Group was deployed to Northwest Africa about a month later to
reinforce US Troops fighting there. Again, we see the "Preparation for
Overseas Movement" or POM code. Interested readers might want to have a look at this link. The inset is from a Signal Corps photo that shows tank B6 of what we believe was a 752nd TB Lee. Note
that there is a small number/letter combination stenciled above the top
color bar. This is the 5-digit serial number assigned to this
particular unit. When
we showed this to Bob Holt, he replied, "The 752nd POM code was indeed
9190-L. This code appears in several 752nd photos and it also appears in
a few 752nd documents and in my dad's personal paperwork. I have seen
this code on both C and B Company tanks, as well as on battalion-level
documents. The bar colors for 9190 would be white-brown-white." We would
guess that this unit serial number plus bar code system was
stenciled on the equipment of the 1st Tank Group before the Lees, etc.
were shipped to the UK in the same convoy in September 1942. Presumably,
the other Tank Battalions of the 1st Tank Group would have been
assigned their own unit serial numbers, and Bob Holt informed us, "I've
seen three different POM codes in various photos in England - 9188,
9189, and 9190." It would be our guess that the Battalions were
instructed not to paint regular tactical markings like "752 Δ" on
their equipment in order to keep the enemy from "counting heads."
Readers
might be wondering why our photo selection shows mostly Chrysler M3
Lees, that is, those with radial engines and riveted hulls. The answer
comes down to sheer numbers. The Detroit Tank Arsenal produced 3243 such
units, while ALCO only produced 385 M3 Lees and Baldwin a mere 84. Here
we take a little detour from Perham Down in December 1942 back to the
Detroit Tank Arsenal around midyear. The massive plant was still under
construction at the time as evidenced by the incomplete section on the
right in the photo. Quite a few Registration Numbers are readable, with
all of them indicating Lees accepted in June 1942. Most of the tanks are
"no doors" Lees, but a few, such as USA 3010618 (1), can be seen with
welded on side doors. Of interest is that the pistol port (circled) is
open, that is, working on 3010618. When the doors were eliminated, the
original intent appears to have been that "a pistol port with
protectoscope must be placed on each side of the hull in approximately
the same location as the eliminated escape doors." As is evident by the
many Lees with solid armor left sides in this photo, the pistol port on
the left was quickly deemed unnecessary and dropped from the design.
However, there is some small evidence that a few "welded door" Chrysler
Lees may have been built with working pistol ports on both the left and
right sides (inset). The use of rivets to fill in the welded doors' hinge holes is observed as well. Unfortunately,
at present, we don't know of any surviving examples with these
features. The longer M3 75mm guns are in the majority in the shot, but
there are "still" some M2 guns with counterweights (2) present. The M3
was developed for the Sherman series to provide an increase in the gun's
muzzle velocity. The Sherman had priority for these, but it appears
that Chrysler alone was able to arm some of its Lees with the longer
gun. By mid-1942, the R-975-C1 radial engine was in production. This
featured the high exhaust pipes and external air cleaner set up as used
on all but the first few radial engine Shermans. Some of the Lees seen
here are installed with "squarish" plates (3) in front of the air
cleaners, while others have the original triangular plates (4). It seems
a bit unnecessary, but the rear stowage bins can be seen with the word
"Stowage" (circled) stenciled on them. For future reference we would
note that the stencil is in a dark color. A few M3A4s (5 & 6) are
visible. These are characterized by M4 bogies and a lack of rear stowage
bins and grouser boxes. Note the Lee on a railcar completely covered by
a tarp (7).
This photo is dated 17 June
1942 and shows a completed "General Grant" [sic] undergoing a
run-in on the test course at the Detroit Tank Arsenal.
Despite the fact that we don't know of any surviving examples, we
offer this photo as further evidence that Chrysler used rivets to fill
in the hinge holes (circled) on at least some of the Lees it built with
welded-on side doors. This stands in contrast to Baldwin Locomotive,
which appears to have attempted to fill in the hinge holes so that the
exterior surfaces of the welded-on doors were more or less
flat. We might assume that the final 25 M3 Lees that ALCO produced
in July and August 1942 had welded-on doors or no doors like their
M3A1s, but we can't say for certain or comment on the appearance of the
welded-on doors, since there don't appear to be any period photos or
surviving units.
This APG photo is dated 17 September 1941 and shows the M3 Pilot with
"Three Ventilators for Medium Tank, M3." The ventilators don't appear to
be welded on, and they may be wooden mock-ups, but the photo does show
that ventilators were planned early on. The idea to mount a ventilator
(1) on the top hull hatch was obviously not adopted. Comparing this
photo with the earlier DTA factory floor image, it can be seen that the
positions of the other ventilators were changed slightly. As best we can
tell from counting heads, at least with Chrysler Lees, ventilators were
introduced in production in May 1942 at around Serial Number 3500/USA
3010135. In July 1942, our old friend Sedgley Thornbury, now a major,
tried to do a little counting heads himself regarding the intro of the
vents. We agree with his conclusion: "The installation seems to be
confined to tanks of the seven digit serial number." (Of course, he was
actually referring to seven-digit Registration Numbers, a few of which
he cited.) The grouser boxes appear to have been introduced a little
later in May and the rear stowage bins more towards the end of the month
or at the beginning of June. And while we suspect that field
modification kits were issued for the grouser boxes and stowage bins, we
don't find any evidence that that was the case with the ventilators.
Grants were not installed with this type of ventilator. Instead, they
appear to have been equipped from the start with a blower fan mounted on
the left front pistol port. For a little context, we would mention that
the first Sherman was accepted on the last day of February 1942, and it
was equipped with this same type of round ventilator as were all
succeeding units. The overhead view of the pilot featured earlier on
this page showed a much larger dust cover for the 75mm gunner's
periscope than the neat little zippered job (2) seen here. Some fittings
(3) have been added, suggesting a dust cover was planned for the 37mm
gun. As mentioned earlier, the only Ordnance or factory type photo we've
encountered that shows a dust cover on one of the main guns (the 37mm)
is on one of the last DTA Lees, USA 3058309. Just visible here is a
small strip (4) welded around the indirect vision device casting of the
driver's door, suggesting that it may have been intended to provide a
cover. As best we can determine, this strip was never factory installed.
However, a similar strip has been observed around the driver's
protectoscopes on a few surviving Grants in India and Australia. The
inset shows the strip on a WW II combat casualty monument on display in
Kohima, India. In his book, "M3 Lee/Grant," David Doyle relates that, in
March 1942, the Waterhouse Company of Webster, Massachusetts was
contracted to produce 700 sets of 7 types of canvas covers for the M3
Medium including ones for "Cover, 37mm., Gun Plate" and "Cover, 75mm.,
Gun Periscope Sight, M1." These were to be attached to "steel frames"
provided by Waterhouse and tack welded on to the tank. We would note
that another of the Waterhouse covers is listed as "Cover, Door,
Indirect Vision." It seems likely that some of these kits were shipped
to India and Australia since their M3 Mediums remained in service until
the end of WW II and beyond.
Lees in the U.S.S.R
The German-Soviet
Pact of 1939 of course ended with the invasion of the USSR on 22 June
1941. On 7 November 1941, President Franklin Roosevelt formally declared
"that defense of the Soviet Union was vital to the defense of the
United States." This made the USSR eligible for assistance under the
Lend Lease Act. The original provision was for $1 billion of supplies
and materiel. The First Protocol included "1103 Tank, Medium - M3
complete with radios, accessories, and essential spare parts." These
were requisitioned by the Amtorg Trading Corp. for delivery starting
November 1941 and ending in June 1942. For shipment, the items were to
be marked, "NKVT-U.S.S.R., Order No. L41223" and "Three sides of each
box [OVM boxes?] should bear a black diagonal line 2-3 inches wide." In
his 2019 article, "The American Highrise," Yuri Pasholok states
that the first 4 units arrived in December 1941, with 2 each being
delivered to the ports of Murmansk and Archangel. After that, shipments
arrived on a regular basis. It should be pointed out that all of the
"Tank, Medium - M3" were Lees with radial engines, although at one point
a British liaison officer in the US noticed some Grants marked for
shipment to the Soviets. He explained that the Grants had been built to
British specifications for British Lend Lease, and the error was
corrected before the tanks left port. During the course of WW II, Lend
Lease materiel was delivered to the Soviet Union along several routes as
shown on the Department of State map above. In the early days, the
"North Russia" or Arctic route to Murmansk and Archangel was primary,
and most or all of the Lees of the First Protocol appear to have been
shipped that way on the infamously hazardous PQ convoys which ran from
September 1941 to September 1942.
What is known about
Soviet use of the Lee and Sherman remains limited, particularly to
Western researchers. In "The American Highrise," Yuri Pasholok writes, "On
May 23rd, elements of the 114th [Tank] brigade crossed the Severskiy
Donets [river] with the 242nd Rifle Division and 64th Tank Brigade and
partially liberated the Chepel village [AKA "Chepil" or Чепіль in
Ukraine]. The village was
fully cleared on May 25th. During this fighting the M3 tank commanded
by Lieutenant A.D. Mimotin destroyed 4 German tanks. Another one
destroyed 3 German tanks, but the crew died in the battle. The action at
Chepel punched a breach in the German defenses and allowed several
units to escape an encirclement." The author does not state it, but this
engagement may have marked the combat debut of the M3 Medium, since the
Grant appears to have had its baptism of fire with the British on 27
May 1942, the second day of the Battle of Gazala. Thanks to the recent
work of researchers like Yuri and Gabor Horvath, it is obvious that, in
many cases, the Soviets used the USA Registration Number for bookkeeping
purposes in their test and combat casualty reports. Most of the few
available photos of Soviet Lees were taken by the Germans, are undated
and uncaptioned, and show destroyed or captured examples. The photo
above is one of a series featuring USA 304850 (turret number 147) which
was captured intact and shipped to the Proving Ground at Kummersdorf,
Germany for evaluation.
In a
couple of the photos, # 147 is shown with the M4A1 "War Daddy II" which
the Germans had captured from the US 1st Armored Division during the
Battle of Kaserine Pass in February 1943. From this, we would estimate
that the date of the photos was "sometime around mid 1943." By the
Registration Number, USA 304850 would have been accepted at Chrysler's
Detroit Tank Arsenal in January 1942. The corresponding Serial Number
would have been 780. A report dated 20 November 1942 from the People's
Commissariat of Foreign Trade to Gen. Philip R. Faymonville of the
American Supply Mission to the USSR lists the USA Registration Numbers
of 290 M3, mostly Medium but some Light Tanks, with defects "discovered
at inspection upon arrival in the USSR." These tanks had been shipped on
Convoys PQ 12 (arrived at Murmansk on 12 March 1942) through PQ 18
(arrived at Archangelsk on 21 September 1942). USA 304850 was reported
to have been shipped on the SS West Chestwold, one of 24 merchant ships
that comprised Convoy PQ14. Primarily as a result of damage due to
storms and ice, only 7 of the cargo ships actually made it to Murmansk,
arriving April 19th. The defects on USA 304850 were reported as "Tracks
show wear and mechanical damage, Broken stop signal, and Suspension
covered with corrosion." Corrosion was the primary issue with most of
these tanks. The Arctic Convoys sailed through an extremely harsh
environment (inset), and US officials on the scene observed that many of
the tanks, particularly those loaded as deck cargo, arrived completely
covered with saltwater ice. Ice had often seeped into the
interiors "through pistol ports, driver's windows, top hatch covers,
ventilators, and even around rivets." In many cases, this rendered the
tanks "unserviceable for action without considerable work and
repair." The US did not come up with a standard and effective method of
"sealing tanks for shipment to overseas theaters of war" until the Tank
Depot system became fully established at the beginning of 1943.
Needless to say, the Soviets were not greatly impressed with the
"retro" design of the M3 Lee. As noted, the condition of many of the
tanks upon arrival caused problems. One can only imagine the
uncertainty and confusion due to the lack of instructions on so complex
an item. The first M3 Technical Manual, which was published in October
1941, was very short and sparse, and, of course, was in English. It is
thought that the Amtorg Trading Corp. published a Russian language
translation of this Manual in early 1942. It should be noted that a
somewhat more complete TM was published in May 1942, and in July, the
Ordnance Department disseminated a "Base Shop Data Book" which
contained hundreds of pages of illustrated instructions regarding
"methods of dismantling the units described, making the necessary
repairs, and reassembling the components into a serviceable unit." It
is assumed that this material was made available to the Soviets,
although it probably came "a day late and a dollar short." The original
radial engine ran on 91 octane aviation gasoline. In May 1942, the
R-975-C1, which was modified to run on 80 octane gas, replaced the
R-975-E2 in production at the Continental Motor Company. A Field
Service Modification kit, "Modify carburetor for 80-octane fuel," was
also produced for conversion of earlier E2 engines. In the meantime,
the Soviets resorted to bolstering their available aviation fuel with
an additive known as the "R9 improver." For context, readers should
keep in mind that the engine change came about 2 months after the
Sherman first entered production. In 1941 and '42, the 75mm was
considered an excellent tank gun, capable of effectively firing both
high explosive and armor piercing rounds. However, Yuri Pasholok states
that "The first few shipments had no AP shells for the 75 mm gun...The
first AP ammunition arrived with PQ-14 in late April, only 1200 units.
This was 40,800 short of the total amount needed to load up existing
tanks." The photo above shows USA 304293 on display at Patriot Park in
Kubinka, Russia. This tank was accepted at Chrysler in October 1941. It
appears to have arrived in the Soviet Union in early 1942, one of the
first Lees received. USA 304293 was tested at the Soviet Armor Center
at Kubinka from May 1942 through at least March 1943. Photo courtesy of
Yuri Pasholok.
As
best we can determine, the Soviets ordered an additional 278 M3 Lees
under the 2nd Lend Lease Protocol which ran from July 1942 to June 1943.
The 2nd Protocol also included a small order for 219 M4A2s and 2 M4A4s.
Production planning in the US assumed that the Soviets would have
ordered up to 2000 M4A2s under the 2nd Protocol, but perhaps based on
their experience with the Lee, they held back? In any case, the Soviets
shot some footage of
some of their Lend Lease Lees. In the screen capture on the left, a
unit is shown being unloaded from a cargo ship. The M3 Medium had no
lifting rings, and here the stevedores have resorted to hoisting the
tank by running cables lengthwise under the hull. A counterweight is
just visible on the 75mm gun, suggesting that this tank was factory
built with a gyro-stabilizer. These were reported to have been
installed on Lees starting around the end of January, 1942. Thus
we would guess this scene was filmed several months after that.
The screen capture on the right is part of a series which depicts
a bunch of Lees and a few Shermans being transported on railcars. The
Lee appears to be a late production Chrysler with no doors (1), grouser
boxes (2), and rear stowage bins (3). Counting heads suggests that the
side doors were completely eliminated at Chrysler starting around June
1942. As
best we can tell, the doors were never eliminated from ALCO and Baldwin
M3 Lees but were simply welded in place. The Sherman directly
behind
would have been an M4A2 from the 2nd Protocol. The first 26 of
these are reported to have arrived "at a northern port of entry" in
November 1942. This would tend to date this scene no earlier
than late 1942, but more likely months later.
Here
we see a Lee that was recovered from the SS Ballot in 2018 "by
specialists of the Russian Northern Fleet’s Search and Rescue unit". The
Ballot was a US Maritime Commission freighter that was part of Convoy
JW 51B consisting of 15 merchant ships bound for Murmansk. On 31
December 1942 during the "Battle of the Barents Sea," escort ships of
the Royal Navy turned back an attack by a German surface force which
included the heavy cruisers Admiral Hipper, Lützow and six destroyers.
The merchant ships proceeded unharmed to Murmansk, but on 2nd January
1943, the Ballot is reported to have run aground in heavy fog and was
abandoned off Kildin Island in the Barents Sea. Actual "no doors" M3
Lees appear
to have been made exclusively by Chrysler. A few M3A1 hull castings
were produced with no doors, but we have yet to find examples of riveted
or welded hull "no doors" ALCO or Baldwin Lees. Rather, these are seen
with the side doors welded on. For improved ballistic protection, the
Ordnance Department decided to eliminate the side doors and replace them
with an escape hatch in the belly plate. This decision did not sit well
with users including the Soviets. In a letter dated 20 January 1943,
the Soviet Purchasing Commision in the US contacted Tank-Automotive
Command: "Moscow advises us that the Medium Tanks M3 which arrived the
last time in our country had no side doors. The doors on each side of
the hull were intended for the crew to enter or leave the Tank. The
absence of these doors on the Tank make it extremely difficult for the
crew, especially during combat action. Moscow requests an explanation
for the reason of this change in the design of the Tank." Although the
Serial Number of this tank is not yet known to us, we can report that
the highest Serial Number of a Soviet Lend Lease Lee we have recorded
from period documents is SN 4678 (Chrysler, July 1942). Note the pressed
metal road wheels (1) and the "long" 75mm M3 gun (2). Photo courtesy of
Dmitry Ukryukov.
Dmitry Ukryukov provided us with a close up of one of the bogie
units which we thought might be of interest. The first iteration
of the pressed metal road wheels lacked the familiar "spokes.”
They begin to show up on a few Chrysler Lees around March, 1942, and
appear to have been completely replaced by the standard spoked pressed
metal wheels, such as seen here, by the end of May. The "standards"
were subsequently used on all models of Chrysler built Shermans with
VVSS. It would appear that when the sailors cleaned the
barnacles and such off the wheels, the pressed metal facing
of the one on the left fell apart because the rivets had corroded away.
This provides something of an idea of the hollow nature of the wheel's
construction. In addition, a good deal of the contact surface of
the return roller has corroded away. The original rollers were
steel fabrications. According to Technical Bulletin TB Ord 18, dated
April 1943, " A new cast-type track roller has been developed for use
with steel tracks on medium tanks. The old type rollers do not
hold up when used with steel tracks. Steel rollers B168339 will,
therefore, be replaced with cast rollers B207814 when replacement
becomes necessary due to failure." Of course, the cast rollers entered
production well after the final M3 Medium had been built. Finally, this
tank can be seen with bogie brackets with a pair of horizontal ribs
(arrows). These also appear to have been exclusive to Chrysler built
Lees. From the examination of the few such surviving bogies, these
were produced by two plants of the National Malleable and Steel
Castings Co., one in Cicero, Illinois (logo H inside a C) and the
other in Sharon, Pennsylvania (logo N inside a circle). Those made
at the Sharon plant have the casting date on them. Our example was cast
in 3-42 (March 1942). The earliest date we have encountered at present
is 2-42, but counting heads suggests that they began to enter the
production pipeline in late 1941. The part number of the bracket
is D37893, which is cast in just below the date.
The
salvage of the Lee from the Ballot reminds us of the tremendous loss of
men and materiel suffered in the attempts to supply the Allies.
Official Lend Lease records have it that the US War Department shipped
1386 M3 Medium Tanks to the USSR. In "The American Highrise," Yuri
Pasholok writes, "945 M3 medium tanks arrived in the USSR officially,
but in reality, the number was higher. A transport with these tanks sank
close to the Soviet shore in 1942. Twelve tanks were recovered and
restored in 1943. They ended up in the 429th Independent Tank Battalion.
Including these tanks, the total number of M3 mediums used by the Red
Army was 957." Thus, even during the War, some Lees were salvaged from
the sea. The discrepancy between the number shipped and the number "used
by the Red Army" suggests that 429 Lees, nearly 1/3 of those shipped,
were "lost in transit." The Luftwaffe targeted the Northern ports, so
the danger did not pass when the cargo ships arrived at their
destinations. For instance, Convoy PQ 12 dodged an encounter with the
battleship Tirpitz and arrived at Murmansk on 12 March 1942. However,
the British freighter Lancaster Castle "was bombed and sunk by German
aircraft when anchored at Murmansk roads." Another ship of the Convoy,
the SS Stone Street, had transported some Lees, and one, USA 304332, was
"exposed to bombing at port...tank caught on fire...Repairs Required:
Major." Daniil Khazratkulov wrote "It's alive!" when he posted some
photos of the Ballot Lee that he took in Murmansk in 2019 during a
rehearsal for the 9 May Victory Day Parade. The original suspension and
tracks have been replaced with those from a 1944 production Sherman. It
is thought that all of the Soviet Lend Lease M3s were shipped with the
original commander's machine gun cupola. This tank appears to have been
recovered without the cupola, and now has some sort of fabricated
replacement that is more like the Grant's split hatch cupola. The plates
(arrows) seen in the rear were not part of the original design, but, as
a late production Chrysler Lee, this tank was built with the M4 type of
exhaust and air cleaner set up which included the extension plates. A
counterweight has been added to the M3 75mm gun, although these were
only necessary to balance the shorter M2 gun with the gyro-stabilizer.
The M4A2(76)HVSS seen in the background was salvaged in July 2014 from
the wreck of the SS Thomas Donaldson, a Liberty Ship sunk in the Barents
Sea on March 20, 1945. This tank is Serial Number 64465, indicating
that it was built at the Fisher Tank Arsenal in December 1944. When
recovered SN 64465 had VVSS, so the HVSS suspension is also a retrofit.
We
try to keep a a list of
surviving Shermans/variants in the world. We do not consider those undersea to be "survivors," but the Ballot Lee
joined the ranks as soon as she was back on dry land. There are reports
that another late production Lee was salvaged in August, 2021 and is
"stored somewhere in the Murmansk area." The Russian freighter
Kolkhosnik sailed from Boston with a Lend Lease cargo including "ore,
barbed wire, truck parts, tires, munitions, and tanks." On 17 January
1942, about a year before the Ballot ran aground, the Kolkhosnik struck
Smithson Rock, near Sambro Island off the coast of Nova Scotia and sank. The
wreck site is popular with divers, and in 2020, Bob Semple filmed 4
tanks which can be identified as Lee's by their unmistakable
silhouettes, including the commander's cupolas seen here. By the date of
the sinking, it is thought that these M3s would have been part of the
initial allocations to the Soviets made in December 1941, either
Shipping Order G-28068 for 132 units or G-213683 for 42. Photos courtesy of Bob Semple.
According
to Yuri Pasholok, M3 Mediums served with, among others, the 41st,
114th, 192nd, and 241st Tank Brigades, along with the 230th and 240th
Tank Regiments. They fought on all fronts from May 1942
until the end of the War, including in the Battles of Stalingrad and
Kursk. Yuri reports that there were 102 still in service by 1 June 1945.
This uncaptioned, undated German photo of a Soviet Lee captured intact
caught our attention since it appears to show some sort of protective
cover retrofitted over the engine air intake (1) such as the British
wanted. Panel (2) was not riveted but screwed on since it was used for
the installation and/or removal of the 75mm gun. The screws running
along the top of the panel have been removed for some reason. The top
hatch cover has also been removed. The visible bogie bracket castings
can be seen with the "raised lines" across the top.
The
Soviet Union was the only allied country that was "officially"
allocated and shipped any Tank Recovery Vehicles based on the M3 Medium.
These were initially given the experimental designation "T2," but in
August 1943, the Ordnance Technical Committee assigned the nomenclature
"M31" to conversions based on the M3 Medium, with "M31B1" and "M31B2"
assigned to those based on the diesel powered M3A3 and M3A5
respectively. Unfortunately,
little is known about their use if any in Soviet armored units. From
August through December 1943, Baldwin remanufactured and converted 146
diesel T2s from used Lees gathered in "from the field." Baldwin docs
state that these were converted specifically "for the Russian
Government." However, US Lend Lease documents have it that the Soviets
were charged for only 115 retrievers as Lend Lease. It is not known what
became of the other 31. Perhaps the Soviets only ordered 115, or 31
were repossessed and distributed elsewhere. Above shows a fuzzy photo
reported to have been taken at Kubinka Proving Ground in 1943, according
to the website “Engines of the Red Army in WW II”.
An Ordnance document has it that the Lend Lease T2s were assigned
Serial and Registration Numbers 751/USA 40142501 through 896/USA
40142646. At present, we cannot confirm if that is accurate, since there
don't appear to be any historic documents/photos or any surviving
examples within that range. We would note however that a number of WW II
documents from the Russian Archives identify US Lend Lease AFVs by
their US Registration Numbers, so perhaps some Soviet T2 listings will
come to light in the future?
Lees in North Africa
The
arrival of the American Medium Tank in North Africa is described as "a
resounding event." For the first time, the British had a weapon in the
"dual role 75mm gun" that "provided the means of killing German tanks
and anti-tank gun crews at ranges hitherto undreamed of. And this could
be done from behind the heavy armour of a reasonably fast and very
reliable tank." Up until this point, it was the intention of the Brits
to arm their Shermans when they became available, 90% with their
6-pounder gun and 10% with the 75mm. We invite readers to have a look at
our Grant page, since the British primarily employed the Grant, the
model that had been designed to their specifications. However, a few
Lees also took part in the Campaign in North Africa. As mentioned
previously, the evidence suggests that the Grant had its combat debut
with the British on 27 May 1942, the second day of the Battle of Gazala.
At that time, one British report has it that there were "138 Grants in
our three Armd Bdes." The Germans were estimated to have had more than
twice that number of "Mk III and Mk IV tanks." For the most part US
Medium Tanks were described as "Grants" up until around November 1942
when the term "Grant/Lee" starts to appear in some documents. However,
British Purchasing Commission files distinguish between Grants and Lees
shipped to the various Theaters, and we can observe that by the time of
Gazala at end of May 1942, 478 "M3 (Br) Gas" and 72 "M3 (US) Gas" had
been exported to the Middle East. When Shermans began to arrive in
September 1942, it was reported that 493 "M3 (Brit) Gas," 164 "M3A5
(Brit) Diesel" and 75 "M3 (US) Gas" had been exported. These appear to
be the final numbers of M3 Mediums shipped to the M.E as the figures
remain constant after that. Quite frankly, we are somewhat surprised
that as many as 75 Lees were provided to the active combat theater
instead of just a few evaluation units, but that may have been a
function of what M3 Mediums were immediately available at the time of
the shipments. Above we have a photo believed to have been taken at the
US Middle East Training Center by its Director [then] Maj. G. Burling
Jarrett from Aberdeen Proving Ground. The school had been established in
May 1942 to train members of the British armored corps in the
maintenance of US tanks and self-propelled guns. Both the Grant and the
Lee have been outfitted with "sandshields" (1) typical of those
fabricated at British Workshops starting in early 1942. Both have also
been installed with fittings for "Sunshields" (2) a Middle East
modification introduced in March 1942 whereby a canvas cover could be
placed over the tank to make it appear to be a lorry [truck]. The Lee
can be seen with an additional "mystery" fitting (3) retrofitted. While
the Grant would have been built with the rear stowage boxes (4), the Lee
would not have, and we assume they were fabricated at British Workshops
specifically for the Lees, since they appear in other photos. Note that
the engine crank (5) is in its "ready to use" location. One of the
Middle East mods was "Lengthening of starting handle [Feb. 1942]." At
least one of the Lee's bogie brackets can be seen to have the horizontal
ribs (6).
Here we have two photos of Maj. Jarrett posing with M3 Lee T-22688. The
first Lees (as opposed to Grants) were shipped to Egypt in December
1941, with 13 reported to have arrived on the cargo ship Pampas on 25
Feb 1942. Only their US Serial Numbers are listed in the Michael Dewer
files showing that they were a mix of Baldwin and ALCO M3s. Counting
heads suggests that the first 30 or so Lees were assigned British War
Department Numbers (T-Numbers) when they got there and that these
numbers ran from about T-22669 through T-22698. The balance of the Lees
sent to the M.E. appear to have had WD Numbers in the range from T-30176
through T-30252. Both ranges appear to have been exclusive to the
Middle East Lees, and we wouldn't be surprised if the T-22XXX Lees were
re-numbered to the T-30XXX range at some point. T-22688 can be seen with
the British type sandshields, sunshield fittings, and a dust cover for
the 75mm gun, all mods reportedly introduced at British Workshops in
early 1942. Unlike the Lee in the previous image, this unit was not
retrofitted with stowage boxes on the rear sponsons. Maj. Jarrett had
been a collector of weapons since boyhood and was extremely
knowledgeable about Ordnance. Thus, following complaints from the
British, and studying the problem, he was able to dramatically improve
the anti-tank performance of US 75mm rounds by substituting their fuses
for more "hair trigger" French fuses last produced in 1918.
Approximately 90,000 of the old fuses were located at a French
encampment in Syria. In another instance, Jarrett suggested that 15,000
rounds of captured high explosive Panzer IV 7.5cm ammunition could be
"returned" to the Germans by way of the M3 Medium's 75mm gun. However,
the rotating bands of the captured shells had to be trimmed down to fit
the M2 tank gun. "Among the minor miracles of the war is that not a
single shell exploded while being spun furiously on the lathe...When
tested on a captured Panzer tank, it not only pierced the armor plate,
but with its high explosive burst it scattered the tank over the desert.
"Wow, that's better than our best ammunition," exclaimed Jarrett." For
this and other ordnance innovations during his time in North Africa,
Jarrett was awarded the Legion of Merit. The article from which we have
quoted was written by Arch Whitehouse and entitled, "The Junkman Who
Stopped Rommel." (Cavalier Magazine,
December 1957) Col. Jarrett played a
huge role in the establishment of the now defunct Ordnance Museum at
Aberdeen Proving Ground. Those of us who study armor history are in his
debt.
Unlike
the Soviets, the British pretty much leaped all over US produced armor
as it became available under Lend Lease. Despite their dislike for the
Lee design, they requisitioned nearly 5000 units along with the 1686
Grants. Keep in mind that only 4572 Lees were actually built, but the
British Tank Mission led by Michael Dewer knew that any overage would be
converted to the replacement design with the main gun in a revolving
turret. The British shared a common language (mostly) and welcomed
American technicians and training schools and the like, and as a result,
the LL armor program got off to a better start than it did with the
Soviet Union. At one point, it is reported that Maj. Jarrett produced a
sort of dictionary of British and US technical terms that attempted to
merge the two into a common language. We suspect that no one read it,
but it goes to illustrate Jarrett's level of enthusiasm. The British
mentioned that in the early days, spare parts were nearly nonexistent,
and they had to resort to "cannibalism" to keep their Grants, etc.
running. The Lees would have made good "parts junkers," but period
documents and photographs make it clear that some were actually used as
fighting tanks. The examination of unit records that list T-Numbers
suggests that the initial delivery of Lees to the front lines came in
early July 1942 during the First Battle of El Alamein. A handful were
reportedly issued to the 3rd and 5th Battalions of the Royal Tank
Regiment no doubt as replacements for the many Grants lost during the
retreat from Gazala to the "final" line at El Alamein. The photos above
are screen captures from some raw footage held by the Imperial War Museum. The film's "production date" is given as 1942-07-12,
which we take to mean 12 July 1942. The film also shows a Grant,
T-24226, believed to have been "Clovelly" of the 3rd RTR. In any case,
both Lees can be seen with quite a few of the external "Modifications on
Medium Tank M3" done by Base Ordnance Workshops as the tanks were
processed for issue. A modification that was approved in April was
"Increase the stowage of 75 mm to 80 rds and armoring bins." On 10
April, the 3rd RTR reported that "All Grant tanks modified for new
ammunition basis of 80 – 75 m.m. and 80 – 37 m.m." Thus, the M3 Medium's
as designed 37mm round capacity was decreased by over half in order to
make room for 30 additional 75mm rounds to supplement the tank's
original capacity of 50. More significant was "armoring bins." From the
start, the British were concerned about the vulnerability of the
ammunition in the M3 Medium, and later in the Sherman, and made urgent
recommendations to the US Ordnance Department. Mostly for production
reasons, over a year would pass before changes could be implemented to
the Sherman's design to better protect the ammo. One report from the
theater has it that it was determined that 8 grousers per side was
sufficient and that these could be stored in the bins provided at the
factory on Grants or added at Base Shops to the Lees.
The photo above is dated
7 August 1942 and has a sort of "United Nations" theme. The wartime
press caption attached to the photo reads "Yank Tank in Egypt...A New
Zealand officer chats with the English crew of an American "General
Grant" [sic] tank after a clash with German tank forces "somewhere in
Egypt." Punctures in the armor were caused by shell fragments." A close
examination of the print reveals that one of the two crewmembers is
wearing a Royal Tank Regiment cap badge and that the Lee is
T-30207. It was retrofitted with the British type sand shields and the
"sunshield" fittings, but like T-22688 shown earlier, not the stowage
bins on the rear sponsons. The dark paint, which is likely the
original factory olive drab, suggests that this tank had once been
installed with a dust cover for the 75mm gun. The tracks show
extreme wear, but the rubber on the bogie wheels appears nearly
new. The horizontal ribs on the bogie brackets offer a clue that
T-30207 was produced at Chrysler's Detroit Tank Arsenal. Photo courtesy of Alexander
Turnbull Library.
Here
we have an OWI [US Office of War Information] photo that appeared in
newspapers in a number of Allied countries. The caption reads, "Captain
William Bailey, of the U.S. Army in North Africa, stands atop a General
Grant [sic] tank in which he fought for ten hours against General
Rommel's forces in the early phases of the German attack on Egypt. The
tank was undamaged." Several photos in this series have September 1942
dates, and one that shows a Yank crew with an actual Grant, is
headlined, "Strong Contingent of U.S. Troops Reinforces British in
Middle East." As best we can tell, the "strong contingent" amounted to
about 60 "tankists" who were sent to North Africa for additional
training and brief combat experience. The first group of 15 took part in
an engagement on 13 June 1942 at El Adem towards the end of the Battle
of Gazala. They are reported to have fought in 3 Grants which they
turned in the next day before departing to return to the US. This
episode provided the very loose premise for the US tank crew of a Lee
named "LULUBELLE" to be serving with the 8th Army immediately after the
Fall of Tobruk in the 1943 film "Sahara." The second group of US tankers
was led by Captain Bailey. The War Diary of the 5th RTR notes that on 5
August 1942 "3 Offrs [Officers] and 42 O.R.s [Other Ranks] of United
States Army (Tank Corps) attached to unit." On the 12th, a "Grant Sqn
[was formed] under command of Major King 2 RGH [Royal Gloucestershire
Hussars] consisting of 2 RGH [39 men and 9 of their Grants] and American
crews." This unit was assembled as C Sqn, 5 RTR with 12 Grants,
however, based on the photo, it would seem that a Lee or two may have
been in the mix. C Squadron was involved in an engagement in the area
around Sidi Abdel Rahman on August 31/ Sept 1. All of their tanks were
reported to have been damaged but stayed in the fight. The unit suffered
4 casualties, including US Army Sgt. Conner who was wounded. On 12
September, "Capt. Baillie [sic] and American crews return to the Delta
area prior to returning to the USA." In any case, our subject can be
seen with a T-30XXX WD Number and a few of the British Base Shop mods,
including the rear stowage bins. The tank appears to have been
camouflage painted. Again, the horizontal ribs on the forward bogie
bracket hint that it was produced by Chrysler. We suspect that perhaps
all but the last 3 of the 75 Lees shipped to the Brits in the Middle
East were built in February 1942 or earlier, so it is improbable, but
not impossible, that any examples with welded up or eliminated side
doors, ventilators and other late features served there.
This photo is dated 27 October 1942 a few days after the start of the
Second Battle of El Alamein. It shows a pair of M3 Lees, one named
"Battleship II," along with a few of the new M4A1 Shermans that had
arrived in Egypt in September 1942 as part of the "Emergency Shipment."
It is thought that these tanks served with the Staffordshire Yeomanry,
one of the 3 Armoured Regiments of the 8th Armoured Brigade. In a sort
of roster of 8th AB tanks that appears to have been compiled during the
second week of November, 10 "Swallows" [Shermans], 15 "Grants or Lees"
and 22 Crusaders are listed on the "Staffs Yeo" page variously as "Fit,"
"Received," "Evacuated" or "Destroyed." Years ago, we found
documentation of the War Department or T-Numbers assigned to the Grants,
and these can be found at the top of our Grant page. The Staffs Yeo
"Grants or Lees" list contains the T-Numbers of 5 "non-Grants" - 30176,
30201, 30203, 30229 and 30248, which, of course, we take to have been
Lees. The rosters of the 3rd Royal Tank Regiment and the Nottinghamshire
Yeomanry (Sherwood Rangers) also list a few "non-Grants." The Shermans
were the stars of the show, but the Grants and Lees served as well.
Although Lees were provided with an "antenna pot" mounted on the left
rear of the hull superstructure, in many cases, such as here,
Commonwealth Lees are seen with the antennas mounted on the hull "roof"
directly above the interior location of the radio. The longer antenna on
"Battleship II" would have been for the Number 19 radio's "A set"
antenna, while the shorter one would have been for the "B set."
The
photo above is dated 21 March 1943 and captioned, "Tank men ready for
the road. Note the inscriptions on the tank - Alamein and Tripoli are
scored out and Tunis appears to be the next stop. 1st and 5th Tank
Regts. and 1st Rifle Bde. 7th Armd. Div." This M3 can be identified as a
Lee by the shape of the turret. It can be seen that the fixed machine
guns are not installed. In April 1942, "Removal of twin Browning guns
and plugging of holes" became a mandate of the Mechanisation
Experimental Establishment (Middle East). Thus, we believe that no
Eighth Army Grants or Lees actually used the fixed guns in combat. On
this example, if the holes were plugged as ordered, it was from the
inside. By March 1943, all available Shermans were being supplied to
front line units, but of necessity, some Grants and a few Lees continued
to soldier on until the end of the Campaign. Just before the Axis
surrender on May 13, 1943, the Eighth Army Tank State lists a total
inventory of 109 Grants and 221 Shermans, with 43 Grants and 89 Shermans
"Serviceable with [combat] Formations." An additional 263 Grants were
counted in formations in the Middle East "Other Than Eighth Army,"
including with units in training, in Schools and in Workshops. We
believe "Grant" was being used generically here, and also included what
remained of the 75 "M3 Lee Gas." Thus, of the 732 M3 Medium series tanks
supplied to the Middle East, about half could still be accounted for at
the end of the Campaign. It is assumed that the other half had been
lost to attrition during the year (May 1942 - May 1943) that the M3
Medium had been in service. IWM NA1305.
Combat
Command B of the 1st Armored Division was assigned to the Center Task
Force to provide armor support to the 1st Infantry Division. The
objective of the CTF was the capture of the major port of Oran in
Algeria. CCB's two Light Tank Battalions (1st Bn/1st AR and 1st Bn/13th
AR, both with M3 Stuarts) provided almost all of the armor support from
the 8th through 10th of November. However, it is at least possible that
the M3 Lee had its combat debut with the US Army on D plus 1, 9
November, 1942. The US Army "Green Book", "Northwest Africa: Seizing the
Initiative in the West" describes "a column that was en route to Ste.
Barbe-du-Tlelat to help Colonel Water's force oppose a French armored
threat from Sidi bel Abbes. Since the column contained two medium tanks,
the only medium tanks ashore, it promised to provide substantial
support to the eastern flank of the Center Task Force." These would have
been Lees of the 2nd Battalion, 13th Armored Regiment, since they were
the only medium tanks that were in the CTF. In fact, they were the only
Lees involved in the invasion phase of Operation Torch. Then
Major Henry Gardiner, Executive Officer of the 2nd Battalion, mentions
in his notes that on November 9 "Two of our tanks came in [on Z Beach]
on L.C.T.s...They would never have made it except for their
waterproofing." Gardiner goes on to state
that because of the heavy surf on Z Beach, unloading operations shifted
to the recently captured port of Arzew. An "Operations Journal" of the
13th Armored Regiment reported that on 10 Nov. at 1018 hours, "2 columns
have entered Oran...no rpts recd yet as to results...2 tanks, 1 light, 1
med., 12 gun destroyed by direct hits from arty." Whose "arty"
destroyed whose tanks and where is not clear. At 1215, "Order "Cease
Firing" has been given by French General in Oran has asked for
conference and terms of surrender." In his memoirs, Col. Robinett
mentions that as he toured around after the battle, he saw a "a medium
tank which had been knocked out and burned" near the Tafaraoui airfield.
Again, not at all clear, but we don't believe that the French had any
tanks that Robinett could have described as "medium." In
the absence of any photos showing M3 Mediums of the 2nd Bn/13th AR on
November 9th or 10th, above we have a map of the Center Task Force. Col. Robinett was
in charge of Task Force Green (1) which landed at X Beach on 8 November
and included the M3 Lights of the 1st Bn/13th AR. The bulk of CCB was
assigned to Task Force Red (2) which included the M3 Lights of 1st
Bn/1st AR and the M3 Mediums of 2nd Bn/13th AR. A "Flying Column" led by
Lt. Colonel John Waters of 1st Bn/1st AR landed on 8 November at Z
Beach. It moved inland some 25 miles, and after a brief assault,
captured the Tafaraoui airport at noon. The main body of CCB came ashore
at Z Beach on the 8th and 9th with some elements landing dry shod at
the port of Arzew.
To add a further note of uncertainty about the possible role of M3 Lee
medium tanks on November 8th through the 10th, here we have a Signal
Corps photo dated "9 Nov 42" and captioned, "American Medium Tanks [sic]
are unloaded at a port in Algeria. 1st Armored Div., Combat Command B,
at Arzew." Of course, these are M7 "Priest" 105mm Howitzer Motor
Carriages, and it is thought that they would have belonged to the 27th
Armored Field Artillery Battalion which was a part of CCB. Some sources
have it that the 27th AFA Bn was equipped with T19 105mm Howitzer Motor
Carriages (half-track mounted), but this photo suggests that they had at
least 2 M7s. These Priests obviously landed dry from the L.C.T.
[Landing Craft Tank] seen on the right. We see no evidence that they had
been waterproofed in any way, but the fiberboard packing tubes for the
105mm ammunition suggest that they were "combat loaded", that is, ready
to go into action upon landing. In any case, while the caption writer
misidentified these as "Medium Tanks," we don't believe that Col.
Robinett or Major Gardiner would have made the same mistake.
On 8 November the Eastern Task Force of Operation
Torch assaulted and quickly captured the port of Algiers, the capital
and largest city of Algeria. Some units of the ETF immediately rushed
even further east with the object of seizing the Tunisian ports of
Bizerte and Tunis over 450 miles away. On 12 November, elements of CCB,
including the 1st Bn/1st AR and the 2nd Bn/13th AR were ordered to head
east from Oran to support the advance of the British 78th Infantry
Division into Tunisia. Signal Corps photographers under the supervision
of Hollywood notables Darryl Zanuck and John Ford shot some color
footage which was released to the public entitled, "At the Front with the U.S. Army in North Africa". The scenes were reported to have been
filmed in November and December 1942 and even included some combat
footage of Axis tanks during the Battle of Tebourba. The narrator refers
to them a "General Grants," but the Lee footage begins as the tanks
leave Algeria on LCTs and disembark at the port of Bone some 340 miles
away. They then move overland in convoy into Tunisia. In the screen
capture on the left, it can be seen that the stars and stripes painted
on the turrets were yellow. Examination of the overland footage shows
the geometric tactical markings for D, E, F and Headquarters Companies
of the 2nd Bn/13th AR. These are also painted in yellow. Some of the M3s
are noted with numbers that appear to have been hurriedly brush painted
in white, as in the image on the right. Most or all of the Lees are
seen with the tow cable draped across the front and attached to the
right-side towing lug as on #47.
In the "At the Front..." footage, a small number of the Lees and a few
half-tracks are noted to have US flags on the front and sides. These
appear to have been paper prints that were pasted on to the AFVs in the
vain hope that if the French saw them during the initial stages of the
invasion, they would not fire. The screen capture on the left shows a
Lee of E Company, 2nd Bn/13rd AR while the one on the right shows an M2
Half-Track with its flag fraying off. Tragically, the casualties
incurred during the Torch landings are estimated at more than 2000 with
1000 killed for the US and British and nearly 3000 killed and wounded
for the former and future French allies.
In late November 1942, some of the crews of the Lees of D, E and F
Companies of the 2nd Battalion/13th Armored Regiment were photographed
as they stopped for maintenance and resupply just inside the Tunisian
border. Most of the images, like this one, were taken on 23 November at
Souk el Arba, near the site of a recently established RAF airfield. It
is thought that the "D 2" (1) seen here indicates D Company, 2nd Platoon
as opposed to D Company, Tank 2, since "D 2" is seen on more than one
example. The Signal Corps captions included the USA Registration Numbers
of the Lees, but some are questionable. For instance, this one is
listed as "Tank #209751." We might assume that the writer meant
"309751," which would indicate DTA April 1942 production. We can at
least observe that, where they can be seen, all of the other tanks
photographed have RNs that begin with "309" with the following numbers
indicating Chrysler February, March or April production. This is one of
the few photos in the series that shows the rear of the tank, and if the
2nd Battalion's Lees were waterproofed as stated by (now) General
Robinett and Major Gardiner, it is barely evident. The area on the
engine access doors outlined in red may provide a clue that something
was there. We would guess that that might have been where the bottom of a
sheet metal enclosure was attached to the tank. This would have sealed
in the exhaust pipes and air cleaners and would have included an exhaust
stack that rose a few feet above the level of the engine deck. The
original pioneer tool stowage seems to have been replaced on the Lees of
the 2nd Bn/13th AR. For instance, there are shovel fittings (2) on the
lid of the left-side stowage bin, while the axe and perhaps the mattock
(3) appear to be mounted on the right-side lid. The tow cable (4), which
was originally coiled on the engine deck, can be seen running to the
front of the tank. The engine hand crank (5), not seen anywhere in the
original tool layout, is mounted on the edge of the engine deck. It is
mounted on the upper rear hull plate on some of the 2nd Battalion's
other Lees. It would appear that none of the 2nd Bn's Lees shipped down
from Northern Ireland had been retrofitted with grouser boxes on the
glacis or hull roof, and this may have been the reason for the
rearrangement of the tool stowage. Some sort of rack (6) was added, and
grousers (7) and a camouflage net (8) can be seen strapped to it. The
rubber mud flaps (9) show to good effect in this photo.
When trying to "count heads" regarding the introduction of the rear
stowage bins, we had originally assumed that the ones seen on the Lees
in this photo series were factory installed. However, we showed this and
a few other pix to the late Rod Bellars and he was pretty adamant that
these were not the same bins as were on a couple of late production
Chrysler Lees he owned. He said there was a difference in construction,
but we could not understand what it was due to his explaining it using
some incomprehensible Aussie lingo. He seemed to be saying that the
Tunisia lids were constructed a little "higher" than the factory jobs
and pointed out that the hasps seen in the Tunisia pix provided for
padlocks on the lids (arrow), whereas his Lees, not to mention those
seen in factory photos, were padlocked on the sides. Other differences
Rod mentioned were that the lids of the factory bins held only one tool
each, the idler adjusting wrench on the left and the engine crank on the
right. Finally, the word "STOWAGE" was stenciled on at DTA in a dark
color, not the light color seen here. Since then, we have done a
counting heads recount, and now believe that the bins were factory
installed starting in early June 1942, at least at Chrysler. The caption
of this particular Signal Corps photo is one of the more informative
since it actually lists the tank and crew as "2nd Bn. Co. D, 13th Arm.
Reg. 1st Div." However, it gives the USA Number as "309392" when it is
clearly 309592 (March 1942). The photo was taken at Souk el Arba, and is
dated a bit later than most, 26 Nov. 1942, with "A tank crew in North
Africa, just before departure for battle front." Note the open,
unprotected 42 round 37mm ammunition bin (1) visible through the left
side door. A piece of metal (2) appears to have been welded to the
handrail above the door to contain the tow cable as it makes its way to
the front of the tank. The direct vision visor (3) in the commander's
cupola is open and the casting appears similar if not the same as that
used on early Shermans.
The captions of the
Signal Corps crew portraits do not name any of the crew members,
however General Robinett features the photo above in his memoir and
identifies the officer on the right as 1st. Lt. Charles L. Davis. The
caption is dated 23 November and gives the location as Souk el Khemis,
another airfield site about 12 miles from Souk el Arba, both of which
were about 100 miles from the front. The Lee is listed as USA 309508
(March 1942). Leading elements of the British 1st Army had fought their
way to within sight of Tunis, but the Axis had been able to land men
and materiel, unmolested by the French troops at Tunis and Bizerte, and
quickly established strong defensive positions at the mountain passes
leading to the ports. If we discount the idea that a pair of Lees may
have fought during the initial landings around Oran, then the US Army
combat debut of the Lee may have come on 28 November, when the 5th
Battalion of the Northamptonshire Regiment, riding 13 to a tank (per
Major Gardiner) on the Lees of Company D and a platoon of F were
ordered to seize the town of Djedeïda. Robinett reported that
Davis's platoon led the attack, and "all" of his tanks were quickly
destroyed by heavy antitank fire. Gardiner states that "four tanks
[were] knocked out and set on fire." Davis was wounded but attempted to
render aid to the survivors and was later awarded the Distinguished
Service Cross. The attack petered out, and the Hampshires could only
get as far as a ridge commanding Djedeïda, and this was pretty
much the high-water mark of the first Battle for Tunis. The tank can be
seen with "6528-F" (right inset) stenciled on the door. We believe this
was the POM shipping code for this unit for US to Northern Ireland
before the introduction of the color bars. At least we have observed
similar stencils in a few of the Northern Ireland and Tunisia photos,
sometimes censored out. Indeed, in a December 1942 "Recommendations"
document, Captain Robert Van Zant of the Maintenance Company, 2nd
Bn/13rd AR twice refers to his unit as "6528-F". The stencil on the
stowage bin might be "C-85117", probably the Part No. of the left side
bin judging by a few other photos. The right-side bin might have been
C-85128. Again, we see a cable clamp retrofitted to the grab handle
above the door. In another photo of this same tank taken on the same
day, the tactical markings can be seen (left inset). Of course, the
upside down "L" denotes Company D. We believe the Roman numeral in
front indicates "platoon leader." The Arabic number behind looks to be
a "2" and we think it denotes the number of the platoon (1 to 3). Lt.
Davis survived his wounds and continued to serve. In the late 1940s, he
wrote a student paper for the Advanced Infantry Officers Course at Ft.
Benning entitled, "The Operations of the Third Platoon, Company "D",
13th Armored Regiment (1st Armored Division) in the Vicinity of Mateur,
Tunisia, 1 May to 9 May, 1943 (Personal Experience of a Platoon
Leader)." Assuming Gen. Robinett correctly identified Lt. Davis, he
must have been assigned to the 3rd platoon when he rejoined the unit in
March 1943 after discharge from the hospital.
The Western Task Force had landed on the Atlantic coast of French
Morocco and captured the major port of Casablanca on 11 November 1942.
CCB of the 2nd Armored Division included 54 Shermans of the 3rd
Battalion, 67th Armored Regiment. These were the only Shermans that were
involved in the invasion phase of Operation Torch. Depending on how one
defines "combat debut," a case could be made that that the Sherman had
its combat debut with the US Army during operations around the minor
port of Safi, November 8th through the 11th. Sorry to say, we have not
come across any specific descriptions in unit records or any still
photos or motion pictures of these actions. The Western Task Force
remained in Morocco to guard against possible Axis threats on the
Spanish/French Moroccan border. Discounting any "combat debut"
engagements during the invasion, it can be documented that a platoon of 5
M4A1s from the 3rd Bn/67th AR had been sent to the front in order for
their crews to gain experience. These were attached to Company E of the
2nd Bn/13rd AR which was down to 9 Lees as a result of earlier action
during the Battle of Tebourba. On 6 December 1942, Company E was ordered
to "charge up the valley" in order to relieve the 1st Battalion of the
6th Armored Infantry Regiment exposed at Djebel el Guessa. The Axis
forces were well prepared for such a counterattack, and within 15
minutes, all of the Shermans and most of the Lees had been knocked out. A
later attack by the Lees of Company D was also repulsed. At this point,
according to General Robinett, the 2nd Bn/13rd AR "had now been reduced
to 22 badly worn M-3 tanks." We are not aware of any photos of the
ill-fated Sherman platoon, so instead show a Lee and crew of Company E,
2nd Platoon as photographed at Souk el Arba on 23 November 1942. The
Registration Number is listed in the caption and can be seen in the
photo as USA 309132 indicating DTA February 1942 production, the
earliest RN recorded from the group of crew shots. Note that there
appear to be 2 pioneer tools and fittings on the lid of the right-side
stowage bin. According to "At the Front with the U.S. Army in North
Africa," "each tank commander receive[d] his allotment of detailed war
maps" such as seen here.
An important factor in the Axis build up was air superiority, which
enabled them to extend and solidify their Tunisian bridgehead. The
Allies recognized that they had lost the initial race for Tunis and
suspended offensive operations by the end of December as winter weather
mired the front in mud. Meanwhile, the British 8th Army pursued Rommel's
Afrika Corps through Libya while the British 1st Army built up its
strength in Tunisia for a spring offensive. Victory was seen as
inevitable. Prime Minister Churchill and President Roosevelt met at
Casablanca in January 1943, where Churchill's "next step" plan for an
assault on Sicily followed by an invasion of mainland Italy won out over
Roosevelt's somewhat premature desire for a cross-Channel invasion of
Northwest Europe in 1943. The photos above show the condition of a pair
of 2nd Bn/13th AR Lees that had fought from 28 November to 12 December
when the Battalion was pulled off the line to reorganize and replace
losses back in the area of Souk el Khemis, AKA "Stuka Valley" due to
frequent air attacks. The rubber can be seen to have completed
delaminated from a number of the roadwheels on USA 309478 and worn off
the tracks of what is described in the caption as "M3 medium tank
#309506," both DTA March 1942 production. USA 309506 bears the tactical
markings of F Company, and likely the 3rd Platoon leader's mount. Both
tanks had well over 200 engine hours and 1000 miles of operation.
General Robinett reported that during CCB's 2 weeks in combat, his
armored units had lost about 75 per cent of their tanks, but "only" 20
per cent or their men. Major Gardiner was wounded when his Lee was KO'd
on 2 December during the Battle of Tebourba. He recovered and rejoined
the 2nd Battalion as they came into their new bivouac with 14 Lees
limping in under their own power. Over the course of the next month, the
unit trained and rebuilt its strength up to about 44 tanks (out of an
authorized strength of 54) with Shermans in D and E Companies, "leaving
M3s only in F Co."
Earlier, we discussed the average service life of the R-975 series
radial engine. Here we have an "In the Field" report dated 21 December
1942 from Major Richard Grondona of 13th AR, CCB. It lists the "ten high
running tanks within the Command." As was often the case, the tanks are
described generically as "Light" and "Medium", but the Registration
Numbers listed identify the lights as M3 Stuarts and the mediums as M3
Lees. The Lees would be survivors of the November/December battles of
the 2nd Battalion/13th Armored Regiment, and 3 of them are pictured in
the Signal Corps crew photos. Assuming no typo, USA 306337 would have
been an ALCO M3 accepted in March 1942 by our reckoning. The others were
Chryslers. The engine miles averaged around 1700 and the engine hours
around 300 and those listed "continue to operate." Major Grondona
comments, "In spite of long hours running, the performance of tank
engines has been excellent." Again, we have a recommendation "that all
rubber padding be removed as it is said to easily catch fire."
The rest of the 1st Armored Division arrived in theater around Christmas
1942, with the 2nd and 3rd Battalions of the 1st Armored Regiment
equipped with Shermans, while the 3rd Battalion of the 13th Armored
Regiment "still" had Lees. The "new" units lost so many Shermans,
particularly during the February battles around Kasserine Pass, that
some losses had to be replaced with Lees. Bob Holt tells us that the
752nd Tank Battalion was "stripped of all their tanks and most of their
crewmen to fill the horrendous losses sustained by the 1st AD in North
Africa." The veterans of Gen. Robinett's CCB, including [now] Col.
Gardiner's 2nd Bn/13th AR, played a pivotal role in stopping the Axis
Kasserine offensive at the Djebel El Hamra Pass on 21/22 February 1943.
Even so, the 1st AD's reputation had sunk so low that, the day before a
"final" assault planned for 6 May in the area around Mateur, Robinett
reported that the replacement Division Commander, Gen. Ernest Harmon,
deeply insulted him and the men of CCB by asking "Will the damned tanks
fight?" Both Robinett and Gardiner were wounded in the ensuing action.
The Campaign ended on 13 May 1943 with the surrender of a quarter of a
million Axis troops trapped against the sea in Tunisia. The photo on the
left shows Gen. Robinett in late March 1943 "on reconnaissance,
Maknassy Valley." On the right, Col. Gardiner poses with his M4A1
Sherman, "Henry III" which was KO'd 6 May 1943 near Djebel El Assafir.
The photo above is simply stated to have been taken in Tunisia in April
1943. The no doors Lee has a readable Registration Number, USA 3028994,
indicating July 1942 production at DTA. It can be seen with the "final"
(M4/M4A1) exhaust and air cleaner set up, including the "squarish"
plates. Photographic evidence suggests that all of the Lees used by the
US Army in Tunisia were installed with either the Quick Fix exhaust and
air cleaners or the "final" configuration seen here. In contrast, most
of the Grants and Lees used by the British 8th Army in North Africa
appear to have soldiered on with the original pepper pot exhausts to the
end of the campaign in May 1943. The large number on the turret and the
name "Barbarian" call to mind the Lees of B Company, 752nd Tank
Battalion seen in the Perham Down photos. Perhaps "Barbarian" was one of
the 752nd's Lees provided to the 1st AD to replace the severe losses
that their Medium Tank Battalions had suffered?
Readers will recall that the 751st Tank Battalion (Medium)
was involved in a Field Exercise at Ft. Jackson in June 1942 that was
witnessed by Winston Churchill. Shortly thereafter, the unit was
assigned to the 1st Tank Group, which appears to have included 3 Medium
Tank Battalions, the 751st, 752nd and 755th. These units arrived in the
U.K. in August 1942 and took up training in the area around Tidworth
Camp. In early 1943, the 1st Tank Group was deployed to Northwest Africa
to reinforce US Troops fighting there. Of the 3 Medium Tank Battalions
of the 1st Tank Group, only the 751st actually fought in the campaign.
On March 1st, the 751st was attached to the 34th Infantry Division and
elements were first deployed a few days later during a diversionary
attack on Pinchon. It is thought that the 751st was mostly equipped with
the M3 Lees it brought down from England, but the unit records only
refer to their tanks as "tanks." However, in "What American Tankers Have
Learned in Battle," published at Fort Knox in July 1943, Pvt. Raymond
Christy, driver of Tank 1 of Company "C" describes his experience near
Fondouk in April 1943 as he attempted to "bail out" of what was
undoubtedly a Sherman. He goes on to report that he was picked up by the
Battalion Commander, Colonel Louis Hammack's "M4 tank." In any case, on
8 April 1943, the 751st was "Complete as to tank strength (54)" as it
provided armor support to the 34th ID in its controversial and costly
attempt take the mountain pass at Fondouk. By the end of the 3rd assault
on 9 April, the 751st was down to 21 tanks. Soon after, the unit was
withdrawn to reorganize and replace losses, but returned to the front in
early May, attached to the 9th Infantry Division for the final drive.
"The first two tanks of Company A, 751st Tank Battalion" are reported to
have entered Bizerte on the afternoon of 7 May just behind
reconnaissance units of the 894th Tank Destroyer Battalion. Axis troops
had pulled out but left behind snipers, mines, and booby traps. Possibly
the last photos of US Lees in action in North Africa and even Europe
for that matter, were of the 751st in Bizerte. The above shows a pair of
Lees in the city, one named "After Effect." Note the outlined number 3
on the rear of the turret. At the end of the Tunisian Campaign, the
751st was re-equipped with Shermans. The name "After Effect" "reappears"
on a 751st M4 KO'd in Italy. While it was intended that the 1st Armored
Division would be entirely equipped with Shermans by the end of March
1943, there were still 51 Lees on strength at the end of the Campaign in
May 1943, along with 178 Shermans.
At the end of the Tunisian Campaign, most of the Lees in Northwest
Africa appear to have been mothballed. Author Richard Hunnicutt states
that the remaining Lees of the 1st Armored Division "were turned over to
the French for driver training," but, at present, our French sources
have not been able to confirm this with even a single photo. In February
1944, Army Service Forces directed "return of approximately 200 Medium
Tanks M3 Series in North African Theater to the United States and
requesting that action be initiated to declare Medium Tank M3 Series
obsolete." However, here we have an example that remained in service and
was photographed on 5 November 1943 at the 5th Army Engineer Training
Center in St. Denis du Sig, Algeria. This contraption reportedly carried
170 15-pound explosive charges which were picked up magnetically at
point 1 after which the boom was rotated forward, and the charge was
lowered and exploded 6 feet above the ground. The blast wave was said to
be effective at a bit more than a 7-foot radius at detonating the US
M1A1 anti-personnel and the German Teller mine. The boom's power takeoff
broke during its initial demonstration and could not be repaired, so
the project was abandoned. However, tests based on a similar concept
were carried out later at Ft. Belvoir, Virginia using a Sherman
installed with something called a "Pancake Mine Clearing Device."
Ultimately, this also proved to be a dead end. In any case, the Lee can
be seen as USA 309695 indicating Chrysler March 1942 production. Note
that it has "unspoked" pressed metal road wheels. This same tank had
been filmed in February 1943 on a Warwell car (inset) at Depot 0-640
Tidworth, Wilts, England. Many of the US Army Lees in the UK are seen
with rear stowage boxes retrofitted, but judging by their absence in
both photos, USA 309695 was not so modified. It was likely shipped to
Northwest Africa as a replacement with "BLUFF" being the destination
code.
Lees in Australia
There
was a long-held misconception that Australia received “hand-me-down” M3
Mediums from the British in North Africa. The facts are that in the
dark days of January 1942, the government of Australia was extremely
concerned about a possible Japanese invasion and pointed out that "there
are, at present, practically no tanks in the Commonwealth." The
Government requested that "adequate supplies of tanks should be diverted
to Australia from United Kingdom and American production at the
earliest possible date. The immediate minimum requirements are stated to
be 775 Cruiser Tanks." As a consequence, starting in early 1942, new
tanks were allocated to the Australians from US production, and the
first 15 M3 Grants arrived there from the US in early April 1942. The
first Lees (M3 US Gas) are reported to have arrived 5 months later on 30
August. By November 1942, the US had shipped 777 M3 Mediums, including
263 "Grant Gas," 259 "Grant Diesel" and 255 "Lee Gas." This was 2 more
than the “775 Cruiser Tanks” requested, although it was reported that 20
tanks had been “lost in transit.” Since the first Lees were not
allocated to Australia until mid 1942, most of them are seen with late
features such as ventilators, no doors and the longer M3 75mm guns. The
undated photo above was taken in Richmond, California. The caption reads
in part, "Tanks on flatcars are British tanks shipped into Richmond
Tank Depot for repairs." This seems a bit disingenuous or perhaps just
clueless, but it does suggest that the Lees arrived as shown. It can be
seen that the British requests for sand shields (1), and driver's
periscopes (arrow) were finally obliged. The installation of the
periscope necessitated the removal of the grouser box on the hull roof.
In trying to establish a date for the photo, we know that Ford Motor
Company was not contracted to set up its Richmond plant as a Tank Depot
until 20 July 1942. By 8 August, 121 AFVs are reported to have arrived,
and we think that the Lees in our photo comprised some of them. However,
the Depot was still in the process of being established, equipped and
manned, and did not yet have the capability to make extensive
modifications. It
is thought that these tanks were actually modified and sealed at the
Detroit Tank Arsenal before shipment to RTD, where they provided the
nascent Depot with a sort of "how to" regarding preparation for overseas
shipment.
In
this rear view, the Lee in the foreground can be seen as T-26024. The
USA Registration Number was masked over but we were able to read it from
the original 8 X 10 glossy print as 3058041, indicating DTA July 1942
acceptance. This tank features the "high" exhaust pipes (1) typical of
the R-975-C1 radial engine installation, and the "squarish" plates (2)
in front of the air cleaners, typical of late production Chrysler Lees.
At the request of the British, these tanks were not installed with the
Lee's commander's cupola. The British disliked the Lee cupola since it
increased the M3's already excessive height by 4 inches compared to the
low-profile split hatch of the Grant's design. Eventually
the US agreed to supply Grant hatches with Commonwealth Lend Lease
Lees, but production was delayed, and rather than postpone tank
shipments, many of the mid to late 1942 CW shipments were sent without
cupolas, Grant or Lee. An Australian "Minute Paper" dated April 1943
suggests that this was the case with all of their Lees, "They were
without turret flaps which we had agreed to provide locally." However,
it goes on, "These [Grant cupolas] are now arriving from America and are
being fitted," which gives us an idea of the length of the delay in
supplying the cupolas. In any case, the Lees seen in the RTD photos were
obviously not shipped with Lee cupolas, but the round objects (3)
resting on the On Vehicle Materiel boxes (4) do not appear to be Grant
split hatch cupolas. Rather, we believe that these were plywood covers,
that were removed at RTD to gain access for interior inspection. Note
that two plates (5) have been retrofitted to the rear of the turrets.
We haven't come across any documentation about these but suspect they
may have been added at the request of the British to accommodate the
abortive "Camouflage Net Bin."
Here we can get a closer view of one of the Lees at RTD. In a previous
photo, the fronts of the turrets are seen sealed and covered over with
some sort of fabric. T-26057 is not sealed in this manner, perhaps
either because it was removed, or had yet to be installed. In any case,
it affords us a look at the fitting (1), around the 37mm gun mantlet.
The evidence is that some late production Lees were factory installed
with these metal strips, which suggests that a dust cover may have been
provided, although we haven't come across any period photos of it in
place, except on USA 3058309 shown earlier, one of the last Lees built
at DTA. Try as we might, we could not get a good read of the masked off
USA Registration Number on T-26057. This and a few other Lees in the RTD
photo series are observed with a round object (circled) next to the
75mm gunner's sight housing. Note how the long M3 75mm gun is propped up
by a 2 x 4 (2) and secured with metal strapping. The tank is held in
place on the railcar by the familiar U-shaped fittings (3) seen on a
number of the El Alamein Shermans. The shipping destination code is
stenciled on twice. It is a diamond (4) with what we believe was "XXI"
inside. This diamond has been observed in period photos of a few Lees
and a Sherman in Australia. The stenciling seen below the diamond
appears to be "SR1164 A, 3-G-629" which indicates that this unit was
part of a British June 1942 Lend Lease Requisition for 155 M3 Lees. Note
the multi-part construction (5) of the sheet metal that made up the
front and rear sections of the sand shield. It may be of interest to
some to know that the Richmond Tank Depot is now part of "The Rosie the
Riveter/WWII Home Front National Historical Park".
The above photo is dated 5 June 1943 and was taken in the Tank Assembly
Workshop of the NSW [New South Wales] Railways Chullora Workshops, in
the Sydney suburb of Chullora. The caption reads in part, "Of interest
are the General Lee Medium tanks being refitted for the Australian Army.
As well as building 54 Australian designed AC1 [Sentinel] Cruiser tanks
[seen on the sides in the photo], the NSW Railways also modified 58
General Lee tanks." The Grant type split hatch cupola (1) on the Lee in
the foreground is waiting to be installed. The last of the Australian
Lend Lease Lees are stated to have arrived on 3 November 1942, but the
shipping sealant is "still" on the pistol ports (2), gunner's (3) and
driver's (4) periscopes, and ventilators (5) suggesting that these tanks
had been sitting around for quite some time before arriving at the
Chullora Workshops. The number (3) also points to a round object next to
the 75mm gunner's sight housing, as observed on some of the RTD Lees.
Note the plates (6) on the rear of the turret. Weld scars (7) appear to
have been left behind when the grouser box was removed to accommodate
the driver's periscope. © State of New South Wales through the State Archives and Records Authority of NSW 2016.
According
to British Ministry of Supply documents, 255 "M3 (U.S.) Gas" or more
specifically "M3 Lee Gas" were delivered to Australia before the end of
1942. We take this to mean that all were radial engine, riveted hull
models. The majority were late production, Chrysler built, no doors
Lees. The Australian Army preferred Grants over Lees but, at the outset,
"were thankfully prepared to accept either." Correspondence suggests
that the Australians had not been informed of the decision to omit the
doors on the Lee model, and someone at the Ministry of Defence appears
to have suggested to the Prime Minister's Office that the US was fobbing
off “defective” tanks on Australia. Lt. General John Northcott, the
Chief of the General Staff attempted to explain the modification cycle
in order to put the issue to rest, "There is in my opinion nothing to be
gained in further representation to the United States authorities." In
any case, here we see T-25752, which we take to have been a late
production no doors Lee, probably one of those shipped from RTD. This
appears to have been modified by the Australian Army to make it more
Grant like. The side door without pistol port (1) strikes us as an
obvious retrofit. We can only assume that a door was added on the right
side as well. Other modifications include the very elaborate bullet
splash protection for the turret (2), far more extensive in design than
that seen fitted to a few British M3 Mediums. An armored cover for the
engine air intake (3) was added, along with a box on the turret rear
(4). This turret box does not appear to have any external access hatches
but does have what look to be two aerial mounts, one on each side. The
authors believe that this may have been an armored radio box, designed
to permit the No.19 radio to be moved from its standard location in the
hull of the Lee, to the turret as per the Grant. Of course, such a
change would have enabled the Lee’s crew to be reduced from seven to six
as with the Grant. As elaborate as these modifications were, T-25752
appears to have been a test subject, since most of these modifications
are not seen fitted to Lees in Australian service.
This photo is dated 1 June 1943, and shows activities at the
"Primary wing, drivers' maintenance suspension system A.F.V.T.T.C.
(Moorebank)." Moorebank is a suburb of Sydney in the state of New South
Wales. We would guess that "A.F.V.T.T.C." stood for "Armored Fighting
Vehicle Technical Training Center." In early 1943, schools were set up
throughout Australia by the [US Army] Ordnance Casual Detachment, Tank
Maintenance. Here we see trainees working on the suspensions of a pair
of immaculate M3 Mediums. The Lee can be seen as T-25947. As best we can
tell from counting heads, the Lees supplied to Australia were assigned
WD Numbers that fall within a range from T-25199 through T-26061. This
range was not exclusive to Australian Lees. Many of those in the UK and
India have been recorded with WD numbers within this range and higher,
up to about T-26459. The highest recorded for Australia, T-26061, is
reported to have arrived in Sydney on 3 November 1942 aboard the "SS
Wiliam Williams." The fittings (1) on both the Lee and Grant indicate
that they had been installed with sand shields in the US. The sand
shields were screwed on to a metal strip (2) that was retrofitted to the
bottom of the upper hull. This late production Lee would have been
built with ventilators, and an indication of this is that the upper hull
hatch (3) does not lie flat when opened. Both the Grant and Lee are
armed with M2 75mm guns, but the Lee's has a counterweight indicative of
fitment with gyrostabilizer. Both tanks have the Grant type commander's
cupolas. The periscope (4) on the Lee's hatch appears to be installed
with a handlebar for moving it around, like a submarine's periscope.
Here we see a train loaded
with tanks and carriers travelling south into Sydney through
the railway triangle between Homebush & Strathfield stations,
on 7 Feb 1944. The lead tank is T-25734, a "doored" Lee with M2
75mm gun with counterweight. This and another doored Lee further down
the line (1) are the only examples that do not have factory installed
engine deck stowage boxes, at least not on the right side. Note
that, with the introduction of the stowage bins, the engine crank
handle (2) was mounted on the lid of the bin on the right. Both of
these Lees are missing the plates on the rear of the turrets as
seen in one of the Richmond Tank Depot photos. A no doors
model, T-25744, the second Lee from the front, can also be seen
to lack the turret plates. Of interest is that some
of the periscope housings (3) on the turret hatches
are different from the standard driver's periscope
housings (4). It seems possible that when the Grant type
commanders' hatches were finally shipped from the US, they did not
include the standard Grant type periscope housings and the Australians
made do with what they had. A number of the Lees can be seen to have
had the factory installed sand shields trimmed (5) rather than
completely removed. For whatever reason, the 37mm turret guns have been
removed from these Lees, but it appears that this was not the case with
the M3(A1?) Stuart near the rear of the train. © State
of New South Wales through the State Archives and Records Authority of NSW 2016.
We can record another
pair of Lee WD Numbers (T-26029 and T-26061) in this rear
view of the same train as it pulls into Homebush station
a few minutes later. All of the Lees can be seen
with the formation sign of the 3rd Australian Armoured Division
(1), which was in the process of being disbanded at this date. The
rear angled stowage boxes (2) appear to be direct copies of the UK
pattern boxes, but without the No. 4 Essex methyl-bromide fire
extinguishers mounted on top. It can be seen
that armored housings (3) have been retrofitted to
protect the very vulnerable engine air intakes, a serious fault of
the M3 design. These are of the Australian pattern which
differed in detail from the UK design that we discussed
previously. Almost all of the world's surviving Grants and Lees
are ex Australian Army. A clue to their origin is the multi-section
bullet splash (4) that was retrofitted around the base of the turret.
These have also been noted on a small number of surviving M3 Mediums in
India, but not on those from the former Soviet Union, US or Great
Britain. © State of New South Wales through the State Archives and Records Authority of NSW 2016.
In
the previous NSW railway images, the turrets were facing away from the
camera, but in this view, we can see that the 37mm gun mantlets of
T-26031 and the next tank are fitted with the dust cover strips. Both
are late production, no doors Chrysler Lees with the R-975-C1 exhaust
and air cleaner set up. The protective cover (1) retrofitted over the
engine air intake is much more elaborate than the simple hinged cover
used in the design of M4 and M4A1 Shermans. A pair of fittings (2) are seen welded to the bottom edge of the upper rear hull
plate. Again,
note the different configuration of the periscope covers on the
commander's hatches when compared to the standard Grant type driver's
periscope housings. We
can't explain the absence of the 37mm guns in these photos. Once the
danger of a Japanese invasion had passed, the three Australian Armoured
Divisions were eventually disbanded. The 3rd AD, whose tanks are seen in
this February 1944 series of photos, was the last to be disbanded in
March 1944. Perhaps the removal of the 37mms was the first step in the
retirement of these Lees? © State of New South Wales through the State Archives and Records Authority of NSW 2016.
We would
observe that the dust cover strips do not appear in the series of DTA
factory photos where many of the Lees are seen with Registration Numbers
indicating June 1942 acceptance. However, they do appear in the August
photo series which led up to the moment when "Chrysler M4 Tanks Crowd
Last M3 Off The Lines." In this cropped view, the 4 Lees with installed
turrets are seen to have the fittings. In the absence of documentation
or much counting heads evidence, we would simply speculate that some of
the very last Chrysler Lees had the dust cover strips factory installed.
Note that the Lees do not have commander's cupolas fitted, perhaps
suggesting that they may have been meant for Commonwealth Lend Lease. On
the other hand, they have the upper grouser box fitted which would have
to have been removed to make way for the Grant type driver's periscope
and housing.
There is one surviving Lee that has (or had) a dust cover for the 37mm
gun. This is ex-Australian, SN 4540 (July 1942). Chris Hughes
photographed it at the Littlefield Collection, but it is now on display,
without cover, at The American Heritage Museum in Hudson, MA. The cover
strikes us as a little too clean to be new old stock. On the other
hand, it looks pretty real with a zippered flap (1) in front of the
gunner's sight, which, apparently, was rolled up and secured to a buckle
(circled) when necessary. In any case, it has "37 M.M. GUN PLATE" and
the Part Number "D51353" stenciled on (inset 1). In the overly-comma 'ed
Army nomenclature, we suspect that this item would actually have been
named "COVER, 37 M.M., GUN PLATE." No doubt it would have been buttoned
through the grommets to something like the strip seen in the previous
captions, which is not present on this example. As cited earlier from
David Doyle's "M3 Lee/Grant", the Waterhouse Company was reported to
have been contracted to produce 700 sets of 7 types of canvas covers for
the M3 Medium including ones for "Cover, 37mm., Gun Plate." These were
to be attached to "steel frames" provided by Waterhouse and tack welded
on to the tank. Inset 2 is a blow up of the only period photo we know
showing the cover on one of the last DTA Lees, USA 3058309. It appears
to have been attached with slotted, round head bolts or machine screws.
Should any readers have any further info about the "Cover, 37mm., Gun
Plate," we would be pleased to have a report. Since many of the late
Commonwealth Lend Lease Lees were shipped without the US machine gun
cupola, that item has become practically a "Holy Grail" search for
restorers. In the case of SN 4540, an MG cupola from a Canadian Ram has
been substituted. The Lee's cupola had direct vision visors on each
side, while the Ram's did not. As a matter of minutia, we would note
that another of the Waterhouse covers reportedly produced was "Cover,
Cupola" also to be attached to "steel frames." We would further point
out that SN 4540 can be seen with a strip around the driver's
protectoscope (inset 3). This is likely for the Waterhouse item "Cover,
Door, Indirect Vision." Photo courtesy of Chris "Toadman" Hughes.
Leife Hulbert photographed the M3 Lee preserved at the Australian Army
Tank Museum at Puckapunyal. He found the Serial Number 3711
stamped on both the front and rear towing lugs, indicating that it was
accepted at the Detroit Tank Arsenal in May 1942. The corresponding
Registration Number would have been USA 3010346. This Lee can be seen
installed with ventilators (1) which we believe were introduced in May
about 200 units before 3711. The grouser boxes appear to have been
introduced at about the same time, and the outline of the box on the
glacis plate (2) is visible here. Note how it could be installed over
top of the rivets (arrow), since the boxes were open on the bottom.
Serial Number 3711 "still" has working side doors. Not long after this,
the doors were either welded up or completely eliminated at Chrysler.
The evidence suggests that Chrysler would have shipped this tank with
one fixed machine gun ready for install, but it can be seen that the
ports (3) were plugged and welded up, most likely during processing in
Australia. The driver's periscope and cast housing (4) would have been
provided and installed in the US and necessitated the removal of the
upper grouser box. The 37mm gun can be seen with a counterweight for
the gyrostabilizer. The 75mm would have been shipped with a
gyrostabilizer and counterweight as well, since Chrysler reported that
they began to install gyros around the end of January or beginning of
February 1942. Since the first 23 Lees were shipped to Australia
in early August 1942, we suspect that May might have been about the
earliest production month of the Lees they received. We can at least
observe that, to date, we haven't come across any period photos showing
Aussie Lees without ventilators. The War Department Number of this
Lee appears to have been lost to time as it has "25154" painted on
which is a Grant T-Number, inappropriate to a Lee.
In
this view looking down onto the left side of SN 3711, the locations of
the ventilator (1) and the driver's cast periscope housing (2) are seen
to good effect. The inset, shows a close up of the housing (from another
Aussie Lee owned by the late Rod Bellars) with a British Part Number WD
1628 and the caster's logo of a US Company - Sivyer Steel. It is
thought that the fitting marked 3 and the non-standard holes in the hull
roof (circled) had something to do with the Australians' preferred
method for mounting the antennae for the British No. 19 radio, which, in
the Lee, would have been located directly below in the left front of
the hull. The holes for mounting the Lee's standard cast "antenna pot"
are not present on the plate marked 4. However, based on the rivets
missing from the lower section of the angle iron (arrows), we suspect
that this plate was a replacement taken from a Grant. The multi-part
turret splash (5) appears on just about every surviving ex-Australian
Lee or Grant. The protection is continuous on other examples, so we
would assume that the section missing here had somehow broken off. It
strikes us as odd that a simple handle was not part of the design of the
Grant style split hatch (6). Note the open at the top periscope housing
(7), somewhat like what is seen on British Crusader tanks.
In this rear view, the stub (1) of one of the "Quick Fix" fishtail
exhausts (inset) is present which suggests that this tank was built with
an R-975-EC2 radial engine. The "Quick Fix" exhaust and air cleaner
modification was likely original, installed at the factory by Chrysler.
They reported that they began installing the "Quick Fix" on 10 March
1942 and would do 600 units before the change was made to the
"production modification" which we interpret to mean the introduction of
the R-975-C1 engine with the final, M4/M4A1 exhaust and air cleaner
configuration. We would mention that while the final set up included a
pair of mufflers mounted inside just ahead of the "high" exhaust
outlets, the "Quick Fix" mod did not include mufflers at all. In any
case, while we have no reliable way of counting heads, we would guess
that SN 3711 was one of the last Chrysler Lees built with the R-975-EC2
engine and the "Quick Fix." Note the "mystery" plates (2) and footman
loops on the turret rear. There is no weld scar evidence that this Lee
was ever installed with the symmetrical, US type stowage bins on the
rear sponsons. Again, we suspect that SN 3711 may have been one of the
last Chrysler Lees produced without the bins. At present, our counting
heads evidence hints that these were factory installed starting in early
June 1942, at least at Chrysler. The fittings marked 3 would indicate
that this Lee was once installed with the angled rear stowage boxes
patterned after those devised by the Department of Tank Design in the
UK. The fittings marked 4 suggest a former installation of the Aussie
pattern armored cover over the engine air intake. The fittings marked 5
present another mystery. They are seen in period photos and on a few
surviving, mostly Aussie Lees, although nothing is ever shown attached
to them.
Leife photographed some of the bogies of SN 3711. The example
shown here has a casting date of "2-42" [Feb. 1942], while another has
"3-42." It can be seen that the wheel on the left has a pressed metal
"face" without spokes, while the one on the right is the standard spoked
type used by Chrysler to the end of Sherman VVSS production. Note the
rivets (circled) which held the discs on to the wheel rims. The return
roller attachment to the bogie bracket (1) is in the original
configuration. Again, observe how little space there is between the
bottom of the return roller and the bogie bracket. Hence the spacer
modification. At present, we find no evidence that any Lees or Grants
were built with the spacers factory installed.
Here
we see a very nice example of a running, ex Australian no doors Lee,
that is a popular attraction at the Americans in Wartime Annual Open
House in Virginia. Note the multi-part
turret splash (1). As a July 1943 production Chrysler, this tank would
have been built with the "high" exhaust pipes (2) and the external air
cleaners (3). The inset shows the very neat way that Chrysler filled in
the pepper pot holes (4) on the Lees they built with R-975-C1 engines.
When
the side doors were welded up or eliminated, an escape hatch was added
in the Lee's belly plate. David Doyle photographed the hatch inside the
Americans in Wartime Lee. It was installed directly behind the 41 round
75mm ammunition bin (1). As designed this bin was open at the rear, so
it is thought that the folding armored door (2) was added by the
Australians as part of a program to better protect the M3's ammunition.
In the absence of any Ordnance photos, we won't assume that this
represents the configuration of the Lee's original escape hatch
but would note that it is identical to the one designed for the T6 pilot
and used on many production Shermans. The right side photo shows the T6's
escape hatch as photographed at APG in August 1941, nearly a year before
the side doors were eliminated on the Lee. The hatch was secured at 4
points and could be opened or closed using the rotating handle (3). A
pair of handles (4) were installed to assist crew members with
lifting/retrieving the heavy hatch. For re-installation, "One member of
the crew must lift and hold the hatch cover in place from underneath the
vehicle while a second member locks the release and locking mechanism."
The APG caption makes note of the "Flange with Gasket Grooves." There
were some complaints early on that the hatch was not completely
weatherproof or adequately secured, but these issues were soon remedied.
As
noted on our Grant page, of
the 757 M3 Mediums received by Australia only 3 Grants (diesels) are
known to have been deployed overseas to a combat theater - Balikpapan in
July 1945. Thus, any of the Lees that were actually issued would have
served in training units. Despite the large numbers of AFVs received by
Australia, there is no evidence that any tank retrievers of either US or
British design were supplied. Consequently, a few M3 Lees were
converted to an indigenous design of tank recovery vehicle. The photos
above show one such example, which is labeled "Australian Grant
ARV" [Armoured Recovery Vehicle], even though it is clearly fitted with a
Lee turret and the WD Number (T-25959) is not applicable to a Grant.
Judging by the non-standard door on the left side (1), this conversion
was based on a late production "no doors" Chrysler Lee, with side doors
retrofitted. "No door" Chrysler Lees did include a pistol port in the
right-hand side of the hull, and it would appear that it was salvaged
and added to the door (2) retrofitted on the right. As the war ended,
all of the gasoline powered Lees and Grants were declared surplus and
sold at disposal sales, while the diesel Grants soldiered on for another
decade. Many of the surplus tanks were purchased by members of the
public at “fire sale” prices. Some were cut down and converted for
agricultural use. Others were bought as curiosities and preserved more
or less intact. Indeed, most of the world's surviving Lees and Grants
are ex Australian. Interested readers are invited to browse through the Surviving
M3 Lee and M3 Grant tanks PDF list. Aside from complete tanks,
Pierre-Olivier has included hulls and turrets and other bits and pieces
scattered throughout the country.
Lees in India and Burma
A
few days after the 7 December 1941 attack on the US Fleet at Pearl
Harbor, the Japanese invaded the British Colony of Burma. Their
immediate goal was to cut off the "Burma Road," the main Allied
overland supply line to China. Politically, the Japanese thought that
the restless British Colony of India "next door" might easily "fall
into their laps," if they could promote themselves as a liberating
force offering independence. By 26 May 1942, the disjointed Allied
troops that had attempted to defend Burma had been routed out of the
country by the seemingly invincible forces of the Empire of Japan.
Although India was third on the list of British priorities after the
Middle East and the United Kingdom itself, men and materiel were
shipped out to forestall the Japanese, and it was hoped, eventually
retake Burma. In this regard, the British allocated quite a bit of
armor to India, including 896 Lend Lease M3 Medium Tanks. The first
exports from the US are listed on 24 February 1942 and consisted of 16
Grants and 8 Lees. The shipments continued until a total of 369 "Grant
Gas," 10 "Grant Diesel," 515 "Lee Gas" and 2 "Lee Diesel" had been sent
by the end of 1942. The photo above shows mostly Lees, but focuses on
an M3A3 Grant, one of the only 12 diesel powered M3s shipped to the
country. T-24022 would have been accepted at Baldwin in June 1942. US
records indicate that this tank was “In San Francisco Awaiting
Shipment, October 15, 1942.” However, the photo is dated 27 April
1943, over 5 months later. The caption describes the scene as at an
"Indian port city." British records state that materiel was received at
the ports of Karachi (now in Pakistan) and Bombay (present day Mumbai)
on the west coast of the country. We would point out that the Lees are
outfitted with M3 Grant type sand shields such as seen in the Richmond
Tank Depot photos in the Australia section. Furthermore, only a small
number of the Lees can be seen with the machine gun cupola. As with
Australia, many of the Lees were shipped without cupolas, and the Grant
type split hatches were provided by the US later as they became
available from the manufacturers.
The photo
above is dated 10 July 1942, and shows an earlier shipment since the
Lees appear to be as built with no sand shields or driver's periscopes
retrofitted. Some
of the Lees are missing their 37mm guns, but the M3 Grant in the
foreground has one. The caption has it that these were part of "a huge
convoy from Britain." As with Australia, we can assure our readers that
all of the Lees and Grants were shipped new from the US. The caption
also cites "hundreds of tanks lined up ready to go into action against
the Japs." However, a 10 November 1942 report from the US Army Training
Detachment in India suggests that conditions at the ports of Karachi and
Bombay and at Kirkee Arsenal were chaotic. It would seem that too many
tanks were shipped to India too quickly which overwhelmed the available
infrastructure. The report concludes that "No possible excuse can be
seen for issuing these tanks in the condition that has been noted in
this report. These tanks are supposed to be FIT FOR COMBAT. While the
Tank Units in India are now in a training period, a sudden invasion of
this continent would undoubtedly require their use." Fortunately, the
"sudden invasion" didn't occur until March 1944, giving the theater
precious time to train and get things sorted.
The monsoon season in Burma (now Myanmar) generally runs from May
through September. Thus, during WW II, offensives were conducted in
between the monsoon months. In late 1942/early 1943, the Commonwealth
attempted a limited offensive in the Arakan on the northwestern coast of
Burma. After being run out of the country 6 months earlier, it was
thought that a small victory in the Arakan might boost the sagging
morale of the forces in India. Elements of the 14th Indian Division
crossed the frontier and advanced down the coast until they were stopped
by a strongly fortified position at the town of Donbaik. Repeated
attacks failed to dislodge the Japanese. Armor support was minimal and
consisted of 16 Valentines of C Squadron, 146th Regiment, Royal Armoured
Corps. The Japanese counterattacked and threatened to cut off the
Commonwealth force, which retreated back into India in May 1943. In
January 1944, a much larger force, the Anglo-Indian XV Corps of 3
divisions, invaded the Arakan. Armor support was provided by the newly
formed 25th Dragoons. It would appear that the regiment deployed
overstrength with a Reserve Squadron in addition to the usual A, B and C
Squadrons. Again, the Japanese counterattacked starting in February
1944 with the idea of cutting off the divisions and isolating and
destroying them in detail. The Lee as opposed to the Grant appears to
have had its combat debut in the theater on 26 January 1944 when C
Squadron supported an attack on "Tortoise Hill" by the 161st Indian
Infantry Brigade, 5th Indian Infantry Division. At first, the Japanese
"Ha-Go" offensive seemed to be on the verge of success. However,
Commonwealth forces did not retreat this time but formed defensive
"boxes" that resisted all efforts by the Japanese to destroy them. The
"Admin Box" of the 7th Indian Infantry Division has been described by
author Bryan Perret in "Tank Tracks to Rangoon" as "the scene of one of
the most ferocious defensive battles in British history." The 25th
Dragoons' armor was pivotal in defeating the Japanese for the first time
in Burma. The historian of the 5th Indian Division wrote, "The role of
these tanks and their crews cannot be over emphasized. It was their
accurate, high velocity, close range blasting which put our infantry
back whenever the Japanese penetrated our defences or captured any vital
position." The screen captures above are from a (silent) film held by
the Imperial War Museum entitled, "14TH ARMY BREAKS JAPANESE COUNTERSTROKE IN THE ARAKAN:
BATTLE OF THE ADMIN BOX." Both Lees appear
to be Chryslers. The "doored" tank has the later M3 75mm gun while the
"no doors" has the earlier M2 with counterweight. The "no doors" Lee at
least would have been built with standard rear stowage boxes, such as
the one on the right side. The factory bins were symmetrical while the
box seen on the left on both tanks is higher than a factory bin and sits
on an angle. The image on the right shows the no doors Lee from the
rear and it can be seen to have the Quick Fix Exhaust and Air Cleaner
modification, likely factory installed by Chrysler. It is thought that
the rope or wire seen at the base of the turrets provided handholds for
the 3/4 Bombay Grenadiers who were attached to the 25th Dragoons as
infantry escorts.
The photo above is captioned in one instance, "Major General Briggs
arriving on 25th Dragoons Lee "Shrewsbury" in the relief of The Admin
Box 24th February 1944." Lt. General Sir Harold Rawdon Briggs was
commander of the 5th Indian Infantry Division. For a few days at the end
of January 1944, the 25th Dragoons supported the 5th Indian Division
who were attacking down the Arakan coast. On 4 February, the 25th was
ordered to head east across the Mayu mountain range via the Ngakyedauk
Pass in order to support the 7th Indian Infantry Division in its attack
on the town of Buthidaung. However, the 25th's reserve squadron remained
with the 5th Division as a deception measure. Shortly after the
Dragoons' Lees had crossed, the Japanese managed to cut the Ngakyedauk
Pass and get between and behind both the 5th and 7th Divisions. Rather
than panic and retreat as the Japanese expected, the Allied troops
formed defensive boxes that ultimately foiled the Ha-Go Offensive. The
scene captures the dramatic moment when the 123rd Brigade of the 5th
Indian Division supported by the reserve squadron broke through the
Ngakyedauk Pass (called "Okeydoke Pass" by the Allied troops) and
reestablished contact with elements of the 7th Division besieged inside
the Admin Box. The fighting continued until the monsoon rains came in
May, with the front stabilized along a line from Maungdaw on the coast
to Buthidaung in the valley east of the Mayu mountain range.
"Shrewsbury" can be seen with bogie brackets with horizontal ribs
typical of Chrysler Lees. This tank has the driver's periscope (1) which
was retrofitted on Lend Lease Lees at the request of the British. It
appears to have a ventilator (2) next to the driver's periscope which,
coupled with the working doors, would lead us to put the tank's
production date around May 1942. The high, angled stowage bin (3) would
have been a local addition. Without seeing other photos, it would be
hard to say if this tank was shipped with factory installed stowage
boxes, but most "ventilated" Lees were. This photo and the IWM footage
suggest that the 25th Dragoons may have installed the Number 19 radio
antennas at the front of their tanks as seen here. The longer "A set"
antenna (4) was 8 feet, while the "B set" (5) was only 25 inches. The B
set's wiring appears to have been protected inside a box like conduit.
The monsoon rains brought the Arakan front to a standstill, and in late
June 1944, the now veteran 25th Dragoons were ordered to return to India
where they were stationed at Poona. Their Lees remained in the Arakan
in what we assume was some sort of tank dump in a place called
"Dechuapalong" which is/was located a little south of the port of
Chittagong, the Commonwealth supply base on the southernmost border
between India and Burma. We try to record Ordnance Serial Numbers, USA
Registration Numbers, and British War Department or "T" Numbers from
period photos and documents, as well as surviving Shermans, variants and
predecessors. The 27 June document above lists the "B.A. Numbers"
[British Army?] of 73 of the 25th Dragoons' Lees in the Arakan as they
sat out the monsoon season and suffered its effects. From "counting
heads" we can state that the vast majority of the Lend Lease Lees
supplied to India were assigned WD Numbers that fall within a range from
T-25199 through T-26459. That is not to say that this range was
exclusive to Indian Lees. Many of those in the UK and Australia have
been recorded with numbers within this range. The highest, T-26459, is
listed in a Vehicle Mileage Return compiled by the No.1 RAC Independent
Tank Delivery Troop, 15th Indian Corps on 31 August 1944. In the Arakan
list above, note that there is one "outlier" T-39232. Along with that,
T-39234 is seen without guns in a period photo in India, possibly a
command tank. Finally, a well-known series of photos were taken in the
UK of T-39481, a Canal Defence Light nicknamed "Giraffe." In any case,
the Arakan Lees were listed in "Class V" condition, the worst, requiring
4th Echelon Maintenance, or basically complete overhaul. There was some
thought that the tanks would be evacuated back to India after the
monsoon, but by 17 August, it was determined that "these tanks shall not
be evacuated but broken up in situ to provide spares...the hulls and
remainder are to be written off." No doubt, the British would have been
aware that the US Ordnance Department declared the M3 Medium obsolete in
April 1944. Since no further spare parts were to be produced, part of
the procedure involved "cannibalization of all salvageable components
and disposition of all non-salvageable parts to the best interest of the
government." The documents suggest that the 25th Dragoons started the
campaign with 80 Lees, since they reported the complete loss of 7 during
the fighting. In any case, 73 is a substantial number and one wonders
if there is any trace of them left in the area? The IWM Admin Box
footage shows at least 1 Valentine Bridgelayer and 9 are listed in the
doc. These were likely from the 3rd (Independent) Bridging Troop
attached to the 25th Dragoons and were valued enough to be ordered
returned to India for complete rebuild. The 16 "Tank Sherman M4A4" do
not appear in the Admin Box footage. These were left behind by C
Squadron, 149th Regiment RAC which had been deployed to the Arakan at
the height of the Ha-Go offensive and fought in support of the 36 Indian
Infantry Division in April and May 1944. It would appear that these
would have been the first Shermans to go into combat in Burma. They were
ordered to be brought into operational condition in place so that they
could be used "as reserve tanks for the AFV Formation allotted for
operations in the ARAKAN 1944-45."
The last combat action for the M3 Lee during WW II appears to have taken
place on 16 May 1945 when the Lees of A Squadron, 3rd Dragoon Guards
(3rd Carabiniers) of the 254th Indian Tank Brigade along with a troop of
M4A4s from A Squadron, 19th Lancers, 50th Indian Tank Brigade attacked a
Japanese strongpoint about 60 miles north of Rangoon. Details are
sketchy, but the Lancers reportedly captured a Ha-Go light tank intact.
With the defeat of the Japanese in Burma, the 254th Tank Brigade
returned to India in June 1945 where it was intended that the 3rd
Dragoon Guards would be re-equipped with Churchill tanks in
anticipation of Operation Zipper, a series of amphibious landings
planned for August/September 1945 with the objective of recapturing
Malaya and Singapore. The caption to the photo above is headlined
"Prome, Third City in Burma is liberated" and there is a note that the
"Picture was issued May 1945." On 3 May 1945, a mobile column led by A
and B Squadrons of the 3rd DG captured Prome without a fight as the
Japanese garrison had fled. In any case, although not the most
informative, this would be the latest dated photo we could find that
shows M3 Lees in combat during WW II. The lead tank can be seen with the
name "ANGEL" painted on the side door which would lead us to suppose
that it was a Lee of A Squadron. One source has it that the extremely
large Allied stars seen here only begin to appear on the Lees of the
254th Indian Tank Brigade starting in 1945. The bags hanging from the
side of the lead tank likely belonged to the "tank protection infantry"
that were assigned to escort these tanks. A "Lessons from Ops" comment
recommends that for future operations, "Adequate arrangements must be
made for the carriage of inf kits, rations, water and cooking pots
elsewhere than on the tks." The trailing Lee appears to have had its
original T41 flat block rubber tracks replaced with the “WE 210” rubber
block tracks that were standard equipment on Grants.
The M3 Medium was an ungainly looking thing. However, author Bryan
Perret described it as "A tank which could have been specifically
designed for use in Burma...The advantage of such a layout was that the
75-mm could always be used on the target ahead, whilst the [37 mm gun in
the] top turret could be traversed to sweep the surrounding trees clear
of snipers." M3 Medium crews claimed "that the difference of axis
between 37 mm and .3 Browning [coaxial machine gun] and the 75 mm gun
has been invaluable. There are several cases of tks firing at two
different targets at the same time. They also claim that 37 mm cannister
has fully proved itself." Despite requests from some armored units,
such a round was never developed for the 75mm gun. Jim Goetz visited the
surviving M3 Lee on display at the Armoured Corps Museum in Ahmednagar,
India. He was not permitted to look for the serial number, but from its
appearance, our guess is that this unit was produced by Chrysler in May
1942. We base that on its similarity to SN 3711 at Puckapunyal, with
working side doors and ventilators, but no evidence of factory installed
rear stowage bins. The red fittings on the front appear to have been
retrofitted in theater for installation of the Number 19 radio antennas
with fitting 1 for the long "A set" antenna and fitting 2 for the short
"B set" antenna. We can observe that we have seen a few period photos
that show the B set bracket mounted on the dual fixed machine gun
casting as seen here. They are noted on Lees of C Squadron, 150
Regiment, Royal Armored Corps, 254th Indian Tank Brigade during the
battle for Mandalay, March 1945. One example is "Caledonian". The WD
Number, T-26217, may be authentic, or at least we can say that it is
appropriate to an M3 Lee, although we don't have an historical listing
for that particular number. On the other hand, the tank is labeled "M3
Grant."
In this view, note the little hand hold fittings (1) seen in many period
photos of Lees in Burma. Item 2 held a pair of 4-inch smoke mortars,
and these are also common fixtures in period photos. Item 3 may have
been installed to secure a theater made stowage bin to the left rear
sponson.
The Variants: M3A1 Lee
As the United States geared up to become "the Arsenal of Democracy," the
automobile, locomotive and steel manufacturers quickly adapted to "war
work." They began to introduce more efficient production methods, along
with many technological advances. The photos above show the earliest
conception of the M3 upper hull, produced as an experimental casting. In
September 1940, this was thought to be the largest armor casting ever
made. After some refinement, the steel industry was able to demonstrate
that such large castings could be produced to Government ballistic
specifications. Furthermore, casting reduced the amount of assembly
time, and eliminated the rivets of the original fabricated hull design.
It was stated that this method offered a savings of about $3000 per
tank. On 19 June 1941, about 2 1/2 months after Rock Island Arsenal had
completed the M3 Lee [riveted hull] pilot, the Ordnance Committee
"authorized the use of cast upper hulls for medium tanks" as an
alternate method of construction. Note the use of the generic term
"medium tanks." We would remind readers that the M3 was an interim
design, and the cast hull innovation was really aimed at its
replacement. Thus, on the same day that the use of the cast hull was
approved, the Committee also approved creation of a full-size wooden
model of a cast upper hull with the main gun mounted in a fully rotating
turret. This would be followed immediately by the Medium Tank, T6 pilot
(the Sherman) which was "presented" at APG on 3 September 1941.
The photos above show "General Steel Casting Corp. Top Hull #2"
photographed on 18 March 1941, the day after it arrived at APG. Its
appearance is quite a bit different from the hull shown in the previous
caption, but the notes in the margins of the photos indicate that
further changes had already been made. "The upper left part of the hull
will be more "streamlined" and "This door with pistol port was for the
purpose of removing the 75mm gun. A new design of hull will not have a
door in this shape." The chalked on "Figures indicate thickness of hull"
and show quite a bit of variation, with the front appearing to be about
3 inches at the top reducing to 1 5/8 inches towards the bottom, and
the sides averaging about 1 3/4 inches all around. After ballistic
tests, it was reported that Top Hull #2 "passed every specification for
cast armor with something to spare. In addition, this cast hull resists
other types of fire (particularly as regards shock) very well."
Consequently, APG recommended that "A cast upper hull for Medium Tank,
M3 be standardized as an alternate construction at an early date."
The
same 14 April 1941 Report from APG noted that another General Steel,
Eddystone upper hull casting "was machined and sent to Rock Island
Arsenal where it will be made into a Medium Tank, M3." The completed
pilot tank was shipped to APG without turret on 4 June 1941. If "walk
around" photos of the cast hull pilot were taken, we have not come
across them. Instead, we offer a partial view of the tank dated June
1941 and focusing on a test of "interrupted parallel grouser type
[tracks] made of cast steel by the American Steel Foundry...installed on
Medium Tank, M3 #2372 (cast hull)." Several APG reports describe this
tank as "#2372." We assume this to be the Serial Number, which would
have been the first available M3 Medium Serial Number after the initial
contracts to Chrysler (1000), ALCO and Baldwin (685 each) were let. This
has created something of a problem for us, since there is some evidence
that the supplemental contract with Chrysler for an additional 1600
units (P.O. T-1473) started with SN 2372/USA 309007. We could have a
case of double Serial Numbers assigned, but we might note that the
various RIA M3 pilots were never officially accepted according to the
Army Service Forces "Summary Report of Acceptances." Barely visible in
the photo is the Registration Number "USA W-304192," confirmed in
another photo from the track test (inset). Readers might recall that the
RIA riveted hull M3 pilot was 304191. From the little that can be seen,
this casting appears to be a bit more "streamlined" than Hull #2, but
not quite the shape of the production M3A1. The tracks tested reportedly
weighed 2000 pounds more than "the standard rubber block. This tends to
make the vehicle sluggish and considerable power is necessary to make
turns because of the firm traction of this track." In the photo, the
tracks appear to be the T37 type of "interrupted parallel
grouser" tracks which ultimately were not approved for production.
The RIA
pilot was referred to in reports as "M-3 Medium Tank (Cast Hull)" or
some variation, but on 9 October 1941, Ordnance Committee Memorandum
17301 provided the nomenclature "M3A1." Additionally, at this early
date, the Committee recommended the elimination of the side doors "from
the cast steel hull [which] will allow the casting to be strengthened
structurally and also result in improved ballistic resistance." This
recommendation applied to the T6 (Sherman) pilot as well. In both cases,
an escape hatch in the belly plate was to be provided. Elimination of
the side doors was implemented at the start of M4A1 production in
February 1942, but not until May on the M3A1 as best we can determine.
In the meantime, the Ordnance Department was searching for alternate
power plants for its medium tanks, and on 10 July 1941, the cast hull
pilot was installed with the Guiberson T-1400 radial diesel engine.
Testing revealed that performance and fuel mileage were superior to the
gasoline powered Wright/Continental R-975-EC2, but the engine proved
unreliable and in May 1942, the Government terminated its contracts for
the T-1400 under a cloud of controversy. "...the contractor grossly
misrepresented that the No. 1400 was a perfected engine." ALCO was
contracted to produce the M3A1s, and its original contract for 685 M3
Lees was amended so that 300 of the units were to be M3A1s. These were
produced alongside the M3 from February through August 1942. Author
Richard Hunnicutt has it that it was initially planned for all of the
M3A1s to be built with Guibersons, but "only 28 were completed using
this engine." Author David Doyle has raised a question about that
number, citing OCM 22178, dated 25 November 1943 which reads, "There has
been only one vehicle built to date using the engine." The OCM goes on
to recommend that the 111 T1400 engines in storage be disposed of as
"obsolete material." In any case, the RIA pilot appears to
have ended its days at APG. In August 1943, it was used as a target for
7.5 cm A.P.-H.E. (Armor Piercing-High Explosive) from a captured German
Pak 40 anti-tank gun.
As best we can determine, the world's only surviving ALCO built
Lee is the cast hull M3A1, Serial Number 1962/USA 306032. It was on
display for many years at the Ordnance Museum at Aberdeen, but is now in
storage at Fort Lee, Virginia. Although we haven't come across any
confirming documentation, we believe that this was the first M3A1
produced by ALCO. "Officially" it was not accepted until February 1942.
However, the photo above is part of a walk around series shot at APG
reportedly on 6 December 1941, so we have something of a timing mystery.
We would note, however, that there were a few cases, such as
Chrysler's, ALCO's and Baldwin's first Lees where they were shipped to
APG well ahead of their official acceptance. Note that the typed info
has it that the engine was the Guiberson T-1400, possibly reflecting the
original intent of equipping all the M3A1s with T-1400s? A Technical
Manual dated September 24, 1942, was published - "TM 9-1750E, Ordnance
Maintenance Guiberson Diesel T-1400 Engine, Series 3, for Medium Tanks
M3 and M4 and Related Gun Motor Carriages." We examined it thinking we
might gain some insight, but there is not a single photo or illustration
showing the engine installed in a tank. Of course, we don't know when the typed info was added to the photo.
Note that the transmission is listed as "Caterpillar." As best we can
determine, Cat did not produce any M3 Medium Power Trains. ALCO would
have been supplied with P.T.s primarily from Mack, with perhaps a few
Chryslers thrown in from time to time. Also, "3 cal. .30 machine guns"
are listed when 4 can be seen installed. As mentioned previously, one of
the fixed MGs was ordered eliminated in June 1942. Oddly, the crew is
given as "only" 6 even though this tank was built as a Lee, not a Grant.
This rear photo shows SN 1962 with the typical pepper pot exhaust,
suggesting that if this tank was shipped to APG with a Guiberson
Diesel, it was a drop in fit, requiring no external changes to the
original exhaust layout of the R-975-EC2. Unlike the M3, the M3A1 design
did not include a pistol port in the right rear. The large pistol port
seen on the top hull hatch door on hull #2 was likely intended to
replace it, but as can be seen here, it was indeed eliminated. The plain
and flat door (1) was the first iteration and was hinged at the top.
From personal examination, we can report that the casting was made by
Union Steel and was Part Number D38464, Serial Number 1. The low serial
number is one of the reasons we believe that this was the first M3A1
produced by ALCO. The original M3 design provided for an antenna bracket
(2) on the left rear, but here we see that another bracket was added to
the right (3). We suspect that SN 1962 was configured as a command
tank with the interior stowage rearranged to accommodate an additional
long-range radio. Note how the sides of the hull casting went all the
way to the rear, which eliminated the shot traps created by the "jogged
in" design of the M3. This makes the rubber mud flaps (4) appear ill
fitted, but they are mounted in about the same location as on the M3.
The taillights (5) were nicely "streamlined," by being inset into the
cast hull. However, this practice did not carry over to the M4A1
Sherman, possibly because the inset taillights were difficult to
service.
Here we have a photo of SN 1962 taken from about the same angle as that
seen in the previous caption. We shot this at APG in 2003 shortly after
the tank had been stripped and repainted. At some point, the pepper pot
exhausts were removed, and a pair of side plates (1) were added to
provide partial support for the retrofitted external air cleaners (2).
The pepper pot holes (3) were usually blanked off, but those on SN 1962
are not. Door bumpers (4) were also added. Note that the exhaust pipes
(5) are in the "high" position. All of this suggests that the tank's
original engine, whatever it was, was changed out for an R-975-C1
Continental Radial. It can be seen that the tank was retrofitted with
ventilators (6) during the course of its service as a test vehicle at
APG. The box like object projecting a few inches down from the belly
plate (7 and inset) would not have been standard to an M3 with an R-975
and may be a clue that this tank once had an alternate engine that
required this modification. Unfortunately, the shadows are too heavy in
the December 1941 photo of the previous caption to see if the "box" was
installed. Original rubber mud flaps (8) are rarely encountered on
surviving Lees. It can be seen that the ones on SN 1962 have eroded over
the years. Counting heads suggests that these were immediately replaced
in M3A1 production with sheet metal parts. Indeed, we have not
encountered any other examples of the rubbers in period photos of M3A1s,
and that is one of the reasons that we think that this was the first
M3A1 produced by ALCO. Comparing this 2003 photo with the December 1941
photos, it can be seen that, at some point, SN 1962 was retrofitted with
the spacer modification (9) that raised the return rollers by about an
inch.
In
this view, it can be seen that the production hull casting featured a
kind of "shelf" (underlined) on the left front. This complex shape is
not present on hull #2 or the RIA pilot. Note that there is yet another
antenna bracket (1), a fairly simple one, welded to the "shelf." This
particular bracket assembly may have been exclusive to SN 1962, or at
the least we can state that we have not seen it in any other of the few
photos of M3A1s. While hull #2 and the RIA pilot had little bullet
splashes to protect the hinges of the side doors, it is apparent that
"doored" production castings did not. Speaking of bullet splashes, the
M3A1 cast hull did not require the reinforcing struts atop the fighting
compartment as on the M3 design. Thus, as can be seen here, there was no
bullet splash to protect the turret ring area from being jammed by
small arms fire or shrapnel. A turret splash was incorporated into a
revised hull casting, and counting heads suggests that the new castings
began to appear alongside the old early in production, around March
1942. The original M3 design incorporated a pair of tripods "carried on
the outside of the tank for use with the bow machine guns." Fittings
were provided for one to be stored on the left front just below the
pistol port. They are not present on SN 1962. Looking at the limited
number of photos of M3A1s, we would observe that tripod fittings on the
left front appear sort of "randomly." There are no counterweights on the
37mm or 75mm guns, which we take to indicate that SN 1962 was not
factory installed with gyrostabilizers.
In this view from the right and a bit overhead, it can be seen that the
rear engine deck panel (1) was shortened a bit to fit the cast hull. The
engine deck panels on SN 1962 were (and still are) affixed with nuts.
It is thought that the decks of subsequent units would have been
attached the usual way with hex head bolts. The tool stowage appears to
have been in the same configuration as the M3. There are fittings for an
idler adjusting wrench to the left of the tow cable, but the wrench is
consistently missing in most period photos. As with the M3 pilot, no
provision appears to have been made for stowage of the engine crank. The
"Mattock, pick, M1 (5-lb. head)" (2) was stored on the right front
alongside one of the tripods (3), while the mattock handle (4) was
stowed on the engine deck alongside the "Ax, chopping, single bit, 5
lb." The M3 series tool and towing cable stowage was inconvenient when
it was necessary to remove the engine deck panels, and the Sherman
design relocated these items to the sponsons and upper rear hull plate
where they wouldn't interfere. An interesting quirk in the cast hull was
the "bump" (5) which presumably provided an inch or two of extra head
room to the driver.
Here we have a close-up view of the "bump" (1) just above the driver's
hatch. Ventilators (2) appear to have been retrofitted to SN 1962 in the
Spring of 1942. The inset shows the left front vent in place in a photo
dated May 1942. As mentioned previously, counting heads suggests that
Chrysler introduced ventilators in production around May 1942. However,
we have not been able to collect enough data to determine the case with
ALCO. The photo provides a good view of the unprotected turret ring (3)
of the initial M3A1 hull casting. Note the "shelf" and the method of
assembly of the antenna bracket (4) welded on to it.
We
recorded the SN from the right front tow lug of the differential
housing as 1962 with a "C" prefix as seen in the top photo. However, as
best we can tell, the "C" is not present on the right rear tow lug
stamping (bottom). At first, we had assumed that the "C" might have
stood for "cast hull," but there are a couple docs that mention a C
prefix on what must have been ALCO M3s, like "Ord.# C-1721...305791"
listed in an October 1941 incident report from Ft. Benning. SN 1721
would have been produced in Sept. 1941, well before the first M3A1 was
officially accepted. It would be nice to be able to confirm if ALCO M3s
had "C" prefixes, but there don't appear to be any known surviving
examples. In any case, the Ordnance Department documents providing the
serial numbers (no registration numbers are given for ALCO Lees) have it
that the M3A1s were assigned serial numbers in a block running from
1687 through 1986. That is demonstrably incorrect; for instance, we
showed some photos of SN 1687, the first ALCO M3 Lee earlier in this
piece. Our "interpolation," which is shown at the top of the page, is
based on counting heads. What appears to have been the case is that the
300 M3A1 Serial Numbers were indeed assigned in a block, but the SNs ran
from 1962 through 2261. The first 275 M3s were assigned SNs 1687
through 1961, and the last 110 M3s ran from 2262 through 2371. Readers
should think of this interpolation as in "beta" and we would gladly
welcome any confirming or refuting evidence.
The next M3A1 we can document is SN 1966, shown in the photo above next
to SN 1962 in a shop at APG. This tank was the subject of an Inspection
Test in the Spring of 1942. From time to time, APG would examine
completed vehicles "to determine through a close mechanical inspection
and a standard series of tests, the faults...which may be attributed to
poor design, manufacture, or inspection." This was essentially a second
acceptance test. Often, the subjects were retained at APG for further
tests or experiments. SN 1966 is described as "powered with a
Continental R975-EC2 Engine, #119765 through a Transmission, Model M3,
#680, manufactured by the Mack Company." The presence of counterweights
suggests that this unit was installed with gyrostabilizers, and indeed
these were tested for 100 miles during the inspection. The counterweight
for the M2 75mm gun appears to have been standard across M3 Medium
production. On the other hand, the 37mm counterweight varied somewhat.
This unit has a capped plumbing pipe (1) such as seen on the RIA M3
pilot. This version appears in a few other photos of M3A1s. SN 1966 does
not have a left front antenna bracket (2) installed as on SN 1962, nor
does it have fittings for the MG tripod on the left front. In this
photo, SN 1962 can be seen with a ventilator (3) installed above the
left front pistol port. In addition, a "blackout driving light" (4) has
been retrofitted. As mentioned earlier, this item was released as Field
Service Modification Work Order, G104-W45 on 4 May 1943.
Our next example is SN 1986, USA 306056 shown above in May 1942.
This was labeled "M3A1E1" ("E1" signifies the first experimental version
of the M3A1). This unit was General Motors Proving Ground Project 8022
and was used as a testbed for yet another dead-end alternate engine -
the Lycoming T1300 which combined 3 aircraft engines into a single unit.
Results were promising but service of the power plant was unacceptably
difficult, and the project was terminated. The weight of the engine is
evident in the greater compression of the rear most bogie unit. Also
apparent is that the powerplant was larger than the R975 series and
required extended access doors (1) and a "blister" (2) on the rear most
engine deck panel. Note what appear to be standard external air cleaners
(3), but that the high mounted exhausts pipes (4) are wider than those
used on the R975-C1 Radial. The tank is seen without guns, pioneer tools
or antenna bracket(s). As with SN 1962, the fire extinguisher pull
housing (5) is in an enclosed, nonstandard configuration. Also, like
1962, the engine deck panels are affixed with nuts. The added taillights
(6) are often seen on GMPG test vehicles. The power cable for these
lights may have come from the antenna hole in the left rear, and the
wire may have been held in place by light colored tape.
Here we
have USA 306058 photographed packed with another M3A1 on a rail car.
The painted-on number, "1988," is without doubt the tank's serial
number as it has an exact mathematical correlation to the Registration
Number. Again, we see the absence of antenna brackets and the odd,
enclosed configuration of the fire extinguisher pull housing. USA
306058 would have been accepted in March 1942, and we would assume that
it came from the factory "still" outfitted with the pepper pot exhaust
set up. Aside from SN 1962, this is the only period photo we have
encountered that shows an M3A1 with the original pepper pot system
installed. It was right around this time that the "Quick Fix" exhaust
and air cleaner modification was introduced, and as supplies became
available, was mandated to be retrofitted to all Lees in service that
were built with R975-EC2 engines. An Ordnance Dept. Memo has it that,
at ALCO, "The first cast steel hull having quick-fix modification will
be Serial No. 2114, and will be shipped about April 4, 1942."
Furthermore, the "production modification" would replace the quick-fix
when "Continental Radial Engines [R975-C1] with modified exhaust
collector rings are received." We can verify that the R975-C1 was
introduced in M3 Medium production at Chrysler but can't confirm
if it ever was at the other makers of Lees and Grants. As with SN
1986 in the previous caption, 1988 can be seen with sheet metal (1) as
opposed to rubber mud flaps.
This Office of War Information (OWI) color photo shows 3 "doored" M3A1s
serving with the Demonstration Regiment at the Armored Force School at
Ft. Knox, Kentucky in the Summer of 1942. A close look at the lead tank
reveals "1988" painted on in blue (inset), so it would seem that this is
the same tank as in the previous caption. The door castings (1) were
the same on both sides, with the hinges mounted to the rear on the right
and to the front on the left. The door seen here appears to have the
number "35" cast in. We suspect that this might have been the part
serial number of this particular door casting. As a matter of minutia,
we would note that the highest number we have seen on one of these door
castings is 218. This number would suggest that over 100 cast hulls were
made with side door openings, however, counting heads from a very
limited sample would lead us interpolate that about 200 hulls out of the
300 M3A1s produced were made with door openings, some of which were
built with the doors welded up. We find this somewhat surprising given
that the Ordnance Committee recommended the "Elimination of Side Doors
From Cast Hull" on 9 October 1941, even before the first unit was
delivered. As usual with recommendations for changes, there was the
proviso "as soon as can be done without interference with production."
The lack of 75mm main guns on the M3A1s behind SN 1988 likely reflect
ongoing shortages and/or greater priorities in the Summer of 1942. We
would guess that the M3A1 furthest from the camera was retrofitted with
the rubber chevron tracks for testing. A few of the first Shermans were
photographed in this Alfred T. Palmer Ft. Knox color series such as the
M4A2 seen in the background. Of course, as these became available in
greater numbers, they replaced the Lee which had been classified as
"Substitute Standard" in October 1941, months before the first Shermans
even began to roll off the assembly lines.
Our favorite Alfred T. Palmer color photo was probably taken on
the same sunny day as the image in the previous caption. It shows a
"mixed bag" of Shermans, Lees and Stuarts of the Demonstration
Regiment. We believe that the DR received no more than 5 or 6
March production M3A1s as they became available in the Spring of 1942.
In this photo, there are 2 more M3A1s in line aside from the obvious
one toward the front as indicated by tanks 2 and 3 in the inset. Tank 2
can be seen to have been assembled using the hull casting that featured
the turret splash (arrow).
By
the foliage, this photo appears to have been taken a few months later
and shows "Boots" Tank B-10 of the Demonstration Regiment being towed
out of the mud. This unit can be seen to have the upper hull casting
that featured the turret splash. We suspect that the bow machine gun
ports have been sealed over with tape or fabric as opposed to
permanently welded closed. In
June 1942, the Ordnance Committee recommended the elimination of the
fixed guns, but ultimately it was decided to retain one of the guns.
Despite that, photos show that a surprising number of the Lees in the
Tunisian campaign had both bow MGs installed. This M3A1 appears to be
another example built without the tripod fittings on the left front.
We've recorded a few names of other Armored Force School M3A1s, such as
"Alert" USA 306075, "Big Ben" USA 306068, and "Bumpy" USA 306126, all of
which would have been accepted in March 1942.
The cast hull would have been more combat worthy than the riveted, but
at present, we have found no photographic evidence that any of the 300
M3A1s were shipped overseas (as gun tanks) either by design or by
accident. They appear to have been distributed to units in training in
the US. Most of the available photos show them serving with the 35th and
37th Armored Regiments of the 4th Armored Division. The Division was
activated at Pine Camp, New York (now Ft. Drum) on 15 April 1941, and
received its first M3 (riveted hull) Lees in the Fall of 1941. Tally
Sheets and Product Correction Reports from Pine Camp list a few Serial
Numbers, which indicate that the tanks had been accepted at Chrysler in
September and October 1941. Of interest is that only SN 115/USA 301113
and SN 116/USA USA 301114 are listed as having come with "Grouser,
C-84981" and each reportedly had 158. We can't help but wonder how that
many grousers could have been stored in/on a Lee? In any case, at the
time, the 4th AD would have been a "heavy armored division," requiring
over 200 Medium Tanks. It is thought that they were issued a number of
the new M3A1s that began rolling off the line at the ALCO plant (150
miles southeast of Pine Camp) in the Spring and Summer of 1942. The
photo above is not very informative but shows a "doored" unit with a top
hinged upper hull hatch. Judging
by the snow and bare trees, we would guess that this was one of the
first M3A1s received by the 4th AD. The man in the spectacles was the
original Division Commander, Gen. Henry W. Baird, who was replaced by
Gen. John S. Wood in June 1942. We
were able to record a couple of Registration Numbers, because the 37th
Armored Regiment reported fires in M3A1s USA 306111 and 306132. By our
interpolation, both would have been accepted in April 1942. We suspect
these tanks were shipped with the original pepper pot exhaust, since on
18 June, Major Frank Kowalski, Jr. submitted "recommendations and
corrective measures" regarding fires in medium tanks to the Commanding
General of the 4th AD. A 30 June Armored Force Board Memo referenced
these and other fires and noted that "Modification Work Order now in
effect" no doubt referring to the Quick Fix exhaust and air cleaner mod.
The 4th AD participated in the massive "New York at War" Parade in New
York City on 13 June 1942. From some color footage and still photos of
the parade, we would judge that the 35th and 37th Armored Regiments
combined to field 15 or so medium tanks, and a similar number of light
tanks. Most or all of the mediums were M3A1s (The color footage shows a
single M3 Lee.) We scanned the photo above at the old Patton Museum
Library at Ft. Knox. The high contrast makes it hard to see details, but
when we lightened the photo "USA W-306.253" (inset) "appeared" on tank
3. By our "beta" interpolation, it would have been accepted in June, so
if accurate, it must have been right off the line at the ALCO plant in
Schenectady 172 miles north of NYC. Tanks 1, 2 and 3 all have upper
hulls with turret splashes integrated into the castings. Tank 1 can be
seen with a welded-up door, while 2 and 3 are "no door" castings. The
color footage also shows a spectator rapping on the armor of an M3A1
with a working door. (Note that this segment of the footage is reversed,
as the hinges for the M3A1's side door are on the incorrect side.) The
M3A1s are noted with counterweights on both guns, suggesting that they
were installed with gyrostabilizers. Tanks 1 and 3 have wedge shaped
antenna brackets on the left front, while tank 2 simply has a hole in
that area. All have MG tripod fittings on the left front, but no
tripods, and all appear to have both fixed MGs installed. We suspect
that there was a problem with the supply of idler adjusting wrenches as,
again, they are not present on these M3A1s. Tank 1 can be seen to have
"35-M-11" painted on the differential housing. Typically, this would be
interpreted as "35th Armored Regiment, Company M, Vehicle 11." At least 2
of the M3A1s in the parade footage are seen marked as "Company M" which
is kind of unexpected, since the highest letter company in an Armored
Regiment should have been "Company I."
In
this photo, the medium tanks of the 4th AD parade up Fifth Avenue past
the reviewing stand in front of the New York Public Library. The lead
tanks are the same ones as in the previous caption. This shot was taken
from the other side of the street and being able to see the right side
of the M3A1s is very informative. Tank 1 (35-M-11) can be seen with its
right-side door welded up but retaining a working pistol port. As a
matter of minutia, we would observe that this is the only photo of an
M3A1 we have seen that shows the welded-up door on the right side. Note
the stowage bin on the right rear. We have circled the square shaped
chunk of steel that served as a door stop on M3A1s configured with the
upper rear hatch hinged at the bottom. In both photos, Tank 2 is noted
to have a 37mm gun counterweight without a "collar" as seen on most
others. The tactical markings appear to show "35-E-10." This "no doors"
M3A1 is not equipped with the rear stowage bin. We thought it might have
been reasonable to assume that all "no doors" M3A1s were built with
bottom hinged upper rear hatches, but here we have an example that
contradicts that since it shows the hatch in the original configuration,
hinged at the top. Tank 3, USA 306253, can now be identified as
"37-I-24." The rear stowage bin is present on this "no doors" M3A1 but
again, the upper rear hatch is hinged at the top. This photo provides a
pretty good illustration of the transitional nature of the introduction
of changes. Of the 6 M3A1s visible, 5 are "no doors," 4 have a stowage
bin on the right rear, but not one is seen with ventilators.
This
still from the NYC parade footage shows another M3A1, Vehicle 9 of the
incongruous "Company M" of the 35th AR. The explanation may be that under
the "Table of Organization and Equipment 17-11" dated March 1942, an
Armored Regiment was authorized a Maintenance Company that was assigned 8
medium tanks, so we suspect that "M" does not represent a letter
company, but rather the Maintenance Company. Of
interest is that this tank can be seen with two ventilators installed
on the hull, but not the turret, even though three ventilators was the
intended standard configuration on the Lee. We've studied the parade
footage and believe that at least 3 M3A1s with the hull ventilators were
present, with each also having a stowage bin visible on the right rear.
One can be seen as "37-H-23" which we will show in the following
caption. Although we have not been able to collect enough data to
determine when these items were introduced at ALCO, we can observe that
the parade took place on 13 June 1942.
The 4th
Armored Division left Pine Camp for Tennessee where it participated in
the Second Army Maneuvers in October and November 1942. Above we have
two 10 October 1942 views of #23, an M3A1 of Company H, 37 Armored
Regiment. To recap a little, item 1 is the pistol port that was
installed only on the right side of the hull after the doors were
eliminated from the casting. The left side of the hull was "clean" as
can be seen in the photo on the right, and, of course, an escape hatch
was added in the belly plate with the elimination of the side doors.
Item 2 is the stowage bin that appears to have begun to trickle into
production shortly before the NYC parade in mid-June. Photos suggest it
was installed on the right side only, and we would guess that it was
intended for the storage of grousers in lieu of the grouser boxes that
were added to the M3 design, since these boxes could not easily fit the
contours of the cast hull. Barely visible is Item 3, the door stop on
M3A1s configured with the upper rear hatches hinged at the bottom. A
ventilator (4) can be seen above the left front pistol port. Period
photos of "ventilated" M3A1s are quite rare. In fact, this is the only
tank in the Maneuvers series that shows a ventilator. We can only
assume that another ventilator was installed on the right top of the
hull, and perhaps another (or not) on the turret. The few Maneuvers
photos of the 35th and 37th ARs' M3A1s consistently show one open hole
in the fixed MG ports, and the tow cable running to the front and
attached to the right towing lug on the differential housing as seen
here.
Here
we have a photo of an M3A1 of the 35th Armored Regiment participating
in the Tennessee Maneuvers on 16 October 1942. The side door has been
welded on to the hull, and a plate has been welded over the pistol port
opening. The "ghosts" of the door hinges can be seen as well. The door
casting has what we believe is a serial number on it, in this case it
appears to be 3 digits beginning with "1." Of course, with the welding
up or elimination of the doors, the grab bar just above was removed,
and, in some photo angles, its presence or absence can provide a clue
about the tank's configuration. The counterweight for the 37mm gun
looks to be the cylindrical type used by Chrysler but with a "collar"
added. These collars are seen in a number of other photos, with their
size and position varying somewhat. We take this example to be
"unvented," since a ventilator would be visible directly above the left
front pistol port if it had been installed. According to the Technical
Manual, "sun glare" headlight covers were provided as on vehicle
material from the start. Muzzle covers for the main guns are not listed
as OVM, and the cover over the 75mm gun appears to have some sort of
pattern on the fabric. Perhaps it was fashioned from a dishrag? Again,
we see the empty tripod fittings and the wedge-shaped antenna bracket
on the left front.
Maneuvers were held on a smaller scale in Louisiana in 1942 and '43. The
Signal Corps photo above is captioned, "The M3 Cast Job tank being
worked on after a break-down at 12:30 P.M. during the Louisiana
maneuvers, 10 miles west of Hornbeck, La. 10/1/42 [Oct. 1, 1942]." The
tactical markings are in the most common format used during WW II, and
indicate that this "no doors" M3A1 served with the 7th Armored
Division's 31st Armored Regiment, and was tank 1 of Company D. In this
view, one can see how the turret splash ends very abruptly at the
midpoint of the hull and has a sort of fin-like appearance (arrow).
Also, note how the casting was built up (1) around the armored fuel
filler covers. The addition of an antenna bracket on the right rear is
something of a mystery. It appears on some ALCO and Baldwin Lees, but
not Chryslers. This example has holes (2) for antenna brackets on both
the left and right but, for whatever reason, the brackets themselves are
not installed. The fire extinguisher pull housing (3) is in what we
would consider the standard configuration. The 37mm counterweight is
another example of the cylindrical type with collar (4). The stowage bin
(5) can be seen overflowing with grousers. There appear to be some
round objects (6), possibly cups, just above the bottom hinged door. We
reckon this M3A1 would have been accepted in June or July 1942, and we
might have expected to see ventilators on it, but if so, the "cups"
would have been resting on one, and perhaps another would be just
visible on the turret. The angled plates (7) are the same as were added
to SN 1962, and were standard fittings on M4, M4A1 and other types of
Shermans. We believe their presence here is indicative of a factory
installation of the Quick Fix mod by ALCO. As mentioned previously, the
installation of the Quick Fix on the M3A1 was listed as "will" start on 4
April 1942 with Serial No. 2114. On the riveted hull it is listed as
will start the day before at SN 2298. These sorts of predictions about
future production were often wishful thinking, but the fact that the two
serial numbers are so far apart is one of the "counting heads" reasons
we believe that the M3A1 SNs were assigned in a block running from 1962
through 2261.
An M3A1 Lee of the 741st Tank Battalion was filmed as one of the
subjects of some "Decontamination of Combat Vehicles" Film Bulletins
issued as training tools by the War Department. The films were shot in
1942 at Edgewood Arsenal, Maryland, which is right next to Aberdeen
Proving Ground. Edgewood was established during WW I as a facility for
the development, testing and storage of chemical warfare agents. For
research purposes, the date of the filming is important, and it was
likely "on or about" 13 July, since at one point a soldier chalks "7/13"
on a "Warning War Gas" sign next to a canvas truck cover that was left
spread on the ground to air out. Men and equipment were apparently
doused with real mustard gas from "enemy" aircraft, and the films
document the protective measures used and the arduous methods of
decontamination. The 741st TB was activated at Fort Meade, Maryland in
March 1942, and it is assumed that some of their vehicles were employed
since they were nearby. The 741st began as a Light Tank Battalion,
equipped with M2A4s, one of which, "Clipper," is featured in the films.
We are informed by 741st TB historian Bill Warnock that the unit was
converting to a Medium Tank Battalion, and "received its first four M3A1
medium tanks on June 3, 1942" with an additional 22 M3A1s
(specifically) delivered by 6 July. This was the final total of Mediums
received at Ft. Meade, and they were reported to have been left behind
when the unit deployed to the Desert Training Center at the end of July.
In any case, the M3A1 was shot from all angles as it was
decontaminated, permitting us to record that it was B-1, and carried the
name "Big Bertha." The Registration Number is partly visible in a few
frames as USA 30626X, indicating June 1942 acceptance according to our
interpolation. It is another example that shows 2 ventilators installed
on the hull only. We assume that eventually ALCO would have installed
ventilators on the turrets of its Lees, but at present, we cannot
document it photographically. For what it is worth, ALCO M3 SN 2322,
which by our reckoning, would have been built in May 1942, was the
subject of an Acceptance Test at APG which ran from the 6th to the 19th
of June 1942. There is a note that "a mushroom type ventilator was
installed in the turret over the 37mm gun," but no photos were included
in the documents we examined. The door stop (arrow) can be seen to be
angled a bit so that the bottom hinged hatch would be in full contact
with it when in the open position. The "1 GP" inside the star may
indicate that the 741st was part of the 1st Tank Group, which included
the 751st, 752nd and 755th Tank Battalions (Medium), all of which were
shipping out for the U.K. at the time this film was shot.
This
photo is dated 14 July 1942 and was taken at the General Steel Plant in
Granite City, Illinois. At that time, the company appeared to be
casting M3A1 and Ram hulls despite the almost desperate calls for
greater production of Shermans, including the cast hull M4A1. We
believe that "533391" was the part number of the no doors cast hull
with the "-1" indicating the first revision, since the hull is reported
with the very low serial number "8." That is to say, there would have
been some no doors M3A1 hulls cast earlier than July. We would assume
that General Steel was finishing up M3A1 hull production at this time,
and that this particular hull might have gone into the making of one of
the last 31 M3A1s produced during ALCO's final month of Lee production
in August. Note how the cast in bullet splash only protects the front
half of the turret. The casting can be seen with a "lip" surrounding
the opening of the rear hull hatch. We are somewhat surprised to see
that the lip is interrupted at the top (arrow) where the center parts
of the hinges (asterisks) were welded to the hull as shown in the
inset. This suggests that the casting was not revised to accommodate
the bottom hinged hatch. In the absence of any surviving examples, we
can only speculate that the original D38464 hatch casting was simply
reversed, and the center hinge parts were welded on at the bottom with
some of the lip ground away if necessary.
The Variants: M3A2 Lee
In the Summer of 1941, just as the first M3 Mediums were beginning to
roll off the assembly lines, Rock Island Arsenal completed a prototype
in which both the upper and lower hulls were assembled by welding. The
photo shows the vehicle at APG on 21 July 1941. Note the prominent weld
seam (arrow) where the 75mm sponson casting is joined to the armor
plate. Also of interest is that the side door hinges appear to have been
screwed on as usual, but then welded on as well. Additionally, the
hinge screws themselves appear to have been seal welded. Other photos
show that this was also the case with the door on the left side and the
engine access doors in the lower rear hull plate. The information panel
lists the tank as "M3-2373 (R.I.A. Welded hull)." We take 2373 to be the
serial number of the unit. Additionally, "USA W-304193" can be seen
painted on the hull. Readers will recall that the RIA M3 pilot,
photographed at APG in March 1941, was listed as Serial Number 1/USA
304191 and the M3A1 pilot, photographed in June, was listed as SN
2372/USA 304192. As with the cast hull, the superiority of welded as
opposed to riveted construction was obvious. Fabrication time was
reduced by the elimination of "a large portion of machine work" [rivet
holes], "weight was reduced for a given ballistic resistance" and
"splash [from rivets] and other dangerous features were eliminated,
although cracks occurred in welds near points of ammunition impact."
Consequently, "it was recommended that the welded construction be
employed, wherever possible, on Medium Tanks M3 and other armored
vehicles."
At the same time, another welded hull was produced by the
Carnegie-Illinois Steel Corporation. Reading between the lines, we infer
that it would have included both the upper and lower hulls, but not
much else. Seven photographs were reported to have been taken of the
hull after ballistic tests in August 1941, but the only one we have come
across, shown above, is not very informative. One thing that strikes us
is that there are still a surprising number of rivets visible on the
inside. A digest of the Report has it that the RIA pilot was a working
tank, "subjected to 556 miles of endurance operation." After that, the
pilot and the Carnegie hull "were subjected to three and four rounds of
75-mm AP [armor piercing] ammunition fire, respectively." It was
obviously not intended to test these units to destruction. The damage to
the "front driver's window and protectoscope glass" appears slight in
the photo. Note the dataplate affixed to the wall of the hull. We
examined the photo with a magnifying glass, and the vehicle is listed as
"Tank Medium, M3" and the Manufacturer as "Rock Island Arsenal." We
could not read what was stamped in the "Serial No." box, but a 27 August
1941 APG Report of the firing lists it as "No. 2374." We have some
doubts that SNs 2372, 2373 and 2374 were officially assigned to these
RIA pilot tanks, since these SNs are listed as having been aboard the
Liberty Ship S.S. Virginia Dare, which was part of Convoy PQ 18. The
convoy was delayed for 9 weeks after the disaster of Convoy PQ 17. PQ 18
had a much heavier naval escort, but even so, the convoy lost 13
merchant ships with 28 arriving safely at Archangelsk on 21 September
1942. Of the 448 tanks shipped, 126 were reported to have been lost. The
Virginia Dare "was credited with shooting down seven German aircraft
and received the Gallant Ship Citation" during this run. It seems
unlikely that the US would have shipped used pilot tanks to the Soviets,
not to mention that earlier, we showed a photo of the cast hull pilot
2372 at APG in August 1943. Rather, we believe that the tanks listed on
the Virginia Dare were Chrysler M3s produced in January 1942 as shown in
our production chart. Whatever the case, in September 1941, APG was
directed to ship both the RIA welded hull pilot and the Carnegie hull to
Baldwin Locomotive. Baldwin was directed "to make a complete tank of
the Carnegie welded hull and repair penetrations and cracks in the Rock
Island welded tank."
Of course, the replacement of riveting with welding in the construction
of future armored vehicles was a foregone conclusion. On 11 September
1941, the Ordnance Technical Committee recommended that "welding of
approved types be authorized as an alternative method of fabricating
tank hulls and turrets." Additionally, “That the Medium Tank, M3, when
equipped with welded hull, be designated: Medium Tank, M3A2.” To put
this into context, on that same day, which was about a week after the T6
[cast hull Sherman] pilot had been "presented" at APG, the new design
was standardized as the "Medium Tank, M4" while the M3 was reclassified
as "substitute standard." Furthermore, an RIA teletype dated 18 October
1941 stated that the T6 welded hull pilot was "now under construction
here." Finally, on 27 October 1941, Baldwin Locomotive was awarded
another contract for the production of 400 Medium Tanks, M4. In the
meantime, Baldwin was directed to change its M3 production "from a
riveted hull to a welded hull." An internal history has it that on 6
October 1941, "Production of M3A2 begun, gas engine, welded hull." "The
first completed tank with welded hull" is specifically listed as Serial
Number 1040 in Ordnance documents. It was shipped to APG in November,
and "the omission of the connecting angles on the inside of the tank"
was noted. We suspect that the "connecting angles" were the riveted
pieces seen inside the Carnegie hull shown in the previous caption.
Baldwin was contracted to produce new tanks and factory photos (inset)
show that the Baldwin M3A2 was built from scratch, and not based on one
of the two pilots. Baldwin asked APG to "inspect this tank, particularly
as to said deviations and notify this office as to whether these are
acceptable or what corrections are desired." The above shows Serial
Number 1040 as photographed at APG on 1 January 1942. It should be noted
here that only SN 1040 and the RIA pilot, USA 304193, are seen with
entirely all welded hulls. SN 1040 was officially accepted in January,
but we suspect that APG found issues involving the welding of the 75mm
gun sponson casting to the armor plates, since photos show that some
riveting was used in that area on subsequent welded hull M3 Mediums.
In
this rear view of SN 1040, note the extremely smooth appearance of the
armor with the weld seams barely evident. Plate 1 kind of breaks up the
smoothness, since it had to be removable for mounting the 75mm gun and
was secured with round head slotted machine screws. It can be seen that
the idler wheel assemblies (2) were "still" secured with rivets, as was
the small twin bow machine gun casting in the front. There is some
thought that the engine access hinges (3) were welded, not screwed on,
but it is not entirely clear in the photos. We can observe that some
surviving Baldwin M4s used these exact same hinges, and they are welded
on in some cases. Perhaps Baldwin was authorized to "repurpose" some M3
access doors and hinges leftover from when they were directed to change
production from radial to diesel M3s? While the RIA welded hull pilot
was built with sheet metal mud flaps, SN 1040 was made with the "usual"
rubber ones (4). The RIA pilot did not include an antenna bracket on the
left rear, while 1040 can be seen with the early fabricated type (5),
and we would mention that work is reported to have begun on this unit on
6 October 1941. The tracks show a bit of wear, and a digest of the APG
report has it that the tank was operated a total of 425 miles on and off
road. As a matter of minutia, this view provides us with a good view of
the slightly "softer" edge (arrow) typical of General Steel D-38530
turret castings when compared with the Continental and American Steel
turret castings primarily used by Chrysler.
We would assume that SN 1040 served as a test vehicle at APG and
elsewhere. We did not come across a folder on the tank in the accession
files in the library at the old Ordnance Museum at APG, so it appears
not to have been preserved for historic purposes like the ALCO M3A1. It
was filmed at Ft. Belvoir, Viginia in March 1943, where it was shown
driving over logs and attempting to break through log barriers of
various sizes. One caption reads in part, "Army Engineers construct
these obstacles as tests for both tanks and drivers, so valuable
experience is gained for actual battle." In this view, it can be seen
that the guns and headlights were removed, and that the front fender had
suffered some damage. Note
that, unlike the RIA pilot, USA 304193, the side door hinges (arrow)
are affixed in the standard way with slotted flat head bolts. The
Registration Number is visible as 305110. This tank plays havoc with our
production chart estimate, since going by that, SN 1040/USA 305110
would have been accepted as an M3 Lee in October 1941. A Baldwin
production document has it that the first M3A2 was delivered in November
1941, but this is at variance with the Ordnance Dept. documents which
state that the first 4 M3A2s were officially accepted in January 1942.
We tend to give the Ord. docs preference in a situation like this. In
any case, sometime after the obstacle course trial, it would appear that
the Engineer Corps at Ft. Belvoir repaired and rearmed SN 1040 and
painted it in a very elaborate, possibly British influenced, 4 color
disruptive camouflage scheme (left inset). We looked through the April
1944 "FM 5-20B, Corps of Engineers Field Manual, Camouflage of Vehicles", thinking SN 1040 might have served as a model, but the
camouflage paint scheme pattern "For Temperate Zones and Jungle," is
shown in the right inset. Based on period photos, it is obvious that US
tanks in the field were mostly just left in olive drab.
Earlier we reported that Baldwin was directed "to make a complete tank
of the Carnegie welded hull and repair penetrations and cracks in the
Rock Island welded tank." This is something of a mystery to us. If this
was done, it is assumed that these tanks would have been returned to APG
or sent elsewhere to serve as test vehicles, but we know of no later
photos. Furthermore, the Baldwin history does not mention doing such
work. We might speculate that the tank shown above was based on the
Carnegie hull, but there is no evidence of any shot damage repair in
this view. In any case, we assume that if an AFV was photographed at
APG, there would have been an accompanying report, which in this
instance, may or may not have solved the mystery. However, we didn't
come across any written information regarding SN 1082, not even a digest
of a report, so the question remains for now. This single known photo
shows a right-side view of the vehicle at APG on 30 January 1942. This
Lee can be identified as having a radial engine by the gap (arrow) and
the pepperpot exhaust that is just visible. Since this unit has a
Baldwin Serial Number, our preferred theory is that this was the second
of the two M3A2 Lees that Baldwin produced new from scratch. We would
also theorize that there were issues with welding the large 75mm gun
sponson casting to the armor plates, and that some connecting angles and
rivets were reintroduced in order to secure it. However, significantly
more horizontal rivets are seen here than on later examples of welded
hull M3 series Mediums. The "excess" rivets are to the left of the red
vertical lines. Of interest here is that, like the RIA Pilot, USA
304193, the door hinges (arrow) can be seen to have been welded on,
although, unlike the pilot, the hinges appear to be solid with no screw
holes. Ballistic tests had shown that the doors were thrown open or torn
off the hull under impact, and experiments such as welding the hinges
and installing a more robust interior latch bar were tried, but,
ultimately, it was recommended that the side doors be eliminated from
the Lee design. Meanwhile, Baldwin was directed to give precedence to
their Grant contract, and the 10 remaining M3A2s were produced as Grants
- 2 in January; 5 in February and 3 in March 1942. We have photos of
T-23622 (Jan. production) and T-23708 (Feb.) on our
Grant page. These
M3A2 based Grants appear to have what we might call the "standard rivet
pattern" on the right side, but it is not entirely certain due to the
angle and clarity of the images. Photo courtesy of David Doyle.
The Variants: M3A3 and M3A5 Lee
The expansion of the Medium Tank Program was affected by the limited
supply of Radial engines that could be produced. As we have reported,
the Ordnance Department was casting about for alternate tank engines. In
August 1941, General Motors was contracted to perform an experimental
installation using M3 Lee SN 28, which was pulled off the line at
Chrysler and shipped a short distance to GM’s Detroit Diesel Plant. The
installation combined two "off the shelf" GM 6-71 diesel truck engines
that were “coupled together by means of a transfer case delivering the
doubled power to a single driver shaft.” Together the engines developed
about 400 horsepower. The design was deemed acceptable, and on 21
November 1941, the twin diesel engine was designated the "GM Model
6046," and authorized for production as an alternate power plant for the
Medium Tank. The day before this, and hard on the heels of the order to
change from riveted to welded hulls, Baldwin reported that they were
directed "that all M3s are to be diesel driven, starting with the 87th
U.S. Tank and the 221st British." The original intent appears to have
been for Baldwin to change to production of welded hull, diesel powered
M3 Mediums which were to be designated "M3A3." However, the complete
changeover to welded hulls was not feasible, and the nomenclature was
amended in January 1942, "because approximately half of the diesel tanks
at Baldwin Locomotive Works will [still] need to be made with riveted
hulls." Henceforth, "M3A3" was reserved for the welded hull, diesel
engine models, while "M3A5" was assigned to the riveted hull diesels.
Above shows a GM Model 6046 twin diesel on display at the Tank Museum at
Bovington. Note the transfer case indicated by the arrow. Photos
courtesy of Massimo Foti.
The introduction of the twin diesel into the M3 Medium design was NOT a
case of a simple engine swap, and Baldwin was given very little lead
time to procure the necessary components for the changeover. The size of
the GM Model 6046 necessitated a number of alterations to the layouts
of both the engine and fighting compartments. For instance, the addition
of the transfer case made the power pack longer than the engine
compartment. Consequently, the firewall was altered to permit the
transfer case to protrude into the fighting compartment. The width of
the side-by-side engines forced the elimination of the two fuel tanks
mounted vertically against the firewall in the original design of the
M3. Instead, the horizontal fuel tanks were supplemented by a pair of
reserve tanks mounted on the engine compartment floor just below the
horizontal tanks. The fuel capacity of the diesel models was 148 gallons
compared to the 172 gallons of radial engine versions. Externally, the
side armor plates (1) and the upper rear hull plate (2) were extended
down and out from the tank in order to accommodate and protect the rear
mounted radiators. The engine access doors in the lower rear plate of
the original M3 design were eliminated because the diesel configuration
mounted a pair of mufflers (inset) across the plate. Exhaust gases were
directed through a rigidly mounted sheet metal exhaust deflector (3).
The engine was serviced through a rather large pair of doors on the
engine deck. This configuration was carried over to the Sherman and
designated as the "M4A2" in December 1941. The photo above is dated 5
November 1941 and shows the pilot installation of the twin diesel power
pack in SN 28/USA 301026, which was originally accepted as an M3 Lee at
the Detroit Tank Arsenal in August 1941. Although this photo has an APG information panel, we believe it was
actually taken at the General Motors Proving Ground in Michigan, where
the vehicle was listed as GMPG Project No. 8038. The tank was reported
to have been driven the 547 miles from there to Aberdeen, arriving on 24
November.
Shortly after SN 28/USA 301026 arrived at APG, testing found
inadequacies with the original AC "hat type" oil bath air cleaners which
were mounted 3 to a side on the twin diesels (inset). The AC Company
presented experimental air cleaners "designed for installation in pairs
on the rear of the tank," a configuration similar to that under
development for use on radial engine medium tanks. As can be seen above,
the experimental cleaners required that the rear of the tank be
extended out 12 inches. The external air cleaners failed in the diesel
application, and ultimately heavier duty interior air cleaners were used
in production. Note that SN 28 is described in this APG info panel as
"Medium Tank M3A5."
SN 398/USA 304468 was a Chrysler Lee originally built in November 1941.
In late 1941, under the designation General Motors Proving Ground
Project No. 8000, the tank "less Wright R975-EC2 engine" was shipped to
the GM Detroit Diesel Plant "for the installation of two General Motors
Diesel 6-71 Engines and two 5-speed Hydra-matic transmissions." This
configuration, with one transmission for each engine, appears to have
been similar to that used on the M5 Light Tank designed a few
months earlier by Cadillac. Tests at APG gave this automatic
transmission system what amounted to rave reviews citing better
acceleration, greater crew comfort and more stability than the standard
manual transmission. In the photo above, the GMPG panel at the lower
left is dated 12 Jan. 1942 and labels the vehicle "Medium Tank M3A3
Diesel Hydramatic." The APG info panel across the bottom is dated 6
March 1942, and the tank is described as "M3A5E1" reflecting the change
in nomenclature, with the "E1" added to indicate that it was the first
experimental version of the M3A5. APG recommended that a single,
heavy-duty Hydra-matic transmission be designed in place of the duals.
SN 398 was to be used again, relabeled as "M3A5E2," GMPG Project No.
8017. In the end, the reliable 5 speed manual transmission originally
designed for the M3/M4 series by the Spicer Manufacturing Company was
not replaced by an automatic transmission due to the immediate need for
these tanks. However, the T20 series of medium tanks developed to
replace the Sherman experimented with various types of automatic
transmissions, including the "Torqmatic" adopted for use in the T26E3
(M26).
The
drawings above compare the engine deck configuration of M3 and M3A2
radial Mediums (on left) to that of the diesel M3A3 and M3A5 Mediums (on
right). All of the armored fuel filler caps on the radial's deck
protected filler nozzles for gasoline. Points 1 filled the fuel tanks
mounted horizontally along the sponsons in the rear. Points 2 were for
the tanks mounted vertically against the firewall on each side of the
engine compartment. Point 3 supplied fuel to the auxiliary generator
mounted in the left rear of the fighting compartment. As mentioned
previously, the vertical fuel tanks were eliminated from the diesel's
engine compartment, and filler points 4 were for diesel fuel stored in
the horizontal tanks. These were supplemented by a pair of reserve fuel
tanks mounted on the engine compartment floor just below the horizontal
tanks. Points 5 provided for lubricating oil, and points 6 for water to
the radiators. Point 7 was for the auxiliary generator (Little Joe), the
same gasoline powered model as used on the radials. The diesel's engine
access doors (8) can be compared with the radial's simple air intake
opening (9). Both were "protected" from shrapnel and the like only by
screens, a serious deficiency that was addressed in the design of the
corresponding models of Shermans.
Evidence seen on a few surviving diesel M3 Lees and Grants suggests
that Baldwin installed some pressed metal labels on to each of the
armored fuel filler covers to help the crews avoid contaminating the
tanks with the wrong solutions. Label 1 reads "LUBE OIL", label 2 reads
"WATER" and label 3 reads "FUEL OIL." These three fillers are mirrored
on the right side of the engine deck. On the left side, there is an
additional filler point, label 4 for "GASOLINE" for the auxiliary
generator (inset). A few examples show a breather tube (5) emerging
from a notch on the fuel filler covers. This appears to have been
released for all versions of the M3 plus the M7 Priest as Field Service
Modification Work Order G104-W26 to provide for "More positive gasoline
tank vent." The idea was to prevent fires by providing "A vent hole of
sufficient size to be drilled in the armor gasoline tank cover lids, to
permit gas vapors to escape to the atmosphere." This is seldom seen in
photos or on surviving M3s. Our photo shows it on a former APG M3A5 Lee
which, of course, used diesel fuel. Note the "short and
straight" hinge pin about to fall out of the
auxiliary generator's fuel filler cover. A chain was attached
to "eyes" (6) to keep the pins from being lost, but it is missing
in this case. We would observe that on the Sherman, the labels were
affixed to the deck near each filler cover, most likely because the
labeled covers ended up in the wrong place on
occasion. Additionally, on the M4A2 [diesel] Sherman, the fuel
type label was elaborated to "DIESEL FUEL OIL." Photos courtesy of
Tyler Reid.
In March 1942, the Armored Force Board at Ft. Knox reported a
number of fuel line deficiencies upon receipt of what they labeled
"Tank, Medium, M3A3, No. W-305153, Ordnance No. 1083." In a 24 August
1942 Report, the vehicle is described as "Medium Tank, M3A5, W305153,
manufactured by the Baldwin Locomotive Works...and powered with General
Motors Twin 6-cylinder, Model 6046, Series 71 [engine]." The tank had
been operated a total of 5225 miles on roads and 600 miles cross country
"to develop any failures and to note deficiencies of the engines and
their accessories." We believe that SN 1083 was the pilot or first
diesel M3 Medium built by Baldwin, and despite the mixed M3A3-M3A5
nomenclature in the two reports, was a riveted hull M3A5 Lee. The report
seems a bit "after the fact," as by the end of August, production of
the M3 Medium had ended everywhere except at Baldwin, and Sherman
production, including the diesel model M4A2 was in full swing. Indeed,
over 700 M4A2s had been produced by then, and 90 were on their way to
the Middle East as part of the "Emergency shipment" to the British 8th
Army. We mention all of this to give readers a sense of what else was
taking place at the time, but primarily to document, at least textually,
that Serial Number 1083/USA 305153 was a diesel, either M3A3 or M3A5.
SN 1083 had been used to test Firestone Experimental [grooved] Bogie
Tires, but the trials had been deemed unsuccessful and discontinued at
2440 miles. Unfortunately, the only photos with the report we examined
show nothing but some of the failed bogie tires, but it can be seen
above that the information panel identifies the tank as "M3A5 Medium
Tank No. 305153." The report mentions that, for the test, "rubber,
pl[ain] bl[oc]k type" tracks had been used for 1699 miles and "Steel
with rubber face on bogie side" tracks had been used for 799 miles." The
inset shows a riveted hull Lee at Ft. Knox with an "Armored Board Test"
placard on the front. This is identified as an M3A5 in a number of
books, although there is no way to tell from the angle of the photo. The
steel tracks might be a clue that it was USA 305153.
Despite the fact that the rear configuration of the Lee shown above is
not visible, we are able to document it because APG did us researchers a
favor and painted "M3A3 1084" on the vehicle. We have collected enough
data over the years to be able to say with near certainty that the "key"
number for Lees built by Baldwin is 304070. That is, when added to the
tank's serial number, it provides the Registration Number. So, 1084 +
304070 = USA 305154. One bit of the data we have collected is "No.
W-305153, Ordnance No. 1083" listed in a report cited in the previous
caption. We interpolate that SN 1084 was Baldwin's first or pilot model
of the welded hull diesel. It is shown above at APG in late 1942 when it
was involved in tests of "Track, T54E1, Burgess-Norton Steel for Medium
Tank" (1). The rivets shown on the right side are in what we consider
the "standard pattern" for welded hull M3 Mediums. Some rivets were also
used on the inside section of the sponson casting (arrow), with others
running up the front plate. They cannot be seen here, but a few more
rivets joined the sponson to the top plates. The side door hinges look a
bit oversize leading us to think that they may have been welded on. In
the first half of 1942, production at Baldwin was dedicated almost
entirely to diesel powered Grants until the British Contract was
completed in July. Consequently, very few M3A3 and M3A5 Lees would have
been built with working side doors, perhaps just the 11 produced up to
April 1942. Unfortunately, we have not been able to locate any photos of
other examples. However, within that group, we have textual listings
from a 27 October 1942 Products Correction Report in which it was
reported that M3A5s SNs 1087 and 1088, and M3A3 SN 1089 along with M4A2
SN 2315, had been in service with Company B of the Demonstration
Regiment at Ft. Knox. The diesel engines had given problems and despite
the assistance of an on-sight GM technician, it was requested that "The
manufacturer replace or repair these engines without expense to the
Government." We wouldn't be surprised if one or two of the Lees shown
earlier in our favorite Alfred T. Palmer color photo were diesel models,
but there is no way to tell from a front shot. Another diesel, SN 1090
is listed as an M3A3 and as General Motors Proving Ground Project No.
8007. GMPG projects generally included a report with photos. If any
readers have seen this report or photos of GMPG 8007, please contact us.
Officially, Baldwin is reported to have produced 84 M3 and 2 M3A2 Lees,
and this would be the mathematical basis for the directive "all M3s are
to be diesel driven, starting with the 87th U.S. Tank." Assuming a
strict serial order, SNs 1002 through 1085 would have been M3s; SNs 1086
and 1087 would have been M3A2s; and from SN 1088 through 1536 would
account for the 239 M3A3 and 210 M3A5 diesel Lees produced. Of course,
this is not how it played out in reality, since we are pretty sure that
SN 1040 was Baldwin's first M3A2 Lee and SN 1082 was the second,
followed by SN 1083 as the first M3A5 Lee and SN 1084 as the first M3A3
Lee. For the time being, our Baldwin production chart at the top of the
page, simply presents the serial and registration numbers in numerical
order without attempting to rearrange things to account for the
discrepancies with some of the known outliers. Caveat emptor. In any
case, we strongly suspect that the photo above is of SN 1084. We assume
that there would have been an information panel on this, and another
right-side photo of the tank taken from ground level, but if so, we have
not been able to locate those copies. This tank can be identified as an
M3A3 by the engine deck configuration, including the shovel fitting
running crosswise on the rear. As mentioned, SN 1084 would have been USA
305154, but a blow up of the Registration Number (left inset) is
somewhat inconvenient to our theory as it seems to show the last digit
as something other than a "4." We made an attempt to examine the RN with
"forensic photo software," but the results were inconclusive, certainly
not the magical clarity obtained by crime labs on TV shows. The thing
is, a Baldwin "Production of Medium Tanks" document has it that they
didn't produce any more M3A3 Lees until July 1942. Consequently, we
believe that the photo above must be of SN 1084, since it is our theory
that that was the only M3A3 based Lee that had working doors. As with
the photo of 1084 from the previous caption, this example can be seen
with the side door hinges welded on to the armor plate (right inset). As
a matter of minutia, we would observe that the examination of the few
period photos and surviving M3A3 based Grants does not show any with
welded door hinges.
Speaking of outliers, here we have SN 1099, confirmed by personal
examination of both the dataplate and the SN stamped on the towing lugs.
By "outlier," we mean that going by our production chart, SN 1099 would
have been the only Lee built by Baldwin in May 1942, and should have
been a riveted hull M3A5. This tank was on display at the Patton Museum
at Ft. Knox, and is now in storage at Ft. Benning. A plaque inside the
vehicle notes that it served with the Brazilian Army and was returned to
the US in 1976. Of the Central and South American countries, Brazil was
by far the largest recipient of Lend Lease armor during WW II. Along
with 427 M3 Series Light Tanks, Brazil is reported to have received 104
M3 Lee series and 53 Sherman series Mediums. The first Lee allocation to
Brazil was for 5 "M3A3, Diesel" (specifically) in July 1942. We suspect
that SN 1099 was produced in July, and might have been one of the first
5 as it is the only example we have come across where the pistol port
(1) was retained in the left side door even though it was welded in and
had the view port blanked off. We would interpolate that this unit was
built with ventilators (2), grousers boxes (3) and rear stowage boxes,
although the rear bins appear to be reconstructions possibly because the
originals had rusted out. The differential housing has "1099" (inset)
stamped on the towing lugs leading us to conclude that it is the
original. The casting marks on the differential are typical of Chrysler M3 Power
Trains. Baldwin's primary supplier was Mack, but it appears that they
received some excess P.T.s and turrets from Chrysler as M3 production
ended there in August 1942. We would judge that this tank would have
been built with T41 rubber block tracks and welded spoke road wheels,
and that the rubber chevron tracks (4) and pressed metal wheels (5) were
retrofitted. Also, that the front bogie is "as built" while the middle
and rear were retrofitted with the G104-W12, "Install Bogie Gudgeon
Spacer," modification that raised the return rollers by about an inch
(6).
In
this view, we see the nearly as built engine deck configuration. The
brackets (1) around the engine air intake screens appear to be
retrofits, probably to hold some sort of cover. Note that like ALCO,
some Baldwins Lees are seen with two cast antenna "pots" installed (2).
The angle bracket (3) is welded on to the removeable plate (4). The top
part of the bracket is clean all the way across, whereas the RIA welded
hull pilot, SN 1040 and 1082 appear to have had a slotted bolt on each
end. The addition of the ventilator behind the top hatch made it so that
the hatch would not lie flat when opened. Consequently, the little
catch (5) was raised about 2 inches and angled to secure the hatch when
in the open position. Note the POL labels affixed to the armored fuel
filler covers.
Here we see how the 75mm sponson casting was attached with rivets on the
top (1) and front (2). Note the use of pyramidal rivets in this case.
Other Baldwins are seen with round heads. Some nuts and bolts (3)
secured the sponson casting to the reinforcing strut in the rear. The
reinforcing struts (4) were not riveted on the M3A3, but tack welded on
as seen here (circled). On most Lees and Grants, the hinges of the
driver's visor are noted to be attached with round head slotted bolts,
such as used on the side doors. This example and a few other Baldwins
are seen to have used a non-removable installation where the hinges are
"flush riveted" (5) on to the armor plate. It is thought that a little
sheet metal "sun visor" (6) was added to the 75mm gunner's periscope on
some or all of the Baldwin Lees produced starting around July 1942.
Lee turrets (Part Number D-38530)
were reported to have been cast for Chrysler by American Steel
Foundries-Granite City and Continental-Hubbard. For ALCO and Baldwin,
General Steel is said to have supplied their D-38530 turrets. The
turret of SN 1099 can be seen with an ASF-G caster's logo (top photo).
It is installed with a ventilator, and if we assume that it is original
to SN 1099, it might suggest that Baldwin was supplied with excess
turrets from Chrysler as Lee production ended there. In addition, we
are confronted with the mysteries and vagaries of supply chronology if
we assume that "127" is the turret serial number. That strikes as low
for a Lee built in mid 1942. In a similar vein, turret serial number
293 (middle photo) strikes us high for Chrysler's first Lee, SN 2 on
display in Newark. However, note that unlike turret 127, turret 293 was
not drilled to hold the "upper cylinder bracket" that secured the
piston of the 37mm gun's gyro-stabilizer assembly. The slotted bolts
(circled) that held the bracket can be seen in a triangular
configuration in the upper photo. The bolts appear to have been
seal welded on, a laborious process that is also seen around interior
rivets and was introduced to prevent them from flying loose when
the tank was hit. The bottom photo shows an ASF-G turret with
ventilator on a late production Chrysler Lee. We believe the "2" above
the Part Number denotes a casting revision, as does the part serial
number with an "A" prefix. On this example but not the other two, the
ASF-G logo has been incorporated into the casting below the pistol port
(inset). Also of note is that the slotted bolts are not seal welded.
The top view of the RIA pilot that we presented earlier shows two
"bumps" on the top of the turret and recall that the tank was reported
to have been installed with a gyrostabilizer for the presentation given
on 24 April 1941. The gyrostabilizer was intended to be standard
equipment on the M3 Medium for both the 37mm and 75mm, although its
introduction was delayed until January 1942 for industrial reasons.
The British view of the gyrostabilizer, at least as published in
AFV Technical Report No. 11 (December 1942) was not positive. Regarding
the recent fighting in North Africa, in both the M3 and M4 series
Mediums, the Brits were not "able to establish by trial that they
(gyrostabilizers) confer any advantage at all." Furthermore, it was
reported that "formations...demanded that this fitment should be
removed...the space and weight which it takes up can usefully be
replaced by...extra items of stowage...It has the additional demerit
that when it leaks it empties the oil system and incapacitates the power
traverse as well." This despite the fact that the US sent technicians
to all theaters to demonstrate the benefits and instruct on the "care
and feeding" of the gyrostabilizer. In any case, while all Shermans
except the 105mm models were equipped with gyrostabilizers, most of the
Grants and Lees shipped to the Middle East were not, and the British
decided that if modification kits became available, they would not
"require" them for retrofit to their pool of existing M3 Mediums.
Pierre-Olivier was able to get an interior photo of SN 1099 from an
interesting angle inside the turret, and here we see the
gyrostabilizer's piston (1) secured to the "ceiling" by 3 lock nuts. The
drawing on the right from the Technical Manual shows the various
components of the "37 mm gun stabilizer system." We believe that the
diesel Lees produced by Baldwin from July to the end of production in
December 1942 included gyrostabilizers for both the 37 mm and 75 mm
guns. At present, we find no evidence that any Baldwin Lees (or Grants
for that matter) were built with the longer M3 75mm guns.
Based on a reader's question, we thought we might take a short detour to
discuss the counterweight used for the 37mm gun. The vast majority of
those seen in period photos are of the type that is installed on M3 Lee
SN 3711 on display at the Australian Army Tank Museum at Puckapunyal.
Despite a lack of documentation, we would have to conclude that this
simple fixture was the "factory" or "standard" counterweight. At the
least we can say that this counterweight was included in a side view
drawing of the M24 Combination Gun Mount where it is listed as Part
Number B197508 (inset). We hope to have the opportunity to measure and
perhaps weigh one of these in the future. In the meantime, Kurt Laughlin
has interpreted the drawings to indicate that the counterweight was
composed of 2 inch outside diameter mechanical tubing which was capped
off and filled with molten lead. "A 5/8 [inch] diameter hole (circled)
was cross drilled, probably to allow installation into the gun shield.
Some number of spacers were attached with a screw and washer, and the
counterweight was complete."
A few other types have been observed. We can't really do anything more
than note the presence of these "variants" in period photos. As yet, no
surviving Lees or Grants have been seen with these types. Earlier, we
pointed out that the M3 pilot was installed with what appeared to be a
capped plumbing pipe. Above left, we have a similar homemade looking
example on one of the 13th Armored Regiment Lees photographed at Souk el
Arba in November 1942. The fittings on the inside edge appear have
served as reducing adaptors. Period photos show one or two ALCO M3A1
Lees with this "plumber's" type. Most of the others in the Tunisia and
Perham Downs series of photos are observed with what we consider the
"standard" counterweight. Another example in the Tunisia series (upper
right) shows a simple pipe with a cap, also noted on a few ALCO M3A1s.
Other ALCOs (lower left) have what appears to be the standard
counterweight with a collar of various widths positioned in various
locations along the counterweight's shaft. The lower right shows another
iteration of the counterweight on a Commonwealth Lee in Burma. The
thinness of the cap may indicate that this was constructed using copper
pipe and fittings. The turret has the look of a General Steel casting,
and the rivets may be "round heads" leading us to speculate that this
"no doors" Lee might have been an ALCO M3 from their final months of
production, July or August 1942. An early opinion about the
gyrostabilizer from a US perspective appears in a report dated 21
December 1942 in which Major Henry Gardiner and his fellow officers of
the 2nd Battalion/13th Armored Regiment wrote, "This equipment is
entirely unable to stand up under campaign conditions and not one tank
went into battle with a stabiliser in operation. It is recommended that
their installation be discontinued until a satisfactory model is
developed."
Using
early Lees and Grants as reference, we had initially thought that if a
turret was not equipped with a gyrostabilizer, the holes would not have
been drilled. However, the image above is a blow up of a Signal Corps
photo taken at the Desert Training Center and dated 22 October 1942.
These Lees are not equipped with counterweights below their 37mm guns
but have plugs (1) instead. We take this to indicate that they do not
have gyrostabilizers. Even so, the Lee in the foreground can be seen to
have the slotted bolts (circled) for the piston. So, we might assume
that at some point, the holes were drilled, and the nuts and bolts were
installed in anticipation. The caster's logo (2) appears to be the "G
inside a hexagon" of American Steel Foundries-Granite City, which we
take to have been the turret casting produced in the largest numbers.
The "3" inside the stars (3) would indicate that these were tanks of the
3rd Armored Division which was assigned to the DTC from July through
November 1942. The entire photo shows at least 100 Lees, including an
M3A1, and 3 M4A1 Shermans. The Lee turret was not equipped with lifting
rings, but aside from the pilot, the castings incorporated three
"nubbins" (4) into which could be screwed heavy duty "eye bolts" (inset)
for lifting.
Continuing our examination of Lee turrets, here we have a view of the
Continental-Hubbard (H inside a C) turret of Chrysler M3 Lee SN 3711 on
display at the Australian Army Tank Museum at Puckapunyal. The cast in
number, 7434 (1), far exceeds the total number of Lees that were
produced, so seems too high to be the turret serial number. More likely,
it is the Heat Treatment number of the piece. This leaves us to
conclude that the stamped in number, 1604 (2), would be the turret
serial number. The caster's logo (3) can also be seen cast in below the
pistol port on this example, but it would appear that that was not the
case with every C-H turret. We hope to be able to collect more data, but
our best guess for now is that the caster's logo below the pistol port
was introduced on the turret moldings of both ASF-G and C-H sometime in
1942.
Surviving
Lee turrets are pretty rare, and it is not often possible to get access
to permit a study of the casting marks. General Steel Grant turrets
have been noted with the turret serial number on the top front and the
GS logo and turret part number placed inside on the "ceiling." We
suspect it was the same with their Lee turrets but need to collect more
information. Pierre-Olivier was able to take the photo above showing the
top of the turret of M31B2, Serial Number 81, at Ft. Benning, Georgia.
Note the "559" (1) which we think is the turret serial number. It can be
seen that this turret was not installed with a ventilator nor was it
drilled out to hold the "upper cylinder bracket" that secured the piston
of the 37mm gun's gyro-stabilizer assembly. There is no evidence that
the "Spot and Signal Lamp" (2) was factory installed on any production
Lees. It entered the Sherman production pipeline in late 1942, and it is
thought that it was installed on most or all of the M31 series
conversions done by Baldwin starting in 1943. The inset shows what we
think is the turret serial number, 465, on
SN 1355, a September 1942 production M3A5 that was formerly on display
at the Ordnance Museum at APG. With thanks to Tyler Reid.
Sometimes
turrets cast by different companies can be identified by minor
differences in the finished product. The turrets cast by American Steel
Foundries-Granite City (top) and Continental-Hubbard (middle) strike us
as nearly identical. In both cases, the bump-out (if you will) that
accommodated the commander's cupola has a "hard edge." The difference is
subtle and often depends on the light conditions, but we would judge
that General Steel turrets (bottom) have a softer, more rounded edge.
Returning to M3A3 SN 1099, we have an interior view that shows the
plaque (1) that declares that the tank served with the Brazilian Army
and was returned to the US in 1976. One can see the irregular line of 4
horizontal rivets (2) and the straight line of vertical rivets (3) that
attached the 75mm sponson casting to the welded hull. In this case,
there are 10 vertical rivets, that is, there are no missing rivets, as
seen on some Lees and Grants. The evidence suggests that 10 rivets was
standard on the diesel Lees. All of the rivets can be seen to have been
seal welded, a time-consuming process meant to prevent the rivets from
flying loose in combat. Of course, this is a welded hull Lee, one can
imagine the manhours spent to do this on a riveted hull. Note the
working pistol port/protectoscope (4) on the right side. It can be seen
that the door was welded in on the inside as well as the outside. The
pairs of rivets numbered 5 (vertical) and 6 (horizontal) would have held
the hinges for a working side door by means of slotted bolts on the
outside and nuts on the interior. We might have expected to see hinge
holes in the exterior view, but the surfaces appear to be clean in this
case (inset), not real obviously indented or filled in. The hinge
fitting (circled) for the pistol port appears to have been flush riveted
(flat) on the left and riveted on the right.
The
diesel Lees built by Baldwin starting in July 1942 seem to be pretty
much the same in appearance with ventilators, grouser boxes and rear
stowage bins. The 75mm guns all appear to have been the short M2 type
with counterbalances. If any of the diesels were built with M3 guns, we
have yet to come across an example. The 37mm guns look to have been
counterbalanced as well. When recording these we make a note of the
features including "welded doors." However, there is a bit of variety to
the appearance of the welded doors. On the left side of the tank, the
side where the pistol port was eliminated, we mentioned that SN 1099 is
the only one we have seen that has a pistol port installed, although it
is welded in and blanked off (1). Other units, such as SN 1332, an M3A5
on display in Rio De Janeiro, Brazil (2), are noted to have had the
pistol port opening (asterisk) filled in by means of a welded in plate.
Note that the pistol port bullet splash (arrow) was retained. This seems
to have been the most common configuration used on the diesel Lees. SN
1280 in Sao Paulo (3) can be seen with a "clean" door (3), although the
indentations from the door hinges and the pistol port opening are very
obvious. There even appear to be two depressions where the grab handle
would have been located. It is almost as if there was once a working
door and then everything was removed and filled in to get to a welded-up
door. The doors on the few other survivors aren't nearly this sloppy. Photos courtesy of Colonel Renato Rocha.
The
right side welded-up door is more or less the same on most of the
survivors. SN 1332 is typical. Some doors are seen with more hinge
indentations/traces than others. However, from a distance, the
welded-on doors of Baldwin built diesel Lees look flat, in contrast to
the welded-on doors seen in a few period photos of Chrysler Lees on
which the hinge holes were "filled in" with rivets. Photo courtesy of Colonel Renato Rocha.
At
least two examples in Brazil, both M3A5s, have solid right side armor
plates with integrated working pistol ports (1). One might expect to see
solid armor plates on the left sides, such as on late production
Chrysler M3s, but both have welded on doors in the retained pistol port
bullet splash configuration (2). Photos courtesy of Colonel Renato Rocha.
Here are photos of the only known
surviving example of a diesel Lee gun tank with solid armor on
both sides such as on late production Chrysler M3s and M3A4s.
This M3A3 is on display at the Agulhas Negras Military Academy in
Resende, Brazil. At present the serial number has not been found. This
is also the only Baldwin Lee that has been noted with the round object
(circled) attached to the gunner's sight housing. The "round object"
has been observed in a few period photos, as well as on a handful of
surviving late production Chrysler M3 Lees whose Serial Numbers
indicate that they were accepted in July or August 1942. Our best
guess is that it served to support a gunner's sight dust cover that was
planned to be added late in production. Photo courtesy of Colonel Renato Rocha.
We
suspect that Baldwin produced a few more diesel Lees with solid armor
on both sides including a few that were ultimately built as retrievers. Recall
that Baldwin was originally contracted to produce 685 Lees. However, in
August 1942, the Ordnance Department submitted a number of
specifications to Baldwin and tasked them with designing a Tank Recovery
Vehicle based on the M3 Medium chassis. For the initial work, Baldwin's
M3 Lee Production Order was reduced by 150 units, and these were
converted new to T2/ M31 series diesel retrievers. One such example is
M31B1, SN 117 on display at the Armor Museum at Saumur, France. As can
be seen above, this retriever has a solid plate with integrated working
pistol port on the right, and a completely solid plate on the left.
We conclude our study of Baldwin welded-on doors with Serial Number
1465/USA 305535. This M3A5 was shipped to Aberdeen shortly after it was
accepted in November 1942 and was the subject of an Inspection Control
Test in December. Some photos were included with the test, and these
show the diesel Lee with the highest known good serial number, at least
for us at present. OCM Item 23185 dated 16 March 1944 recommended
classification of the Medium Tank M3 series as obsolete. The
"Discussion" included "There are approximately 70 Medium Tanks M3A5 that
are new. They were earmarked for International Aid but were never
issued as the requirement was cancelled." If they were really all
specifically M3A5 models, they were probably those produced in the
months of September to the end of production in December 1942. We can
only assume that they would have been salvaged for usable parts and then
scrapped. In any case, SN 1465 can be seen with dust cover strips
around the 37mm gun plate, such as were noted on late production Lees at
the Detroit Tank Arsenal. What caught our attention in this view is
that a working pistol port and a bit of its surrounding area appears to
have been cut from another door and welded on to the right-side door
shown here. We can only surmise that some sort of foul up or
misunderstanding resulted in the original door not having a working
pistol port and the requirement was satisfied by the solution seen here.
For what it's worth, the left side door is seen in the configuration
that retained the pistol port bullet splash as shown in the inset. We
might have assumed that the perfectly flat or "clean" left side door
would have been later in the chronology, but that does not seem to have
been the case. At any rate, we can observe that there was an interesting
variety to the methods Baldwin used to implement the elimination of the
side doors mandate. Except for Ordnance type test photos, most period
photos only show one side of a tank. Consequently, we are grateful to
Colonel Renato Rocha for providing us with a photographic tour of the
surviving diesel Lees in Brazil.
As noted previously, Brazil is reported to have received 427 M3 Series
Light Tanks along with 104 M3 Lee series and 53 M4 Shermans as Lend
Lease during WW II. Brazil was the only South American nation that sent a
large combat contingent overseas during WW II. The Força Expedicionária
Brasileira, or FEB "numbered around 51,600 men, including a full
infantry division, and a fighter squadron." The FEB fought in Italy from
September 1944 to May 1945. However, their Lend Lease armor was not
deployed but remained in the homeland. A Lend Lease Allocations document
states that Brazil received a total of 100 Lees including very
specifically 77 M3A3s and 23 M3A5s. These were allocated from July 1942
through March 1943. However, another official document, "Quantities of
Lend Lease Shipments" has it that they received 104 M3 series Mediums.
Although Brazil is not listed as having received any Tank Recovery
Vehicles, we suspect that the country actually got 4, including M31B2 SN
81 now in storage at Ft. Benning. One online source states that the
Lees "remained in service...well into the 1950s." The photo above is
dated February 1960 and shows about 20 Lees taking part in a review,
perhaps their last detail? Most of the tanks are seen with welded hulls,
but Tank 1 is riveted. Some have replacement tracks of the rubber
chevron (2) or steel chevron (3) type. Tank 1 and a few others can be
seen with dust cover strips around the 37mm gun plate. A few of the
surviving diesel Lees in Brazil have them, and the inset shows the
strips on SN 1355, a September 1942 production M3A5 that was on display
for many years at the Ordnance Museum at APG.
After the Tunisian Campaign, the US Army's only further combat use
of the M3 Lee gun tank took place during the amphibious assault on
Makin Island 20-24 November 1943. The 193rd Tank Battalion arrived in
Honolulu on 7 January 1942, a month after the attack on Pearl Harbor. At
first, independent Tank Battalions were equipped with Light Tanks.
Starting in 1942, as Medium Tanks became available, most such battalions
on the US mainland converted to a Medium Tank organization (3 Medium
Companies and 1 Light Company). We haven't come across any records about
the progress of the 193rd. It is thought that the unit may not have
been fully equipped when it was attached to the 165th Regimental Combat
Team of the 27th Infantry Division for the Makin assault. Only Company A
with Mediums and Company C with Light Tanks were assigned, although
other personnel from the Battalion's Headquarters Company were trained
to operate the LVT-1 (Landing Vehicle, Tracked), and used 16 during the
operation. A few photographs suggest that Company C's Stuart Light Tanks
were diesels. As for the Mediums, from some motion picture footage on
Makin, we were able to record the Registration Number of Tank Number 19
as USA 305298 (left photo), indicating it was produced at Baldwin in
August 1942. USA 305298 appears to have been typical of the Lees of
Company A during the battle - diesels with welded up doors, ventilators,
grouser boxes, stowage bins and M2 75mm guns with counterweights.
Various histories report that Company A landed with 17 M3A5s on 20
November 1943. We can't confirm if they were all M3A5s due to the lack
of records and the limited number of images and their quality. Perhaps
Tank Number 6 (right photo) was an M3A3? At this point, the welded hull
configuration would have been deemed more "combat worthy" at least to
the Ordnance Department, but that was probably not even a consideration
to the logistics people tasked with shipping these tanks.
The well-known Signal Corps photo above is dated 21 November and shows a
pair of M3A5s shelling King's Wharf. Japanese troops had infiltrated
back on to the wharf during the night of D-Day, and their fire was
interdicting unloading operations in the lagoon. Some motion picture
footage shows at least 3 Lees (Speed Numbers 6, 7 and 19) on the beach
opposite the wharf. Another Lee can be seen to be mired in a shell hole.
This probably happened the day before during the initial landing. We
would assume that these tanks were built with flat block rubber tracks,
and that the rubber chevron tracks apparent here were retrofitted. The
tanks can also be seen with partial wading trunks on their engine decks.
These must have been installed in Hawaii and appear to have been
modeled after the type developed by the 5th Army Invasion Training
Center in the Mediterranean Theater. Two of the Lees are reported to
have drowned out when they fell into shell holes while wading in, but
during the 3-day action, the 193rd had about 15 operational Mediums
available to support the infantry. This can be contrasted with Company C
of the 1st Marine Tank Battalion. The Invasion of Tarawa took place at
the same time as the Makin Operation, and the 14 M4A2 diesel Shermans of
Company C had not been waterproofed or outfitted with wading equipment.
Consequently, many were drowned out in the surf, while others were
disabled when their electronics were ruined as sea water flooded in. It
was reported that only 5 of the 14 M4A2s were operational at the end of
D-Day.
Another well-known Signal Corps photo shows 3 Lees moving down a
jungle road past a Jeep with what appears to be "MED 2" painted on the
bumper. There were some complaints that the Makin Operation should not
have taken 3 days and been as costly as it was. The 193rd TB was given
no real training in infantry support. And for reasons unknown, the Army
did not develop an effective means of tank-infantry communication until
1945. As a consequence, the armor's firepower on Makin was not utilized
to its fullest extent. Out of necessity, infantry, tank and engineer
troops in combat quickly came up with their own methods of coordination
for destroying enemy strongpoints. "Lessons learned" were passed on and
used in future operations. In any case, the lead tank can be seen as
"Medium No. 19," which we take to have been USA 305298. Note that there
is one fixed machine gun mounted on the left (1). The objects circled
looked familiar to us, since we had seen them on SN 1355, USA 305425, a
September 1942 production M3A5 that was on display for many years at
APG. In the inset, item 2 is the comb or "pawl" device typical of the
Chester Tank Depot. This was part of a system engineered as a way to
lock or unlock the brakes during shipping without damaging the vehicle's
waterproofing sealant. Item 3 is a roller. It is thought that 5/32-inch
cables were threaded through the roller and into the fighting
compartment by means of a hole made when the middle bolt was removed
from the center section of the differential housing. Item 4 is a metal
strip that appears to have been used exclusively by CTD to hold a "zinc
tag" upon which were stamped instructions on how to use the pawl or
comb. The bogies of SN 1355 received the spacer modification that raised
the return rollers by about an inch. Assuming that No. 19 and the
others had been processed at CTD, say, in January 1943 or later, it
seems possible that this mod might have been installed at the time.
Unfortunately, in the few available Makin photos, there is too much
caked sand on the bogies in the area of the return rollers to make that
determination.
Above shows the dataplate inside Serial Number 1099. The Serial Number
can be seen stamped into the box at the upper right as indicated by the
inset. The
Baldwin plant was located in Eddystone, Pennsylvania, and was part of
the Philadelphia Ordnance District. From August 1942 to
December 1943, Colonel D. N. Hauseman was Chief of the
Philadelphia O.D., and his initials can be seen stamped into the box at
the lower right of the plate. Oddly, the crew is listed as "6 Men"
whereas it is listed as 7 on surviving Chrysler and ALCO
dataplates. All of the Grant dataplates and most of Lees that we have
seen are made of cast brass and have survived the years nearly
unchanged. Sometime in the middle of 1942, the Ordnance Department
ordered that dataplates be made of an alternate material in order to
conserve brass. These have been described variously as “steel
with a thin plating of nickel or cadmium,” or simply “pot
metal.” They were subject to deterioration by rust as the
protective clear coat, if any, wore off. We would judge that the
example shown above is an original Baldwin plate, representative of one
introduced on their Lees at the transition from brass to steel. It has
survived time better than most steel plates, possibly because the tank
was displayed inside a museum for many years. On a side note,
years ago, we visited a Railroad Museum and were told that the
library had a list of the "serial numbers" of all of the tanks built by
Baldwin. As it turned out, these were Baldwin "Construction Numbers,"
possibly the sort of numbers they used on their locomotives. For the M3
Medium series the numbers ran from 62541 through 63910, no doubt
reflecting the original contracts for 685 Grants and 685 Lees. In any
case, these numbers don't appear on any surviving Lee or Grant
dataplates that we have encountered. They may be elsewhere on the
tanks, but we have yet to "find" them.
The Variants: M3A4 Lee
In July 1941, just as M3 Medium production was getting underway, the
Ordnance Department asked the Chrysler Corporation if it could design an
alternate tank power plant "in a hurry." The expedient that emerged
used the "off the shelf" 6-cylinder engine from Chrysler's "Royal" line
of automobiles and combined five of them into a "star" configuration. By
mid-November 1941, the pilot engine was assembled and installed in a
Lee, which was road tested at the Dodge Truck Proving Ground since the
test track at the Detroit Tank Arsenal had not yet been completed. We
think that the donor tank was Serial Number 320, USA 304390, but regret
that we have not come across any photos. It was reported that the engine
compartment was lengthened by 18 inches as opposed to the 11 inches of
the production models, and we can't help but think that the difference
would be noticeable in photos, perhaps by simply "counting rivets." In
the event, the Army found Chrysler's "stop gap" design acceptable, and
in December 1941, Ordnance contracted for the installation of 109
"experimental multiple engine power plants" in the Medium Tank, M3. This
configuration was given the nomenclature "M3A4" and approved for
production later that same month. The view above was taken in October
1942, almost a year after the first power plant had been assembled. The
"tank repair shop" at the Ordnance Depot at Camp Young, California was
manned by a cadre of the newly formed 302nd Ordnance Regiment. The
Government was assisted by the National Automobile Dealers Association
in recruiting trained civilian personnel for such maintenance outfits.
Pvt. Charles Pangburn and Sgt. Clyde Weinbrunner provide an idea of the
great size of the "Chrysler multi-bank engine." Chrysler's model number
for this power plant was "A-57." Some of the total of 30 spark plugs
(circled) can be seen at the top of the individual flat head engines.
The radiator was so large that it could not be contained within the
space of the upper and lower hulls but required an armored "blister"
above the engine deck and another on the belly plate.
What we believe was the second M3A4 pilot model was shipped to APG in
early 1942 where it was tested and photographed in February. As can be
seen above, the tank was USA 304741. APG Reports list it as "Chrysler
Multi-Engine Power Plant in Medium Tank M3A4 #671." Had Serial Number
671/USA 304741 been built as a regular M3 Lee, it would have been
accepted in December 1941, as shown in our chart at the top of the page.
We have not listed it as an M3A4 in that month, simply because the
first of the 109 M3A4s produced were not officially accepted until June
1942 according to the Ordnance Department's "Procurement Master Plan,"
the document we use as the "final word" on US tank production. The
adaptation of the Chrysler A-57 Multibank to the M3 Medium was not a
simple engine swap. The massive power plant required an 11-inch
elongation of the hull of the original design. The center and rear bogie
units were moved further back, so that there was an 10-inch gap between
the road wheels as opposed to the 3-inch gap between the road wheels on
other types of M3 Mediums. As can be seen here, SN 671 was still fitted
with the original type of bogies. Note how the side plates went all the
way to the rear and were joined to the upper rear hull plate. This was
different from the other M3 models (except the M3A1) which were "jogged
in" in the rear.
This view of SN 671 shows a bit the "M3A4 Engine Installation." As with
the GM Twin Diesel power plant, the A-57 Multibank was so large that
there was no room for vertical fuel tanks in the front corners of the
engine compartment. However, the elongated hull enabled the sponson fuel
tanks to be enlarged to hold 80 gallons each. The filler points for
these gasoline tanks are shown at positions 1 and 2. As mentioned
previously, the size of the massive radiator required an armored
"blister" (3) above the engine deck. The water filler point (4) for the
radiator was mounted in the center of the "blister." Like the other
types of M3 Mediums, the engine air intake (5) was protected by nothing
more than a screen. The tools were not stowed on the engine decks as on
other M3 Mediums, possibly to make it easier and quicker to gain to
access the complex engine. Although no pioneer tools are present, the
fittings can be seen mounted on top of both sponsons. A pair of armor
castings (6) affixed to the upper rear hull plate provided outlets for
the A-57's exhaust. Just visible at the bottom of the photo are the open
engine access doors in the lower rear hull.
The Wright/Continental radial engine weighed "1137 pounds, dry" as
opposed to "5400 pounds, dry" for the A-57. The volute springs of the M3
Medium's bogies were barely adequate in supporting the weight of the
original engine. Consequently, and perhaps fortunately, Chrysler found
it necessary to design and incorporate heavier duty bogie units as part
of the M3A4 configuration. The new heavy-duty bogie as seen here had
beefed up volute springs and a trailing return roller arm. These new
bogies were, of course, greatly superior to the originals. Even so,
industrial conditions did not make it possible for Ordnance to mandate
an immediate, "without obsolescence" change. Consequently, except for
the M3A4, M3 series Medium production finished out with the original
bogies. Of course, as the designer, Chrysler was in the position to mass
produce and install the heavier duty bogies to all of its M4A4s,
including the pilot model which was completed on 9 May 1942. Other
builders began Sherman production with the older bogies, but as quickly
as they could be produced, the new bogies, which for convenience, we
refer to as "M4 bogies," replaced the original "M3 bogies," and by the
Fall of 1942 were standard equipment on all M4 series Shermans.
Above
shows what we believe was the first production M3A4. This tank can be
seen with features that would suggest June 1942 or later acceptance,
such as "no doors" and ventilators. The design did not require grouser
boxes like other late production M3 series Lees because the side plates
ran straight to the back which allowed for a pair of grouser
compartments to be created in the rear. The grousers could be accessed
by removing the oblong plate circled. Note that the grouser cover plates
are not present in the photos of SN 671/USA 304741 shown previously.
The front wall of the grouser compartment is denoted by the rivet line
indicated by an arrow. The M3A4 was not installed with rear stowage bins
possibly because they would have interfered with the pioneer tool
stowage on the sponsons or perhaps blocked access to the grouser
compartments. In any case, the evidence is that all of the production
M3A4s would have been similar in appearance. However, the Registration
Number, USA 309733, is again out of sync with the "later" chronology,
since it "signifies" an M3 Lee built in April 1942 by our reckoning.
Official M3A4 production figures are given as 33 in June, 73 in July and
3 in August 1942. The discrepancy might be explained in part by the
wording of the December 1941 contract, "Said Medium Tanks, M3, shall be
furnished by you from production models currently being manufactured by
you...and the hull of each shall be modified by you at the appropriate
stage of production in order to accommodate said Experimental Multiple
Engine Power Plants." The Ordnance Department's desperation for an
alternative power plant along with its desire to replace the Lee with
the Sherman as quickly as possible is reflected in their back-and-forth
correspondence with Chrysler. The Government had contracted for the
production of "the Pilot T6 which became the M4A4" on 5 January 1942,
not even 2 months after the first Multibank was completed and installed
in an M3 Medium. Ordnance wanted Chrysler to switch over to the Sherman
after 2752 Lees (approximately June 1942, SN 4123), whereas Chrysler
wanted to break at 4000. In the end the changeover occurred on 20 August
1942 after 3352 Lees had been produced. It can't be said that the 109
M3A4 Lees served as testbeds for the "Experimental Multiple Engine Power
Plant" or for the M4A4 Sherman for that matter, since by June 1942, the
Government had gone all in, and for the next year, committed its first
ever purpose-built tank plant to the production of over 8000 M4A4s. The
first 2 were accepted in July and 167 in August as the last M3s and
M3A4s rolled off the line.
The above is from the June 1942 series of Detroit Tank Arsenal factory
photos. The Registration Number of the M3A4 can be read as USA 3010292
or perhaps 3010293. Either way, it would "indicate" an M3 Lee accepted
in May 1942, so is another example that is out of sync with the "later"
M3A4 chronology. An additional photo in the series clearly shows an M3A4
as USA 3010149, yet another outlier. If Chrysler attempted to reconcile
the discrepancies by identifying the date of production along with the
serial and registration numbers of each of the 109 M3A4s produced, we
have yet to find the relevant documents. We suspect that the first 7, or
perhaps the first 15 M3A4s, may have been the outliers. The first 7
were produced on Production Order T-1473, completed 13 June 1942. The
next 8 on P.O. T-1506 completed 23 June 1942. The remaining 94 were
produced on P.O. T-2593, completed 4 August 1942. We don't have much
counting heads data but would guess that the last batch of 94 was "in
sync." In any case, it can be seen that the Registration Number of the
M3 in front of the M3A4 appears to be USA 3010748 which would indicate
June acceptance, and so is in sync with our chronology. Note that there
were 3 removable engine deck plates (1) behind the radiator blister.
Each appears to have been about 16 inches deep. This was changed on the
M4A4 design to a single hinged engine deck plate (2) about 33 inches
deep, along with a non-removable 12-inch plate (3) that was welded to
the hull. The M4A4 pilot would have been at APG when this photo was
taken, so we believe that the tank seen here would have been Serial
Number 4805, the first production M4A4, or in any case, one of the
earliest M4A4s based on the "high" turret lifting ring (4). There is
another M3A4 two units in front of our subject.
In his book, "M3 Lee/Grant," David Doyle has it that, "Chrysler records
indicate that all the production M3A4 tanks were shipped to Camp
Chaffee, Arkansas where they were assigned to the 6th Armored Division."
That certainly appears to have been the case, since nearly all of the
available photos show them serving with the 6th AD during Maneuvers in
Louisiana in August and September 1942. The photo above is captioned,
"These tanks of an Armored Div., unloaded at Louisiana, will be used in
the Third Army Maneuvers. 8/28/42." The lead M3A4 can be identified as
6th Armored Division by the "6" inside the turret star. All 7 of these
tanks are alike in appearance with M3 75mm guns, no doors, "M4" bogies,
and no grouser boxes or stowage bins. A hint that they are installed
with ventilators is provided by the angles of the open upper hull
hatches. As mentioned, the photo is dated 28 August 1942 and the 109
M3A4s were manufactured June through August 1942, so would have been
shipped brand new to the 6th AD at Camp Chaffee, assuming they received
all of them. (Recall that at least 1 M3A4 was photographed at the DTC in
August 1942.) It is reported that the division's wheeled vehicles drove
down to Louisiana, while the tanks were sent by rail, two to a car
judging by the photos. The 6th AD was formed from cadre men of the 1st
and 2nd ADs, and organized as a "heavy armored division," which on paper
would have had 232 Medium Tanks and 158 Light Tanks in 2 Regiments
(68th and 69th), each of which would have been composed of 1 Light and 2
Medium Tank Battalions. We can only assume that the 6th AD was equipped
with some earlier M3 Mediums as the cadre prepared to receive and train
some 10000 inductees at Camp Chaffee in the Spring of 1942. In any
event, the 109 M3A4s would not have been half of the unit's full
allowance of Mediums. By the end of August 1942, 169 M4A4s would have
been produced and it seems likely that the 6th AD would have received a
few of those as well.
This
photo is also dated 28 August 1942, and we believe shows some of the
same M3A4s as in the previous caption, but perhaps an hour or two
earlier, since the tanks are not manned, and the turrets are pointed to
the rear. The tactical markings painted on the differential housing
denote "68th Armored Regiment, Company D, Vehicle 17." We have been
wanting to observe that, based on counting heads, Chrysler did not build
its Lees with dust cover "snaps" or "press studs" around the 75mm gun.
However, every once in a while, they seem to show up in period photos,
like on the second tank in line here (arrow). The first two units (at
least) can be seen with the "round object" (circled) attached to their
gunner's sight housings. As mentioned, these have been observed in a few
other period photos, as well as on a handful of surviving late
production Chrysler M3 Lees and one Baldwin M3A3. The inset shows the
object on M3 Lee SN 4540 on display at The American Heritage Museum in
Hudson, MA. Again, our best guess is that it served to support a
gunner's sight dust cover that was planned to be added late in
production.
Again, this Signal Corps photo is dated 28 August 1942, and the caption
reads in part, "Medium tank arrives securely tied to flat car." The
vehicle can be seen chocked and blocked, but there is no evidence that
it is tied down. Perhaps any such tie downs had already been removed? It
is obvious that the familiar U-shaped tie down fittings were not
attached to the front and rear bogies and used in this instance. The
bogie brackets are observed with raised lines (1) running across the
castings. We were able to examine one of these from a surviving M3A4 and
could see the "N inside a circle" caster's logo of the National
Malleable and Steel Castings Company of Sharon, Pennsylvania. These are
commonly noted on Chrysler Shermans. Many National Malleable examples
include the date that they were cast. A close examination of this print
revealed that the Registration Number was USA 3058027 (2), indicating
July 1942 acceptance. The name "Diablo" (3) can be seen painted on the
side. The tactical markings are only partly visible as "D-17." However,
it seems pretty likely that this is the same M3A4 as in the previous
caption.
In March 1942 the War Department eliminated the office of Chief of
Cavalry, effectively disbanding the old horse cavalry. In the meantime,
having witnessed the stunning success of the German Blitzkrieg since
September 1939, the Army was frantically trying to mechanize its forces.
They went so far as to combine 5 automobile engines to make a power
plant for a 30-ton tank. The photo above was taken in September 1942 and
is captioned,""Blue" tanks supported by Cavalry, advance in downpour of
rain during maneuvers in Louisiana." Shortly thereafter, the horse
troopers rode off into history. This Lee can be recognized as an M3A4
primarily by the "M4 type" bogies. The absence of grouser boxes and rear
stowage bins provide secondary clues. The tactical markings identify it
as "68th Armored Regiment, Company I, Vehicle 16." The turret was
reversed on "Diablo" in the previous caption, but here I-16 can be seen
to be an example with the dust cover strip fittings around the 37mm gun
mantlet.
Most of the few Signal Corps photos of the 6th AD M3A4s show tactical
markings of the 68th Armored Regiment, but here we see "D-3" of the 69th
AR. The caption is a little more informative than the others, "An M3
[sic] rolls down ramp from flat car on which it was shipped from Camp
Chaffee, Ark. to Boyce, La. 8/28/42." This tank does not have the dust
cover strips around the 37mm gun mantlet, and the 75mm appears to be the
earlier, short M2 gun with counterweight.
The 6th AD returned to Camp Chaffee in late September 1942, but only
stayed long enough to pack up and turn over its quarters and equipment
to the incoming 14th Armored Division. The 6th was ordered to the Desert
Training Center where it continued to train from October 1942 through
March 1943. As best we can tell, their armor was left behind at Camp
Chaffee. The photo above is captioned, "Stalled M-3 [sic] tank at Camp
Chaffee, Arkansas, November 10, 1942." By the date, this may show an
M3A4 "inherited" by the 14th AD, but we can't say that we know of any
photos of M3A4s with 14th AD markings visible. Their souvenir history
mentions that the 14th AD was formally activated on 15 November 1942,
and during the day, "There was a sham battle, in which medium tanks
(running heavily to the old side-winding M-3's) and light tanks,
supported by infantry, attacked an objective." We suspect that when the
inductees began to arrive in December 1942, the armored units of the
Division were equipped with a mixture of M3A4s and M4A4s. The insets are
a pair of tiny photos from the souvenir history which show one of each
type. It is also mentioned that the Division set up "A school in
Chrysler multi-bank engines" in January 1943. In any case, the Signal
Corps photo above shows the M3A4 being towed by an M1 wrecker truck, but
we've cropped it in order to focus on the Lee. A close examination of
the glossy print at the US Archives revealed the Registration Number to
be USA 3058018 indicating July 1942 acceptance. The M2 gun with
counterweight is likely the original, but could also be a replacement.
This tank does not appear to have the dust cover strips around the 37mm
gun, but does appear to have the round object attached to the gunner's
sight housing.
Earlier we featured a photo that showed a few Lees and Shermans at the
Ordnance Depot at Camp Young, California. One of the Lees was an M3A4.
Based on the identical weathering pattern on the left rear, this tank
also appears in the photo above captioned, "Desert Training
Center...view of tank which was damaged by fire. Aug. 1942." The M3A4s
and a few of the earliest M4A4s were shipped with the grouser
compartment holes blanked off. However, it was found that the fuel tanks
of the M3A4s and early M4A4s suffered an excessive heat condition,
which caused melted solder joints. Consequently, gasoline leaked into
the engine compartment, and became a great fire hazard. This situation
does not appear to have been addressed on the M3A4s possibly due to
their short service life. However, on the M4A4 and early M4A1s, which
had similar heat issues, the situation was remedied by the addition of a
pair grouser compartment covers with air inlet grills that permitted
greater air flow around the fuel tanks. At the Detroit Tank Arsenal, the
grouser compartment covers or "air scoops" were introduced on the M4A4
early in production in August 1942. The dust cover strips around the
37mm gun are present on this example. As can be seen here, M3A4s mounted
the taillights (1) under the upper rear hull overhang. Shermans,
including the M4A4s, had these mounted on the rear sponsons. The exhaust
outlets (2) were repositioned under the upper rear hull overhang on the
M4A4.
Here we have a surviving M3A4 that had had its paint washed away after
many years out in the elements, and yet the named "Goldbricker" (1) was
still clearly visible. The differential housing was missing, but "69-G- "
(2) could be seen in the center of the upper rear hull plate. We have
no doubt that these were WW II era markings, indicating "69th Armored
Regiment, Company G." The Vehicle Number might have been "4" but it is
hard to say for certain. The original Registration Number painted on in
black by Chrysler was no longer visible, but a repainted and
repositioned "USA 3029021" (3) could be seen on both sides. By our
reckoning, this would correspond to Serial Number 4363, and indeed we
recorded that number stamped on the right rear tow lug and stamped into
the hull wall (4) underneath where the dataplate had been mounted.
A year or so after we examined "Goldbricker," the photo above was posted
online. The original Registration Number as painted on by Chrysler is
clearly visible as "U.S.A W-3,029,021" and "Goldbricker" is painted on
in the same location as we saw it some 70 years later. This photo was
likely taken "in the field" since pup tents are visible in the
background. We would observe that "Goldbricker" does not have the band
or star on the turret, such as appears on the M3A4s in the Louisiana
Maneuvers photos. Perhaps the photo was taken not long after the tank
was received at Camp Chaffee? This tank lacks both the dust cover strips
around the 37mm gun as well as the round object attached to the
gunner's sight housing. On the surviving "Goldbricker," some additional
tactical markings, "6 TG 749 Δ," were noted on the upper rear hull
plate on the left as shown in the inset. We translate these as 6th Tank
Group, 749th Tank Battalion. We would think that "Goldbricker" might
have been inherited by the 14th Armored Division when they were posted
to Camp Chaffee, and then perhaps after that it was provided to the
749th Tank Battalion sometime after they arrived at Camp Bowie, Texas in
February 1943. Sgt. J.W. Breakbill of the 749th describes a bit of his
training there, "They put us in a M3 tank with 5 Chrysler engines
mounted in it. Very hot inside when you were buckled up. The turret
traverse was only 45 degrees. You set astraddle the transmission, like
sitting on an oven turned wide open. We were in those tanks for three
weeks, learning were everything was so we could run it blindfolded. Then
they took us out to learn how to drive them."
While other types of Lees were converted to T2 (M31) Tank Recovery Vehicles and Shop Tractor T-10 [Canal Defense Lights], it would
appear that no further use was found for the M3A4s and that they were
simply retired after sufficient numbers of Shermans became available to
units in training. An inventory dated 11 September 1943 accounts for 108
of the 109 M3A4s produced. Most, 102, were at the Red River Ordnance
Depot in Texas. The few others were scattered around at depots and
bases. For instance, one M3A4 is listed as at the Benicia Arsenal in
California, and it seems likely that this was the unit we featured
previously that had caught fire. There may have been an exception to
further use in one case. At the beginning of this section, we speculated
that Serial Number 320 may have been the Lee used for the first
installation of the Multibank engine in November 1941. Recall that the
engine compartment was reported to have been lengthened by 18 inches as
opposed to the 11 inches of the production models. We base our theory on
some shipping documents we happened upon at the US Archives. In the
document on the left, it can be seen that Serial Number 320, USA 304390,
which would have been November 1941 production, was listed as a "Tank,
Medium, M3A4" when it was shipped from Chester Tank Depot to Aberdeen
Proving Ground on 11 January 1943. Note that the tally sheet lists a
37mm gun. At that time, APG had received 6 CDL turrets, along with other
parts, plans and schematics from the British. These were adapted to US
standards and used for the assembly of pre-production pilots. We can't
say for certain that SN 320 was converted at APG, but from there it was
shipped to ALCO in Schenectady on 25 February. In the document on the
right, it can be seen that the vehicle is now labeled "Shop Tractor T10
(Modified Medium Tk. M3A4)" and that there is no longer a 37mm gun on
the tally sheet. Could it be that SN 320 was used to test the
feasibility of doing the Shop Tractor conversion using the M3A4? In any
case, ALCO was tasked with remanufacturing "the M3 chassis to the CDL
configuration." Pressed Steel Car assembled the "S" turrets, and Rock
Island Arsenal performed final assembly under Top Secret conditions.
Unfortunately, the "History of the [US] C.D.L. Project" dated 26
November 1943 makes no mention of the use of an M3A4 hull at APG or
ALCO, although it does rather specifically state that the first of the
two ALCO pilots "Medium Tank, M3 serial No. 2289 was released to
American Locomotive Company for conversion during the latter part of
March 1943." (We take this to have been an M3 Lee built by ALCO a year
earlier in March 1942.) The history has it that the "Services of Supply
[were] directed that 500 C.D.L. units be produced prior to July 1944."
Author Richard Hunnicutt states that a total of 497 were produced, based
on both M3 and M3A1 models.
The Variants : Shop Tractor T-10 [Canal Defense Light]
US
built Shop Tractor T10s served in Europe during WW II, so we think it
is appropriate to devote a few captions to them on this M3 Lee page. The
photos above show both the M3 and M3A1 based CDL conversions that were
preserved "for historical purposes" at the Ordnance Museum at Aberdeen
Proving Ground. They were photographed in February 1949. The riveted
hull was "Salvaged" while notes on the cast hull photo indicate that it
was "To be reconditioned and issued to Auto. Div." in September 1950.
This appears to have been in answer to a request from the US Eighth Army
in Korea "for a means of direct visible battlefield illumination."
Ultimately, it was decided that standard 18-inch searchlights could be
provided at a small fraction of the cost of purpose made searchlight
tanks. In any case, neither of the T10s appear to have survived in the
APG collection past the 1950s. Based on the few available photos, it
would seem that working side doors were not a requirement of the
conversion program. On the other hand, all photos examined to date show
the units retrofitted with M4 bogies (1). Recall that in the February
1942 Report regarding ALCO M3 SN 1687, "It was recommended that all
rotor clearances [around guns] be provided with shields and splash
proofing." Although we have never seen it on an M3 gun tank in service,
the 75mm Rotor Shield (2) modification appears to have been produced and
retrofitted to most or more likely all of the T10s. The "box" (3) above
the 75mm gun may have protected a direct sight telescope. It is thought
that the T10s were equipped with two driver's periscopes
positioned side by side. The cast hull unit has these mounted on
or through what look like round ventilator housings (4). The
riveted hull has the periscope centered over the driver's position
mounted in a similar fashion, while a periscope guard (circled and
inset) indicates another installed directly through the "roof" plate. Reconfigured,
open(?) grouser boxes (5) and rear stowage bins (6) appear to have been
required, along with an additional head lamp (7), mounted on or above
the fixed machine gun casting. We don't believe that the T10 was
equipped with fixed machine guns, but a ball mount (8) for a .30 caliber
machine gun was included on the CDL turret. Again, based on photos, the
T10 conversion program appears to have mandated sand shields, but as
was the case with Shermans in service overseas, most crews removed them
immediately.
Starting
in August 1943, the 701st, 736th, 738th, 739th, 740th and 748th Tank
Battalions (Special) trained with T10s (also code named "Leaflet tanks")
under Top Secret conditions at Camp Bouse, Arizona. They were deployed
to the European Theater of Operations beginning in the Summer of 1944,
but due to the extremely secret nature of the project, no missions were
assigned to either the British or US CDLs. By the Fall, trained tank
crews were in great demand and four of the idle US CDL units were
converted to conventional Tank Battalions, while two were converted to
Mine Exploder Battalions. Author Steven Zaloga reports that "In February
1945, with operations along the Rhine likely, 65 Leaflet tanks were
taken out of depots to be used to guard key bridges against German night
attacks. They were issued to three tank battalions: the 738th, 739th
and 748th." The original purpose of the CDL program was offensive in
nature. Its powerful strobe light, what Aberdeen called a "blinding
ray," was designed to assist night attacks by confusing and paralyzing
enemy defenders. In practice, the CDLs were used as searchlights against
enemy night attacks at Rhine River crossing points or to provide
illumination for engineers attempting to erect or repair bridges. The
738th Tank Battalion (Mine Exploder) appears to have been first to use
CDLs in combat on the night of 9/10 March 1945 at Sinzig near the
Remagen Bridge. "At 2400 hours, Lt. Olson, Co "C", with four (4) CDLs
was given mission to furnish illumination for Engineers at F670175 on
west side of river...a direct hit scored on one (1) CDL, damaging turret
and wiring." The CDLs continued to perform such missions until
mid-April when the 3 Battalions were ordered to turn them in. For
instance, on 17th April 1945, the 738th turned "thirty-four (34)
CDLs...in to 955th Ord." The snapshot above shows one of the units of A
Company, 738th TB (ME) being transported in Mönchengladbach, Germany.
(Along with CDLs, the 738th operated Mine Exploders, Dozers and
Psychological Warfare (Loudspeaker) tanks.) Judging by the foliage on
the trees, this photograph was likely taken in the Spring of 1945.
So
ended the combat service of the Shop Tractor T10. The 10th Army on
Okinawa ordered 60 CDLs but they had not yet arrived when "organized
resistance" ended on 22 June 1945. At that point, the number requested
was cut back to 18 "for tactical and organization try out." For the
planned invasion of Japan, a few advocates proposed that each separate
Tank and Tank Destroyer Battalion be augmented with a platoon of 5 CDLs
in their Headquarters Companies. Again, as on the Rhine, their original
intended offensive purpose was ignored, and "CDL tanks will be employed
in bivouac and positional defense and also to illuminate areas for night
firing." In other words, these were to be used as extremely expensive
searchlights. On 18 July 1945, the War Department notified the Pacific
Theater that an additional 181 "were available for shipment from UK."
This seems to suggest that about 250 CDLs or roughly half of those
built, had been supplied to the ETO. Furthermore, should the PTO desire,
"These tanks can be shipped upon request to ZI [Zone of the Interior,
i.e. US] for modifications consisting of extended end connectors, wading
stocks, moisture proofing of radio equipment, installation of RC-298
telephone and AN/VRC-1 radio, addition of exhaust fans for hull
ventilation, and protective screen over rear deck of hull." And it was
noted that the 60 already on their way had been so modified. Thus, we
gain some insight about the "ultimate" version of the Shop Tractor T10.
There should have been nearly 250 CDLs in the US, so it is a mystery why
the 181 offered to the PTO needed to come from the UK. At any rate, the
photo above shows more than a dozen T10s on rail cars in Nashua, Iowa
in April 1945. These units were obviously processed for shipment, but
the installed sand shields suggest that they had not received the mid
1945 modifications, or at the least, not the extended end connectors.