Introduction
The
rapid expansion of M3 Medium Tank production required more power plants
than the limited supply of Radial tank engines could provide.
Consequently, the Ordnance Department cast about for other
possibilities. In August, 1941, General Motors was contracted to perform
an experimental installation using M3 Lee Serial Number 28, which was
pulled off the line at Chrysler and shipped a short distance to GM’s
Detroit Diesel Plant. The configuration combined two "off the shelf" GM
6-71 diesel truck engines that were “coupled together by means of a
transfer case delivering the doubled power to a single driver shaft.”
Together the engines developed about 400 horsepower. SN 28 was
successfully tested at APG, and in October, 1941, the twin diesel engine
was designated the "GM Model 6046," and authorized for production as an
alternate power plant for the Medium Tank. Above shows SN 28 at APG in
November, 1941. The
upper rear hull plate was reconfigured by being elongated and mounted
on an angle in order to accommodate and protect the rear mounted
radiators. The engine access doors in the lower rear plate of the
original M3 design were eliminated, and instead a pair of mufflers were
mounted across the plate. Note that a sheet metal exhaust deflector was
installed on the pilot. The engine was serviced through a rather large
pair of doors on the engine deck. This configuration was carried over to
the Sherman design as the M4A2.
Above
shows a GM Model 6046 twin diesel on display at the Tank Museum at
Bovington. Note the transfer case indicated by the arrow. The
size of the twin engine configuration necessitated a number of
changes to the layouts of both the engine and fighting compartments.
For instance, the addition of the transfer case made the power pack
longer than the engine compartment. Consequently, the firewall was
altered to permit the transfer case to protrude into the fighting
compartment. From the start the US Army had determined that it would
employ gasoline powered Shermans in its armored units, so production
of the diesel was primarily intended to satisfy the requirements of
the Lend Lease Program. Photo
courtesy of the late Massimo
Foti, a
fine photographer, and friend to Sherman Minutia.
In
April, 1942, the M4A2 became the first model of welded hull Sherman
to go into production at both Fisher Body and Pullman Standard. This
photo shows the pilot tank produced by Fisher (Serial Number 2305,
accepted in April 1942). The welded hull configuration varied from
company to company, and underwent a number refinements over
time. It is believed that the 50 first units produced by Fisher were
similar to SN 2305. No doubt this
early configuration would have been based on the design concepts of
the M4 welded hull pilot constructed without turret at Rock Island
Arsenal in October, 1941. The pilot used the M3 Medium Tank lower
hull, power train, engine & running gear. The upper hull of the
RIA pilot utilized various cast components plugged into the basic
assembly of welded together armor plates. These castings included the
drivers' hoods, antenna bracket, bow and fixed machine gun "plate,"
hull ventilators, and a bullet splash guard around the turret, to
name a few. We have not come across any photos of the RIA
pilot, and it strikes us as possible that the hull was sent to either
Fisher or Pullman and used for one of their pilots, with the GM
Twin Diesel Power Plant replacing the original Wright Radial engine.
Combat debut
in El Alamein
The Sherman’s combat
debut came with the British at the Second Battle of El Alamein, which
commenced on October 24, 1942. The story is well known, but to
recap...On June 21, Prime Minister Winston Churchill was at the White
House when he got the news of the surrender of Tobruk. President
Franklin Roosevelt asked if there was anything he could do to help, and
without hesitation, Churchill replied, "Give us as many Sherman tanks
as you can spare, and ship them to the Middle East as quickly as
possible." Soon after, Roosevelt ordered the dispatch of 300 Shermans
and 100 M7 Priests. This would have been pretty much the entire
production of Shermans up to that point. The tanks were collected up
from the factories, as well as from US units that had just begun
training with them. The "5185 Opportunity" convoy sailed on July 15,
1942 with 302 Shermans and 100 Priests. The Shermans break down to 212
M4A1s and 90 M4A2s. The S.S. Fairport with 51 M4A1s and 32 Priests on
board was sunk by a U-Boat the next day. The Seatrain Texas sailed
unescorted two weeks later with replacements of 52 M4A1s and 25
Priests. The voyage took two months, and the Shermans began to arrive
in Egypt in September, 1942. Apart from these, an earlier
“regular” Lend Lease shipment of 15 M4A2s
“which had been intended to come well ahead...actually only
preceded [the emergency shipment] by a few days. The IWM
photos above are dated September, 9th. On July 15, when the convoy
sailed, the only M4A2s that were in production were made by either
Fisher or Pullman.
This tank
can be seen as T-74271. In another photo from this series, the USA
Number is partially visible as “305313X,”
indicating that it was made by Pullman. Note the
“low” position of the turret lifting rings. Counting heads suggests that Fisher continued with the “high” lifting rings into early 1943. From
that we “interpolate” that any of the 105 M4A2s in
theater at the time, and seen with “high” lifting
rings would have been Fishers, and any with the
“lows” would have been Pullmans. The British War Department
Numbers of these first 105 all appear to have been in the T-742XX and
T-743XX range. The M3 Medium was built without hull lifting rings, and
this deficiency was corrected with the M4 series. However, stevedores
were reluctant to “trust” the lifting rings, and
continued the damaging practice of hoisting the tanks as shown above,
using slings running under or across the belly plate. IWM
E16599
and E16603.
In
a photo from the same IWM series, the USA Number, 3053165 (inset), is
just visible on the rear side of the M4A2 in the foreground.
This tank
can also be seen to be T-74291. Units records list T-74291 as with the
47th Royal Tank Regiment. It was battle damaged during the Alamein
campaign, but recovered and repaired. In a General Motors Technician's
Report from Tripoli dated August, 1943, T-74291 is listed as Pullman
Serial Number 955, which is an exact mathematical match to USA 3053165.
Serial Number 955 would have been accepted in early July 1942, overall
Pullman’s 51st M4A2. Since the convoy sailed on July, 15th,
it is pretty certain that this was a new tank shipped directly from the
production lines, not one that had been issued to US troops. There
wouldn’t have been any time for that. The "UFS"
seen painted on these Shermans is shipping code for "US-Freetown-Slow."
It was a slow speed, zig-zagging convoy from the US to Freetown in West
Africa. From there, the Royal Navy took over escort duty for the long
journey around Africa, through the Suez Canal and on to Egypt. Most of
the “Alamein Shermans” are noted with 3-piece
differential housings, but a close examination of the front reveals
that SN 955 was built with a 1-piece. The engine deck of the M4A1 in
the background is “clean,” while the
M4A2’s is “busy” with a number of
additional cable clamps on the rear most plate. This reflects the
original plan to stow the towing cable on the engine deck in the manner
of the M3 Medium and T6 (Sherman) pilot. Ultimately, the tow cable was
stored along the left side of the Sherman, but the rear deck clamps are
seen in a few photos of early Fisher and Pullman M4A2s. Based on what
we know of this M4A2, we could observe that "the rear deck clamps are
seen on some Pullmans produced up to July, 1942."
IWM E16607.
In
this view from the same IWM series of September 9th, the M4A2 can be
seen as
USA 3053166, the next tank built by Pullman after SN 955 of the
previous
caption. This tank carries the British Number T-74299, and like its
sister tank
above, is listed in unit records as in service with the 47th Royal Tank
Regiment during the Alamein Campaign. Since we’ve been asked
many times, we
would like to point out that there is no mathematical correlation
between the
British assigned WD Numbers and the US Ordnance Serial and/or
Registration
Numbers. For instance, in this case, we see that 3053165 of the
previous
caption was T-74291, while 3053166 was T-74299. The WD Numbers were not
assigned in strict sequence, which makes it impossible to determine the
builder
or month of production of a Sherman if all one knows is the WD Number.
It is
evident that the Shermans seen in this series were outfitted with sand
shields
before they left the US. Pullman provided and installed sand shields
for most of
their Grants, but in the case of the "5185 Opportunity" shipment, the
evidence suggests that these were installed at the Tank Depots which
were just
coming on line in the US. Note
that the front section of the sand shield is rounded on the
Shermans, as opposed to the angled fronts on the Grants and Priests.
The
rounded configuration was adopted when the Ordnance Department mandated
the
installation of sand shields in mid 1943. T-74299 still has some of its
“On
Vehicle Materiel” [OVM] boxes mounted on the rear deck. Most
of the items would
have been unpacked and placed in or on the vehicle when it was
processed for
issue at a Base Workshop. Note
that T-74299 can also be seen with additional cable clamps on the rear
engine deck.
IWM
E 16608.
The IWM photos above
are part of a series dated October 10, 1942, about two weeks before the
start
of the Second Battle of El Alamein. They document the visit of a child
entertainer named Tita Rickard to a repair crew working on a Sherman
“in the
Western Desert.” Note the presence of the bump in the photo
on the left. Due to
the date and the low position of the turret lifting ring, we take this
example
to be another Pullman M4A2 from the emergency, or what the British
frequently
termed, "the special shipment." At first we thought that the use of
the glacis casting with the bump was short lived, and limited to a few
early
M4A2s, along with the two Ford M4A3 pilots. These castings, with the
machine
gun fittings on the inside, would have been rendered obsolete with the
elimination of the twin fixed machine guns in March, 1942. We would
note that
in the few period photos showing the "bump" on M4A2s, as well as on
the two known surviving examples, the tanks have direct vision.
However, the
bump has also been observed in a pair of photos of early 1943
production M4s
thought to have been made by ALCO, and with the later type of drivers'
hoods. We
can only guess that the use of these castings in 1943 was a case of
recycling,
or “waste not, want not.” At any rate,
“the bump” provides us with an
interesting and ongoing little Sherman mystery. Note that this unit has
a
1-piece differential housing, which is seen in period photos on a small
number
of the special shipment M4A2s and M7 Priests, but so far not the M4A1s.
The
British added a number of internal and external items when they
processed these
tanks for issue. An obvious one here is the sunshield framework running
along
the side of the vehicle. Another is the stowage box affixed to the rear
of the
turret. Based on the locations given in the War Diaries of the 41st and
47th
RTRs, we believe this scene was shot in the area of Wadi El Farigh,
about 50
miles (80 km) northwest of Cairo. IWM E
17857 and E
17854.
Since
more than twice as many M4A1s were sent with the special shipment, they
got
most of the photographic “publicity.” For instance,
the crews and M4A1s of C
Squadron, 9th Queen’s Royal Lancers, 2nd Armoured Brigade,
1st Armoured
Division were extensively photographed "in action" on October 16,
1942. It might be said that this series has become iconic, as any
account of
the Second Battle of El Alamein, will generally include one or more of
these
photos. However, the M4A2s also fought in the campaign from the start.
The
various “Tank State” documents record a total of
318 Shermans in the Middle
East at the beginning of the battle. Unfortunately, these and the unit
diaries
don’t break down petrol versus diesel Shermans, so we have
tried to seek out
clues where possible. For instance, on September 4th, 1942, Eighth Army
Headquarters directed that the 1st and 8th Armoured Divisions, along
with the
9th Armoured Brigade, would receive the “Swallows.”
As they were processed for
issue in September, the 1st AD and 9th AB were assigned 94 and 46
petrol
Shermans respectively. The first 64 diesels processed were ordered to
the 8th
AD, along with 30 petrols, which would be “replaced by
Diesels as and when
available.” From this we interpolate that, leading up to the
start of the
battle, the 8th AD, and more specifically, the 24th Armoured Brigade,
was
chosen to receive all of the available diesels. Due to manpower and
materiel
shortages, the 8th AD was essentially disbanded before the start of the
battle,
and the 24th Armoured Brigade, made up of the 41st, 45th and 47th Royal
Tank
Regiments, was transferred to the 10th Armoured Division on October
12th. IWM E
18377.
The
WD Numbers reported for the battle in their respective War Diaries
suggest that enough M4A2s to fully equip two Squadrons were issued to
both the 41st and 47th Battalions of the Royal Tank Regiment, while the
45th RTR appears to have been issued M4A1s. Each
of the Battalions began the battle with 3 Squadrons (A, B and C), two
with Shermans, and one with Crusaders and each Squadron would have been
composed of 14 tanks, assuming full availability. Unfortunately, the
Shermans are not listed in the diary as “petrol” or “diesel,” but we
interpolate from our counting heads research that the WD numbers in the
T-74213 to T-74317 range were M4A2s. From this we take it that the 41st
and 47th RTRs began the battle with only diesel Shermans. The WD Numbers
listed in the diary for the Shermans of the 24th Armoured Brigade
Headquarters (T-74233, T-74250, T-74266 and T-74287) indicate M4A2s,
and we believe that Dover shown above, was one of these. The day before
the battle, the units of the Brigade moved into their starting
positions, “and tanks [were] immediately camouflaged as lorries,” as
evidenced by the sunshield in place. Dover is in the process of being
“teed up” with supplies, and we would observe that this tank has the
additional cable clamps on the rear engine deck, and they appear to be
preventing the various crates from lying flat. The dual muffler and
exhaust system is partly visible here. We would have expected to see the
sheet metal exhaust deflector mounted in front of (and obscuring) the
mufflers, but it is notably absent in this and the few other rear shots
of the Alamein M4A2s. The
“71 on a square” painted on the rear sand shield identifies "Dover" as
belonging to an Armoured Brigade HQ (BHQ), while another Sherman in this
photo series (“Ports’th,” IWM
E
18460) shows the formation marking confirming the brigade as the 24th Armoured Brigade. IWM
E 18463.
The first phase of El Alamein offensive
was codenamed “Operation Lightfoot.” In brief, the
plan was for the infantry in the northern sector of the line to attack
and overwhelm the Axis’ forward positions. Sappers would then
clear two corridors through the minefields permitting the armor to
break through. “No battle plan ever survives first contact
with the enemy,” and the leading armor units, including the
8th and 24th Armoured Brigades, found that the gaps in the minefields
had not been cleared. Thus their progress was stalled, and limited to
“bridgeheads” where they faced extremely strong
defenses. British armored units took a tremendous pounding, but thanks
in part to the 75 mm guns of the many M3 and M4 Mediums deployed, they
gave nearly as good as they got in a battle of attrition that the Axis
forces simply could not withstand. The
War Diaries of the 41st, 45th and 47th Battalions of the Royal Tank
Regiment
state that they suffered their first tank casualties on October 25,
1942, the
day after they were committed. An “Account of Operations 19th
to
the
29th October 1942,” written by Lt. Colonel J B Whitehead,
Commanding
Officer of the 41st RTR reports, “Just before sunset about
forty
German Mark
III and IV tanks attacked across the flank of 41 RTR. These were hotly
engaged
and several were soon in flames. Throughout the day our tanks were
subjected to
heavy artillery shelling from 105mm guns, which were numerous on our
front and
our first tank, 'Cocky', was knocked-out.” The photo above
shows
T-74267 "Bacchus", an M4A2 that was reported with the 47th RTR, "Battle
damaged, recovered & evac'd" in a 24th Armoured Brigade Tank
Casualty State of November, 1942.
The 24th Armoured Brigade reportedly
started the battle with 93 "Swallows." Counting heads suggests that a
little more than 60 of them in the 41st and 47th RTRs, along with 24th
AB Headquarters were M4A2s or Sherman IIIs. The Brigade was "used up"
after 5 days in combat. Towards the end, the 41st RTR "could muster
only eight," the 45th nine, and the 47th five running Shermans. The
Brigade was withdrawn from the front "for a rest and refit" on October
29th. In fact, this was the unit's first and last battle. On the 30th,
it's remaining Shermans and Crusaders were "handed over to Queen's
Bays, 9 Lancers, and 10 Hussars" of the 2nd Armoured Brigade, 1st
Armoured Division. The photos above were taken on November 10th by US
Army Major Paul Wickens as part of a Military Intelligence Report
"illustrating battle damage encurred (sic) by American tanks during the
recent Alamein Offensive." Wickens examined about a dozen M4A1s as well
as 2 M4A2s. "Many...were found about 9 miles South of the Rahman Mosque
in the exact positions in which they were knocked out." Others, such as
the M4A2 on the left had been removed to the "Rahman Collecting Point."
The Major was an Ordnance officer, and noted that the "3 50 mm hits on
turret" were not penetrations, whereas the hit on the left front
sponson was. We see no obvious clues that could identify the unit, or
if this was a Pullman or Fisher. It can be seen to have a 1-piece
differential housing. Wickens made no comments about the M4A2 seen on
the right, which appears to have been photo'd where it was KO'd. We
would guess that this example was built by Fisher, as the turret splash
appears to have the sharp angle (arrow) typical of the fabrications
used by them. The pressed metal road wheels (1) are not commonly seen
on the Alamein Shermans. The WD Number is not entirely readable, but
appears to be in the T-7430X range. We don't believe that the units of
the 24th Armoured Brigade ever got as far as the Rahman track, although
these two may have been former 24th AB M4A2s, perhaps provided to one
of the units of the 2nd Armoured Brigade as replacements?
The
IWM photo above is captioned "A tank crew during a moment of relaxation
in a tank battle," and is dated "29.10.42" [Oct. 29, 1942]. The cartoon
figure of "Capt. Reilly-Ffoul" no doubt caught the photographer's eye.
An article, "From Oldham to Alamein," by Ian Hudson, that appeared in
the Autumn 2020 issue of "Tracklink" identifies the crew as members of
Five Troop, B Squadron, 47th RTR, and the tank as "Blighty." The piece
is essentially a tribute to the young man seen in the lower right -
Trooper Frederick Keates, the "wireless operator and gun loader." The 3
Shermans of Five Troop were reportedly KO'd as they advanced south of
Kidney Ridge on October 27, 1942. A round penetrated the turret, killing
young Fred, and wounding the Commander, Lt. Bob Hiseman (with arms
akimbo in the photo), and the gunner Trooper Mackay (standing above
Fred). Note the trailing return roller arm just visible on the center
bogie. "Blighty" is proof that at least one the "Alamein" M4A2s was
equipped with M4 bogies. At present, we have not encountered any photos
of Alamein M4A1s with this feature. Sometimes the official captions can
be misleading, and sometimes the dates are incorrect. Researcher
John Taylor Firth has concluded that this photo "was actually taken
around the 21st October," that is, 3 days before the start of the Second
Battle of El Alamein. IWM E 18696.
It has been difficult to determine the exact appearance
of the Alamein M4A2s, since there is usually only one period photo of
any particular example, and details such as the glacis pattern are often
indistinct or obscured. We believe that
there is a surviving M4A2 that may have been one of the 90 M4A2s
received by the Brits as part of the "Special Shipment," or one of the
15 that was sent to the Middle East just before that as the first
regular Lend Lease shipment. All 105 of these arrived in Egypt at about
the same time in September, 1942. All would have to have been made
before mid July, 1942, when the convoys sailed. This M4A2 is on display
at the World War II Military Museum in El Alamein, and still has its original Pullman "1942"
dataplate, but, alas, the serial number is obscured, so we can't
determine exactly when it was produced. Nonetheless,
it has some very early features, such as the "indent" on the rearmost
engine deck panel, and 11 bolts across the upper rear hull plate. The
rear hull liftings rings are the earliest "bent rod" type, while the
ones on the glacis are the "padded" castings which quickly replaced
them. Pierre-Olivier
personally examined it, and despite some obscuration by the track
holders, determined that it has an unusual 7 section glacis pattern,
such as seen in a factory photo (inset) of a Pullman M4A2 with "134" stenciled
on the side. (We suspect that was the build number, and if so, it would
have been accepted in July, 1942.) The
tank was extensively rebuilt by cobbling at some point in 1943 or
later. However, we don't think this was one of the 535 M4A2s
remanufactured in the US in 1944, since they would have been installed
with the drivers' hood applique, a bow MG dust cover fitting, and the
"official" cast gun travel lock, not the fabricated one it currently
has. This leads us to theorize that this tank was rebuilt, perhaps more
than once, at British Workshops in the Middle East. A peek inside
by a visitor 25 years ago revealed armored ammunition racks and a skeletonized turret basket,
which, along with the applique armor on the hull sides indicates that it
received the full Quick Fix Modification. It currently has a “no pistol
port” turret, which didn't enter the production pipeline until the
Summer of 1943. The 3-piece differential housing would appear to be
appropriate, but it has a "lip" which was not introduced until late
1942. We suspect that this particular diff was taken from a Chrysler
M4A4, and the comb device it still has is typical of the type used by
Chester Tank Depot starting in late 1942. If this tank was built with M4
bogies, they would have been earlier than the ones currently on there
with the 1943 casting dates. In any case, despite all of the changes, an
M4A2 of this vintage certainly has a place at the El Alamein Museum.
The
British expressed disappointment that no further shipments of Shermans
would be available to the Middle East until the end of 1942. A Tank
State document for early January, 1943 has it that there were 136
"M4A1/M4A2...Serviceable with 8th Army." The doc may provide a clue
about the next shipment to the M.E when it records that an additional 65
had "arrived since 6 Jan," and that 105 were in transit. There is also
the note that 1237 "M4A1/M4A2" and 185 M4A4 had been allocated to the
M.E. up to 31.12.42. However, 241 of the "M4A1/M4A2" had been diverted,
and would go the British 1st Army (6th Armoured Division) which was then
in Tunisia. In fact, after the "special shipment" which included 264
M4A1s, all of the British Lend Lease allocations in 1942 were of M4A2s
(1111) or M4A4s (939) with the exception of one M4A3 sent to the UK for
evaluation. Thus we would conclude that all further allocations in the
"M4A1/M4A2" category would have been M4A2s. The British found the M4A2
to be greatly superior to the M4A1, noting that it had more power and
got better fuel mileage. The two photos above are part of a series dated
15 March, 1943, and entitled "Tanks arrive in Tripoli." After El
Alamein, the 8th Army pursued the retreating Afrika Korps, and captured
the major port of Tripoli on 23 January, 1943. These 3 Shermans appear
to have identical camouflage paint schemes. Most likely they were
processed for issue at a Base Shop in Egypt and then shipped the nearly
1300 miles to Tripoli. The tank in the background in the right side
photo has a WD Number that begins with T-145XXX. Counting heads suggests
that the range from about T-145219 through T-146142 was the next that
encompassed M4A2s exclusively. IWM E 22960 and E 22968.
The
6th (British) Armoured Division was assigned to support the Eastern
Task Force of Operation Torch. The Division's primary armored element
was the 26th Armoured Brigade, which deployed from the UK equipped with
British tanks, and landed in Algeria between 12th and 22nd November,
1942. Plans for the early capture of the ports of Tunis and Bizerte were
dashed when Axis troops were rushed into Tunisia from Italy, and the
campaign was stalemated for several months. The first Shermans from the
241 diverted from the Middle East appear to have arrived in Algeria in
February, 1943. They were hurriedly processed for issue, and shipped up
to the front in Tunisia. For a few days, 54 of them, described as "M4A2
diesel tanks," were loaned to the US 1st Armored Division to make up for
the enormous tank losses suffered during the Battle of Kasserine. These
formed a reserve, but their "use was unnecessary as the enemy was
defeated and withdrew to the east of Kasserine Pass." The tanks were
returned to the British on February 27th. The photo above is dated 24
February, 1943, the day the Axis began its general retreat, and is
captioned "Allied Troops Throw Back Germans on the Kasserine
Front...Sherman tanks moving up in the advance on Kasserine. Allied
Troops, Thala." Although not stated in the caption, we identify this as
an M4A2 of the 6th
(British) Armoured Division, 1st Army, due to the absence of the
extensive modifications carried out on 8th Army Shermans at Base Work
Shops in Egypt. Note
the cast shield protecting the .30 caliber coaxial machine gun. It was
introduced in the Fall of 1942, and included as On Vehicle Materiel on
tanks that were were scheduled for overseas shipment. At present, this
is the earliest dated "in theater" photo we know that shows the co-ax MG
shield. IWM NA 847.
This photo is dated 28 March, 1943
and is captioned "Sherman tanks and crews drawn up for inspection [...]
Sakiet Sidi Youssef. 6th Armd. Div." Some sources report that the
peculiar style of numbers seen on these tanks was typical of the
16th/5th (The Queen's Royal) Lancers, 26th Armoured Brigade. Period
photos of the 6th AD's M4A2s show a much plainer appearance than those
of the 8th Army, since they did not receive the Middle East
modifications before issue. The tank in the foreground can be seen with
a number of improvements, such as the elongated drivers' hoods that
eliminated direct vision. Also evident are fittings for the bow machine
gun dust cover, and the spot and signal light. The drive sprocket is
the "plain" type introduced in the Fall of 1942. The M4 bogies have the
half round track skids of the original design, while the next tank
features the improved "intermediate" skids. The cast shield
protecting the .30 caliber coaxial machine gun is visible on at least
the first 3 of these units. The lead tank is seen with MG and antenna
sockets with "sharp edges, indicating that they were fabrications not
castings. Pullman Standard appears to have used these fabrications
along with cast drivers hoods on the M4A2s it produced for a brief time
in late 1942 and early 1943. IWM NA 1574.
Hitler's
decision to reinforce Tunisia disrupted the goal of Operation Torch -
the capture of the ports of Tunis and Bizerte before the end of 1942.
However, it might be said that the Allied victory in May 1943 more than
made up for the delay. Hitler's "no retreat" obsession, coupled with the
growing strength of Allied Naval and Air power in the Mediterranean
set the stage for one of those rare occasions in warfare where the
entire enemy force was destroyed. A quarter of a million Axis troops
were captured, which rivaled in scope the Soviet victory at Stalingrad a
few months earlier. The Tank State of 5 May, 1943, about a week before the Axis surrender, indicates that
the 9th Corps of the British 1st Army had most of the Commonwealth's
operable Shermans. This included 82 in the 6th Armoured Division, and 75
in the 1st Amoured Division, which had fought at Alamein, and was
transferred from the 8th to the 1st Army in April. The Shermans are
described in the Tank State as "M4A4/M4A2," but we can find no evidence
of the presence of M4A4s in Tunisia at this time. It is thought that all
of the 6th AD's Shermans would have been M4A2s, while we believe that
the 1st AD would have had mostly M4A2s, but also a few of the special
shipment M4A1s, and 4 Grants to boot. The 8th Army was relegated to a
diversionary role towards the end of the campaign, and its 8th Armoured
Brigade is listed with 38 Shermans and 9 Grants, while the 22nd AB
reported 34 Shermans and 27 Grants. The total of serviceable Shermans in theater is listed as 265, with an additional 151 "unserviceable." The photo above is dated 14 May, 1943 (a day after the final surrender in Tunisia) and purports to show the "Meeting of First and Eighth Armies at Bou Ficha" [about 36 miles south of Tunis]. The Sherman, which we take to be the 1st Army representative, appears to be another example of a Pullman M4A2 with cast drivers' hoods, but fabricated bow MG and antenna sockets. IWM NA 2921.
M4A2s
have been difficult to study because most of them "disappeared" to Lend
Lease. Not many were used in tests in the US, where evaluation reports,
etc. often provide the Serial and/or USA Number and some photos, which
in many cases, enables us to gain insight into their appearance at a
particular time. Here we would like to pause and show a surviving
example of a Pullman M4A2, Serial Number 9882, that features cast
drivers' hoods, coupled with fabricated bow machine gun and antenna
sockets. According to author Paul Handel's "Australian Shermans" webpage,
"The tank arrived in Australia during mid 1943, and on arrival carried
both a US registration number (USA W 3096073) and a British registration
number (T 146142)." The "XXI in a diamond" shipping code, and the "as
built" appearance of the tank upon arrival, would lead us to conclude
that 3096073 was shipped directly to Australia from the US. The tank was
one of 3 Shermans used in trials in Australia, and, thankfully, this
one and an M4 Composite were preserved by the Australian Army Tank
Museum in Puckapunyal. USA 3096073 would have been accepted at Pullman
Standard in December, 1942. Note the distinct shape of the "narrow"
drivers' hood castings (1), and the sharp angles of the fabricated MG
(2) and antenna (3) sockets. We would assume that Pullman sourced the
fabrications from Fisher Body. Fisher M4A2s of this period used a number
of other fabricated components, such as the drivers' hoods, turret
splash guards, and head lamp sockets, while these parts are castings on
3096073. The DD at Bovington,
recently reported to be Serial Number 9992, has similar features.
Pierre-Olivier has seen an M4A2 displayed at the Citadel in Cairo,
Egypt, and a privately owned M4A2 with direct vision drivers' hoods.
Unfortunately, as
best we can determine, Pullman did not stamp the tank serial number
anywhere on the exterior of their Shermans, so their SNs remain unknown,
but we strongly suspect that these M4A2s are Pullmans since they also
have fabricated MG and antenna sockets. From
the available data, we would theorize that Pullman started production
using all cast components, and introduced the fabricated components,
perhaps mixed in, in the Fall of 1942, and then went back to using all
cast components in the Spring of 1943.
M4A2s or Sherman IIIs in Italy
For
the Invasion of Sicily (Operation Husky), the Eighth Army was equipped
exclusively with Shermans. The Tank States don't break them down by
type, but the evidence suggests that almost all of those that deployed
from North Africa were M4A2s. The 23rd Armoured Brigade had a paper
strength of 112 Shermans, 8 in the Brigade Headquarters, and 52 each in
the 46 and 50th Royal Tank Regiments. The numbers were the same for the
4th Armoured Brigade composed of the 3rd County of London Yeomanry and
the 44th Royal Tank Regiment. The 1st Canadian Tank Brigade was equipped
with M4A4s in the United Kingdom, and deployed from there with about
220 units. The IWM photo above is dated 10 July, 1943 (D-Day) with "51st
Highland Div." noted in the caption. That would tend to identify the
tank as with the 50th RTR, since they supported the 51st during the
landings. We would identify the M4A2 itself as an early Pullman by the
small bow machine gun casting with the "buttons" on the corners. Like
the "Special Shipment" Shermans, this tank lacks the bow MG dust cover
fitting and the little step between the drivers' hood, items that were
introduced in the Fall of 1942. The WE 210 “Double I” rubber block
tracks seen here had been ordered by the British for their Grant
program, and we doubt if these would have been original equipment on
this or any other Sherman. However, these tracks appear in period photos
on quite a few Shermans in Italy. In a November, 1943 “Policy re
Tracks” statement from GHQ Middle East, the WE 210 along with Rubber and
Steel Chevron tracks were classified as “Operational tracks...which can
be used in the European theater of war.” Other types, such as “Plain
Rubber” and “Cast Steel,” were classified as “Training tracks...which
can be used for training purposes in the Middle East and Turkey.” Thus,
it would seem that despite having slightly smaller dimensions than the
standard Sherman tracks, the WE 210s remained a preferred combat track
of the British. Courtesy of IWM, Photo NA 4197.
There
was some reluctance on the part of the Americans, but after Sicily,
the Western Allies again chose to postpone the opening of the second
front demanded by the Soviets (the invasion of France from England).
Prime Minister Winston Churchill argued that an attack on Italy would
knock them out of the war, and might present an opportunity to defeat
Germany through an indirect approach. In
any case, the British Eighth Army landed in Calabria on
September 3, 1943. Italy signed an armistice with the Allies on
September 8th. On
September 9th, the British 1st Airborne Division made
unopposed amphibious landings at the ports of Taranto and
Brindisi in south-eastern Italy. "Operation
Avalanche," in which British and US troops conducted an
amphibious assault at Salerno Bay commenced on the same
day. The
photo above is dated 9 September, 1943 and shows "a Sherman tank
on the main road BATTIPAGLIA ; 9th Bn. Royal Fus." The
40th Royal Tank Regiment provided armor support on D-Day. A few
period photos of Commonwealth Shermans show that salvaged turret
hatch halves were used to provide additional protection for the
driver's hood as seen here. Based on user feedback, the US produced a
series of modifications that became available in the Summer and Fall of
1943. One such mod was G104-W83, dated August 23, 1943 ..."To install
hatch guards for improving ballistic qualities of the armor plate in
front of driver's and assistant driver's hatches." As published, this
mod only applied to M4 and M4A3 Medium Tanks, but as quantities
increased, it was ordered installed on all applicable Shermans at
Depots, as well as those being remanufactured. This tank also
appears to have a step welded on to the differential housing in the
manner of the M10 Tank Destroyer. IWM NA 6646.
The
Commonwealth maintained a large presence at strategic points in the
Middle East. The area served as a training and/or rebuilding ground for
fighting units from all corners of the British Empire. The Italian
Campaign was not the "walk over" that some had thought it would be, and
"attrition" was much higher than expected. As the forces in the Middle
East completed their training/rebuilding, most were deployed to Italy to
replace combat losses, along with the loss of veteran units that were
ordered to the UK in anticipation of the Normandy Invasion. As of
September, 1944, M4A2s reportedly made up the largest number of Shermans
in Italy and North Africa at 1540, with the M4A4 coming in second at
1154. Some new types, such as the M4A1(76), M4(105) and "M4 17pdr" were
beginning to appear in small numbers. The British 1st Armoured Division
arrived in Italy in May, 1944, and in the September Tank State, was
listed with the greatest number of different Sherman types, including 33
M4A1(75)s, 45 M4A2(75)s, 75 M4A4s, 28 M4A1(76)s and 17 M4(105)s. The
6th Armoured Division, now part of the 8th Army, had a total of 215
M4A2s, along with 2 M4A1(76)s and 9 M4(105)s. The 2nd Warsaw Armoured
Brigade, whose history we will discuss below, is listed with 164 M4A2s
and nothing more. There were 548 "non-combat" M4A2s in "Stock, Workshops
and Training," along with 32 DDs, which some sources state were all
M4A2 based. The photo above dated 18 April, 1944, shows a mix of M4A2s
and M4A4s, and is captioned "long line of Sherman tanks in the armour
park. No. 1 Advance Base Workshops." This armor park was located on the
Corso Malta in Naples. According to their War Diary, No. 1 Advance Base
Workshops moved from Tripoli to Naples in October, 1943 after the huge
port was captured by the Allies. They were in competition with the US
Army and the US and Royal Navies for space, and it is recorded that it
took them about a month to find suitable locations for their workshops. IWM NA 14003.
The 2nd Warsaw Armoured Brigade is thought to have been the only Polish armored unit that was equipped with M4A2s. The Brigade was formed in 1943 in the Middle East as part of the Polish
II Corps. It was composed of the 4th
“Skorpion” Armoured Regiment, the 1st Krechowiecki Uhlan Regiment, the
6th “Children of Lwów” Armoured Regiment, and the 2nd Motorised
Independent Polish Commando Company. The “regiments” were actually
battalion sized, and each was initially equipped with
52 or 53 M4A2s. In early 1945, the Poles began to receive Fireflies and
M4(105)s as part of the updated British War Establishment for armored
regiments. The Brigade trained in Iraq, Palestine and Egypt, before
arriving in Italy in April, 1944. It entered combat
in May, 1944, during the 4th Battle of Monte Cassino. It also
participated in the Battles of Ancona (16 June to 18 July, 1944) and
Bologne (April, 1945). The Brigade finished the war in Loreto, and was
reorganized as the 2nd Warsaw Armoured Division in June,
1945, before being disbanded in 1946. The Brigade is reported to have
been issued “Operational Sherman IIIs...commencing 18 Oct 43.” It is
thought that they received approximately 160 M4A2s while stationed in
Palestine. The Shermans were a mix of 1942 production
models, including a few with M3 bogies, along with a number of units
produced up to the Spring of 1943, which included the later M34A1 Gun
Mounts. “Counting heads” suggests that the WD Numbers of these M4A2s
were scattered throughout the range from T-145383
through T-152588. We would note that we have not recorded any instances
of "T-Number overlap," leading us to believe that the Polish M4A2s were
new issues, not tanks that had been used previously by other units in
battles in North Africa, Sicily or Italy.
The Brigade's Shermans were photographed during maneuvers and
inspections in Egypt in early 1944. At that time, most or all of them
are seen with the “Swabey Sight” installed in the area of the original
factory blade sight. In Dec. 1943, it was decreed that
“The Sight will be issued to all units (Scale – 4 per Troop) and fitted
to all new Sherman Tanks in the Middle East...the Sight is not designed
as a precision instrument but as aid for the Commander to permit him to
get his first round on the ground as quickly
as possible in or near the Target Area.” The photo above left shows
"Taifun" of the Skorpion Regiment during a review in Egypt. It is one of
the more "up to date" M4A2s received as evidenced by the M34A1 gun
mount. To our eye, it appears to be a Spring, 1943
Pullman. The photo on the right shows "Taifun" during the 4th Battle of
Cassino in May, 1944. Note the addition of the “Quick Fix” Modification
applique plate (1) on the hull side. The Swabey Sight (2) can be be seen to good effect here. The
smoke dischargers (3) and the sunshield support frame (4) are other
Middle East modifications that appear on many of the
Polish Shermans. Both photos courtesy of National Digital Archive, Poland.
The finest hour of the Polish II
Corps came in May 1944, during the 4th Battle of Monte Cassino. The
tanks of the 2nd Warsaw Armoured Brigade struggled through the
relentlessly difficult mountain terrain in an effort to provide support
to the 5th Kresowa and 3rd Carpathian Infantry Divisions in their
costly but ultimately successful drive to break the German lines at
Cassino. One such tank was "Sułtan", T-145501 commanded by 2nd Lt.
Ludomir Białecki of the 3rd Squadron of the Skorpion
Regiment. Sappers had cleared a tank track, dubbed "The Cavendish
Road," during the failed 3rd Battle of Monte Cassino. It was reported
that on May 12, while attempting to navigate the narrow track, T-145501
veered into a pile of anti-tank mines that had been hastily removed to
the side of the road. This set off an explosive chain reaction which
utterly destroyed the tank and killed the entire crew. These were the
first combat fatalities suffered by the Skorpion Regiment, and in the
action from the 12th to the 18th of May, the unit recorded the loss of
5 officers and 8 enlisted men KIA, 8 officers and 27 enlisted men WIA,
with 3 Shermans totally destroyed and 8 damaged. Shortly after the
battle, it was decided to leave T-145501 in place, and in May 1946, the
tank became the basis for a monument to the 4th “Skorpion”
Armoured Regiment. In our view, it is one of the most unusual and
poignant tank monuments in the world. In the wartime photo above, there
are "still" a number of anti-tank mines on the ground. Before the
battle, many of the Polish Shermans had been outfitted with sandbags
and spare track "armor" as seen here. An antenna stub can be observed
installed on the antenna bracket (1), suggesting that T-145501 was a
command tank with an additional long-range radio mounted in the right
sponson in place of the usual ammunition rack there. The ventilator (2)
welded on to the turret roof appears to have been detached when the
turret was blown off. It can be seen that T-145501 was painted in the
two-tone desert camouflage scheme typical of most of the original M4A2s
received by the Poles. At the time of its destruction, "Sułtan" was
fitted with the WE 210 tracks (3) originally ordered by the British for
their Grant Medium Tanks.
A
front view of T-145501 photographed by Jim Goetz on a foggy morning.
(Records mention that visibility was poor on the morning of May 12, 1944
as the Skorpions' Shermans crawled up the Cavendish Road.) We can
confidently say that if anyone can locate the Ordnance Serial Number on a
surviving Sherman it would be Jim, along with our own Pierre-Olivier,
who has also visited this tank. However, the lower rear hull plate along
with the rear tow lugs were removed when the tank was set up as a
monument. Both Jim and P-O closely examined the front lugs, since in
some cases, the serial number has been found on those, but no luck. The
dataplate is long gone, although the frame that held it remains. Thus it
would seem that the serial number has been lost to time. So who made
this tank? Note that it has "the bump" (1) along with the filled in
holes for the fixed machine guns (2). As mentioned earlier, "the bump"
has been seen on a few early production Shermans made by Pullman,
Fisher, Ford and ALCO. An interesting anomaly seen on T-145501 is that
the weld seams (arrows) have been ground down, so that they would
disappear under a coat of paint. The only other surviving example we
have seen with ground down weld seams is the September, 1942 production
M4A2 Serial Number 1405, the very first Sherman made by ALCO.
This practice would have been strictly cosmetic, completely unnecessary
and wasteful of labor, so we had assumed it would have been very
limited. For instance, photos of the third ALCO, SN 1407, also accepted
in September, show the bump, but the weld seams stand proud of the
armor, as was obviously the case with almost every Sherman made. So
could T-145501 have been the second ALCO M4A2? Perhaps, but the machine
gun dust cover fitting (3) suggests that this tank was made in October,
1942 or later. Also, although not
readily apparent due to the presence of the spare tracks, this
Sherman has a 6 section glacis pattern, as shown in the inset. This is
the only surviving example we have encountered with this pattern.
In this unusual view of T-145501 again we see the
ground down weld seams (1). The front and rear hull lifting rings (2)
are the first type used on Shermans. For want a a better term, we refer
to them as "bent rods." In general, these were replaced in production
with "padded" lifting ring castings before the end of 1942. In turn, the
"paddeds" were then almost completely replaced with the "standard"
lifting rings by mid 1943. As with a number of early production M4A2s,
this tank can be seen to have had small "spacers" (3) welded to the rear
of the engine deck opening. This caused the rearmost engine deck to be
indented. The engine, along with the upper and lower rear hull plates,
were removed when this tank was set up as a monument. In a period photo,
T-145501 can be seen to have had 11 bolts running across the top of the
upper rear hull plate. Eventually, the number of bolts was reduced to
6, no doubt in order to provide crews with faster access when servicing
the engine. So far, the examination of surviving M4A2s reveals that
those with 11 bolts had the indented rear engine deck plates. Door stops
(4) are present in period photos on many of the M4A2s that
served in Italy. It is thought that these were retrofitted at Base Shops
in the Middle East when the tanks were processed for issue. This unit
has the remains of a small box (5) which is noted on a number the Polish
M4A2s (inset). We can only guess that it may have been a First Aid box?
In the book, Pułk 4. Pancerny "Skorpion", the author, Zbigniew Lalak, states that the Regiment’s LAD [Light Aid Detachment] “welded on their hull sides
additional armor plates strengthening ammunition containers protection.”
This was reportedly at Capriati, not long before the 2nd Warsaw
Armoured Brigade was committed to combat in May, 1944. We are somewhat
surprised at this, since we had assumed that the Quick Fix Modification
kits sent from the US would have been applied by Base Shops in the
Middle East before the tanks were shipped to Italy. After all, the job
was labor intensive, requiring 140 man hours according to the US, and
200 according to the British. In the view above left, the applique
plates (1) can be seen to have been welded on very professionally,
although the front plate is mounted several inches higher than what was
specified. We suspect that the LAD would not have had the time or
manpower to do the other two parts of the modification on the Regiment's
M4A2s - armoring the ammunition bins, and "skeletonizing" the turret
basket. Also seen here is the Chester Tank Depot style comb device (2).
The evidence suggests that CTD installed these on tanks processed for
overseas shipment beginning in November, 1942.
It was reported that 20000
Quick Fix Modification Kits were produced from July through September,
1943. The first order shipped overseas was 984 sets to Oran, Algeria
around the middle of July, 1943. This lot had been produced and/or
assembled by American Car and Foundry of Berwick, Pa. There is no
photographic evidence that these were universally applied to US Army
Shermans that would fight in Italy, the way they were to US Shermans in
the UK before D-Day. Since we have found no record that the British
received any FSMWO G104-W81 kits as Lend Lease, we would guess that
most of the US kits were passed on to the British Commonwealth. Around
mid 1944, it was reported that “Mideast Base Workshops completed
prototype conversions using stores received from America...At Wardian
[Egypt], 7 B.W. are in full production converting tanks at the rate of
15 a day. At Tel el Kebir [Egypt], 2 B.W. are doing 4 tanks a day at
present, and at Haifa [Palestine] 3 B.W. are about to start.”
Thus, it strikes us as odd that a Polish Light Aid Detachment
consisting of about 70 men, would be doing this entire modification in
the field in Italy in April/May, 1944. Looking for clues on T-145501 is
difficult since the inside of the fighting compartment is empty,
making it impossible to confirm the installation of 1/4 inch armor
plate on the original ammunition bins. The “skeletonization of
the turret” called for the removal of the perforated sheet metal
that surrounded the turret basket walls, along with the elimination of
the 12 unprotected ready rounds that were clipped on to the original
turret basket wall. The kit provided for an 8 round armored bin on
the turret basket floor at the foot of the loader. The Mideast Base
Workshops Report stated that "All conversions include the addition
of another layer of four rounds to the existing eight round ready bin
on the floor of the platform." In any case, a look at the turret of
T-145501 shows that there is a LOT of the mesh “still”
on the turret basket. While it looks like some mesh was
removed, it appears to have been shredded as a result of the explosions
that blew off the turret. Pierre-Olivier personally examined this
tank, and concluded that the turret basket was not
“skeletonized,” which leads us to theorize that the
Skorpions’ LAD unit simply welded on the kit supplied side
applique plates. As an aside, in the photo on the right, one can
see the base holders (arrow) of some of the original 75 mm ready rounds.
The
New Zealand 4th Armoured Brigade arrived in Italy in October 1943, and
fought until the end of hostilities, finishing the war in Trieste. The
brigade was composed of three regiments; the 18th, 19th and 20th, each
consisting of 52 Shermans. The Kiwis were predominantly equipped with
M4A2(75)s (or Sherman IIIs), although the regiments were also issued
Fireflies (both IC and VC) and M4(105) (or Sherman IB) Assault Guns as
they became available in 1945. The above shows a column of tanks of B
Squadron, 20th NZ Armoured Regiment, passing through San Giorgio di
Piano, approximately 15 km north of Bologna, on April 20, 1945. The
first two tanks can be identified as 1943 production Fisher built M4A2s
by the sharp angles of the fabricated drivers’ hoods, and the later
M34A1 gun mounts. Note that they are fitted with the unusual “Platypus
grousers,” a modification developed in the second half of 1944 by the
Mechanical Warfare Experimental Establishment in Italy. These were
applied to rubber tracks, and alternated with the Sherman’s standard
issue grousers. The Platypus grousers combined the functions of both the
standard grousers and the extended end connectors, providing extra
traction as well as lowering ground pressure, thereby increasing the
tank’s off road mobility particularly in muddy conditions. ("Rat
grousers" were similar, but designed to fit on steel tracks.) In a
report dated 9 Feb 1945, the Technical Staff went so far as to state
that "Platypus grousers...entirely revolutionize the performance of
Sherman in mud." In
any case, in 1945, a few Commonwealth units were supplied with Platypus
grousers in anticipation of the Spring Offensive. (Alexander Turnbull
Library DA-03839)
Some M4A2s in Italy were converted to "Kangaroo" Armored Personnel Carriers. Mediterranean
Area AFV Technical Report 27, dated 17 April 1945, explains that
"Towards the latter part of 1944 50 Shermans were converted to Infantry
Carriers by the removal of turrets and all interior storage fittings."
All told, 75 "Shermans III" [specifically] were reported to have been
converted from October, 1944 through April, 1945. The Sherman Kangaroo
had a driver and bow gunner, and could carry 10 infantrymen rather
uncomfortably, but in relative safety. They were organized into APC
Squadrons, one of which served as part of the 4th Queen's Own Hussars Regiment of the 9th Armoured Brigade. In
early April, 1945, at the beginning of the Spring offensive, the
Sherman Kangaroo Squadron was assigned to transport the 9th Infantry
Brigade of the 2nd New Zealand Infantry Division. Despite
some difficulties crossing ditches and canals, the Kangaroos enabled
elements of the Brigade to make a rapid advance to the Po river. This
photo is captioned "9 Infantry Brigade ready to go into action for the
first time. Men of 27 Battalion wait in Kangaroos before crossing the
Senio [River]." The leading Kangaroo can be seen with welded together
[fabricated] drivers' hoods, a feature exclusive to Fisher M4A2s.
M4A2s also served in Italy in another non standard configuration, as Duplex Drive "swimming tanks." The 7th Queen's Own Hussars was reportedly equipped with 54 DDs for the Spring, 1945 Offensive. The DDs had been fitted with Platypus Grousers, which were essentially "metal fins attached to tracks to give a better grip in deep going." For the crossing of the Po River on April 25th, A
Squadron was placed under command of 56th (London) Division, B Squadron
was assigned to the 8th Indian Division and C to the 6th Armoured
Division, with a troop of C detached to the 2nd New Zealand Division.
At present, the numbers of DDs that swam across successfully is not
known. On 28 April, 5
of the Duplex Drive Shermans that were still "sea worthy," were used in
an assault across the river Adige. The photo above is captioned "Members
of the New Zealand 5th Brigade attempting to float a Sherman DD tank
across the Po River." The tank can be seen to have Platypus grousers,
and to our eyes, appears to be bogged down in the mud of the riverbank. Photo courtesy of Alexander Turnbull Library.
The
wide "skirts" of the DDs, may have provided additional troop transport
capacity compared to a normal Sherman. It was reported that 17 DD
Shermans carried a company (100 to 150 men) of the 5/5
Mahratta Light Infantry, 8th Indian Division into Venice. The photo
above shows Two
Duplex Drive Shermans of the 7th Queen's Own Hussars photographed "in
the Piazzale Roma in Venice, 30 April 1945." After the Po and Adige
river crossings, Allied units sped north and east, and Venice was
liberated on 30 April, 1945. As with many DDs, the unit in the
foreground has its WD Number, T 151805, painted on the turret since it
would have been obscured in the usual locations on the hull. Note that
the suffix "DD" was added to the WD Number. Counting heads suggests that
the range from about T 150783 through T 154527 consisted of M4A2s
exclusively. In any case, the engine deck configuration
clearly identifies T 151805 as an M4A2. This tank can be seen to have
fabricated turret splash sections, including the rear turret splash
guard, features exclusive to Fisher M4A2s. Courtesy of IWM, Photo NA 24683.
M4A2s or Sherman IIIs in North West Europe
M4A4s made up the bulk of Commonwealth 75 mm Sherman gun tanks at the
start of the Campaign in Northwest Europe. At the end of June 1944, the
21st Army Group reported that they had 762 M4A4s, compared with 391
M4s/M4A1s, and 316 M4A2s. The units listed with M4A2s (Sherman
IIIs) were the 2nd Canadian and the British 8th and 27th Armoured
Brigades. The US Coast Guard photo above shows a Sherman III
unloading "onto a "Rhino" barge during the early hours of the invasion
on Gold Beach, 6 June 1944." This tank was named "Virgin," and can be
seen as T-147013. The combined fox face and "993" formation and Arm of
Service marking identify this as a tank of the 8th Armoured Brigade's
Headquarters. "Virgin" has elongated, cast driver's hoods, but a
fabricated antenna bracket, a configuration that appears very briefly
on Pullman M4A2s produced in late 1942/early '43. This tank appears to
be unmodified or "as built," except perhaps for the addition of sand
shield strips. An antenna fitting can be seen on the antenna bracket on
the glacis, suggesting that this is a command tank in which the
ammunition stowage on the right sponson has been removed and replaced
with an additional radio.
The
photo above is captioned, "Sherman tank crews of C Squadron, 13th/18th
Royal Hussars prepare their vehicles for the invasion, 30 May 1944."
Note the Seahorse (a.k.a. "Pregnant Pilchard") formation marking of the
27th AB on the closest tank. Unlike the 8th AB M4A2 in the previous
caption, these tanks have been retrofitted with the "Quick Fix"
Modification as evidenced by the applique armor on the hull sides. These
are 1942 or early 1943 production M4A2s with M34 gun mounts. Most US
Army Shermans in the UK before D-Day had these mounts replaced where
necessary with M34A1 gun mounts with telescopic sights. Unfortunately,
supplies were limited, and it is obvious that many Commonwealth Shermans
of the Normandy Campaign fought with the original gun mounts. Evidence
suggests that large numbers of the Lend Lease M4A2s sat around for
months in the US before being processed and shipped to the UK, in some
cases, nearly a year after they had been built. We believe that the
Quick Fix Mod, which became available to US Tank Depots in the Fall of
1943, was applied to many of the Commonwealth Shermans before shipment.
The "Sloping Armor ahead of Drivers' Hatches" mod became available at
about the same time as the "Quick Fix," but, at first, only applied
to M4 and M4A3 Shermans. Thus, it is fairly common to see combat photos
of Allied M4A2s with the Quick Fix applique, but not the hatch guard
plates. A modification kit was also provided to replace the original
blade sight with a "commander's vane sight." These tanks can be seen
with both types, although the newer sights appear to be British
versions, not the ones from the US mod kit. Courtesy of the Imperial
War Museum, Photo H38970.
Although
3 Commonwealth Armoured Brigades were substantially equipped with
M4A2s, it was not possible for them to be entirely equipped with diesel
Shermans. As an example, the 27th Armoured Brigade is listed as having
had 126 Sherman III gun tanks, 8 Sherman III OP (Observation Post)
Tanks, and 9 Sherman III ARVs (Armoured Recovery Vehicles). The 27th,
along with the 8th and 2nd Canadian Armoured Brigades, were assigned to
the initial landings at Normandy, and were supplied with Duplex Drive
swimming Shermans for the first wave. Although some M4A2s were converted
to DDs, none were available in time for D-Day. Consequently, the 8th
Armoured Brigade was equipped with 76 US converted M4A1 or Sherman II
DDs, while the 27th and 2nd Canadian ABs had respectively 38 and 76
British converted M4A4 or Sherman V DDs. It would appear that a
Commonwealth Brigade was authorized 11 ARVs. To bring them up to "War
Establishment" strength, each of these Brigades was assigned 2 Sherman V
ARVs in addition to their 9 Sherman III ARVs. The 21st Army Group
listed 316 Sherman VC (M4A4 Firefly conversions) and 2 Sherman IC (M4
conversions) at the end of June, 1944. In
general, these appear to have been issued to Commonwealth Armoured
Regiments on the basis of one per Troop (commonly 3 tanks). The 8th and 2nd
Canadian Armoured Brigades are reported to have had 22 Sherman VC, while
the 27th AB had 29. So each of these Brigades required two different
kinds of fuel, and had to maintain 2 different engine types, or 3 in the
case of the 8th AB with its Sherman II DDs. The
caption of the photo above is "Sherman V Armoured Recovery Vehicle
(ARV) Mk. I, Authie, Normandy, France July 1944." In fact, the "narrow"
drivers' hood castings, and the shape of the antenna bracket identify this
as a Sherman III ARV in a configuration seen on many Pullman and
Federal Machine M4A2s. We believe this vehicle served with the 27th Armoured Regiment (Sherbrooke Fusiliers) of the 2nd Canadian Armoured Brigade, since they liberated Authie at that time. Photos
of Sherman III ARVs are rare as only 29 conversions had been completed
by the end of May, 1945, compared with 189 Sherman V and 169 Churchill
conversions. (Library and Archives Canada Photo, PA116535)
The 27th
Armoured Brigade suffered heavy losses during its 50 days in Normandy,
and was disbanded in late July, 1944. As was the case with a number of
British formations throughout the war, the 27th's regiments were used to
reinforce other depleted Brigades or Divisions. For example, the 13/18th Hussars were reassigned to the 8th Armoured Brigade. From that point on, in the ETO, British M4A2 gun tanks appear to have been consolidated exclusively in the 8th AB. The Staffordshire Yeomanry was transferred from the 27 AB to the 79th Armoured Division (Hobart's Funnies), and took up DD training in the UK. The 1st East Riding Yeomanry joined the 33rd Armoured Brigade in August, 1944, and took over the radial Shermans of
the 148th Regiment, RAC, which was itself disbanded at that time. The
photo above is dated 15 October, 1944 at Nijmegen, and is captioned in
part, "A British tank (of the 13/18 Hussars 8th Armoured Bde.) keeps
watch on the river bank." This tank can be seen to have the name "TWELFTH KNIGHT" painted on above the applique plate. It can be identified as a Sherman III by the configuration of the engine deck, and the absence of air scoops on the rear hull. The antenna mounted on the bracket on the glacis would indicate a command or observation post tank. Courtesy of the Imperial
War Museum, Photo B 10996.
One
of the Canadian Sherman IIIs that landed on D-Day was "Holy Roller,"
CT-152655. Of all of their Shermans, the 1st Hussars chose this tank to
be returned to Canada as a "War Trophy." "For it's the only tank in the
regiment to outlast the war, the only one to come ashore on D-Day, travel
some 2,500 miles, fight through 14 major battles and still be in
business on V-E day, its hull still unpierced, its 75 mm. gun still
firing." In 1950, "Holy Roller" was placed on display as a War Memorial
in Victoria Park in London, Ontario, home base of the 1st Hussars. Like
most Commonwealth independent Armoured Brigades, the 2nd Canadian AB
included three Armoured Regiments - the 6th Canadian (1st Hussars), the
10th Canadian (The Fort Garry Horse) and the 27th Canadian (The
Sherbrooke Fusiliers). On paper, these Regiments were organized into 3
Squadrons, with each Squadron having 19 Shermans. The Squadron
Headquarters was equipped with 4 Shermans, and commanded 5 Troops, each
equipped with 3 Shermans. In some cases, attrition in men and machines,
led to the number of Troops in a Squadron being reduced to 4. We have
personally examined "Holy Roller," and recorded the Serial Number from
the rear towing lugs as 7606, indicating September, 1942 production by
Fisher Body. One might speculate that an early production M4A2 like this
might have been shipped to North Africa originally, but the evidence
shows that that was not the case. Of note is the combat damage on this
veteran Sherman. Photo courtesy of Scott Taylor.
The snapshot above was taken in May,
1944, and shows CT 152655 at Lee-on-the-Solent, near Portsmouth, UK. By
this time, the tank had been waterproofed and installed with wading
stacks in anticipation of D-Day. Initially, Holy Roller was the tank of
Major Frank Wright, 2nd in Command of the 1st Hussars, who reported
that they landed at Courseulles on D-Day, "and got 7 miles inland
before a broken oil line stalled her." In less than a week, the 1st
Hussars lost 63 tanks, and Holy Roller was reassigned to the
Commanding Officer of B Squadron. It is thought that HR served in B
Squadron for the rest of the Campaign. As with many Commonwealth
tanks, HR had spare tracks welded on to the glacis, and these are
credited with saving her from direct hits on 3 separate occasions. The
M3 bogies seen in the snapshot are of particular interest, since they
rarely appear in photos of Shermans in Northwest Europe. It is assumed
that Holy Roller retained the early bogies until April, 1945, when,
according to a newspaper account by Burke Martin, "at Apeldoorn another
88 hit stripped her track suspensions. Tanks have been abandoned for
less, but Holy Roller was a legend by now and had to be saved. Six new
suspensions...were laboriously fitted on and the tank lumbered
away to the last scrap in Germany." At present HR has M4 bogies, some
of which have 1-43 and 2-43 production dates cast on them, which are
obviously not original to a Sherman accepted in September,
1942. The rubber chevron tracks seen in the snapshot also appear
to have been replaced with plain rubber block tracks.
Another
Canadian "national treasure" is "Bomb," which also served from D-Day to
V.E. Day, but with the 27th Canadian Armoured Regiment (The Sherbrooke
Fusiliers). It is currently on display in Sherbrooke, Quebec Province.
"Bomb" is CT-152656, the next number after Holy Roller's CT-152655. Both
of these tanks appear to have the remnants of the Lima Tank Depot type
of comb device. We suspect that both were processed and modified there
at around the same time in late 1943, and may have been shipped to the
UK on the same boat. Our theory is that these tanks sat around in the US for many months before being dispatched. "Bomb"
is serial number 8007, indicating that it was accepted at Fisher Body
in November, 1942, two months after HR. Counting heads suggests that
starting in June, 1942, Fisher M4A2s began to take on a consistent
appearance characterized by the use fabricated components such as the
antenna (1), machine gun (2) and head light sockets (3). Differing from
the castings used by the other Sherman producers, the turret splash was
assembled entirely of fabricated sections. The glacis shown here is
composed of 6 parts, but shortly thereafter, Fisher introduced a single
plate into which the the drivers' hoods, antenna and bow MG components
were welded. Evidence suggests that, in November, 1942, Fisher
transitioned from the direct vision drivers' hood castings seen here to
their very distinct elongated drivers' hoods that were welded together,
i.e. fabrications. These appear to have been used exclusively by Fisher.
General Motors' Buick Division produced M4 Power Trains, all of which
had 1-piece differential housings. As a result, except for a handful of
the earliest units, Fisher M4A2s are consistently seen with E4186
1-piece diffs. These were replaced in production with the "final," sharp
nosed E8543 housings starting around July, 1943.
Holy
Roller was probably one of the last Fisher M4A2s to have been built
with M3 bogies. Bomb appears to have survived with its original M4
bogies intact (although a number of road wheels were replaced). Note the
original configuration of the swing arms (1) without the wrench holes.
The tracks skids (2) are the second type, sometimes called "asymmetric."
The return roller arm (3) is straight and it can be noted that no
spacers (4) were ever added to raise the return rollers up an inch or
so, although modification kits were made and widely distributed. For
reasons unknown, Fisher continued to mount the turret lifting rings in
the original "high" position (5) into 1943, long after the other
builders had transitioned to the low position. Another item that Fisher
fabricated was the 2nd antenna base on the turret as shown in the inset
on Holly Roller. Other builders used forged or cast parts, but Fisher
continued to use this small assembly to the end of M4A3(75) production
in March, 1945.
For
the Overlord Invasion, the Royal Electrical and Mechanical Engineers
(REME) were called upon to provide Beach Recovery Sections whose primary
function would be to clear the beaches as quickly as possible, so that
follow up troops could disembark unimpeded, and maintain the forward
momentum of the attack. One of the specialized vehicles created for the
job was the Sherman BARV, which was designed to tow or push stuck or
broken down tanks and trucks and such out of the surf and on to the
beach. BARVs could push grounded landing craft back out to sea as well.
For this role, the M4A2 appears to have been chosen specifically,
because it was thought that its diesel engine would better handle the
temperature variations due to the tank going in and out of the sea. The
M4A2's turret was removed, and a boat like upper superstructure was
welded onto to the hull. The hull was thoroughly waterproofed and
provided with exhaust stacks, so that it was capable of wading in water
up to 9 feet (2.7 meters) deep. The BARV's crew consisted of 5 men - a
commander, a driver, 2 mechanics and a diver. The diver's primary task
was to hook tow cables to submerged tanks and other stranded vehicles.
We have not found any archival documentation, but an internet source
reports that "An order was placed for 50 BARVs, later raised to 66," and
"Around 52 BARVs were deployed on D-Day." The photo above is captioned,
"a Beach Armoured Recovery Vehicle recovering a Bedford Articulated
vehicle from a Normandy Beach" and is dated 14 June, 1944. Note the
large wooden bumper affixed to the front of the BARV. Courtesy of IWM, Photo B 5578.
As
of today, there are 5 known surviving BARVs; 4 are preserved in museums
or private collections in the UK and India. The 5th was removed from a
target range, and was seen in storage at the Tank Museum, Bovington in
2012. The photo above shows the BARV on display at the REME Museum in
Lyneham, UK. It is thought that all of the BARV conversions were painted
gray as seen here. This M4A2 was built with the later, elongated
drivers' hood castings. The drivers' hatches and periscopes were
removed, and the holes blanked off, since the hoods were partly covered
over by the addition of the bow superstructure. Ironically, direct
vision was retrofitted to the front of the hood castings in the form of
rectangular, glassed in "port holes." Thus, the driver's vision was
extremely limited, and the commander, positioned in a hatch on top of
the superstructure, navigated the vehicle by transmitting instructions
to the driver. The glacis configuration, with the "narrow" drivers'
hoods, the particular type of cast antenna bracket mounted "proud" of
the glacis, and the rectangular, cast "plate" with the bow machine gun
socket, are typical of M4A2s built by Federal Machine and Pullman
Standard starting in the Spring of 1943. As
best we have been able to determine, Pullman did not stamp the Serial
Number on the towing lugs or anywhere else on the exterior of its
Shermans. However, in 2023, the Museum staff sent us a photo of the
tank's dataplate confirming that it was produced by Pullman and is
Serial Number 13895. By our working theory of Pullman Production Orders, SN 13895 would have been accepted in April 1943.
The
US Army used a small number of M4A2s in combat. On December 26, 1944,
the US 12th Army Group sent an urgent communication to the British 21st
Army Group “requesting immediate release of 500 tanks” to provide
replacements for losses suffered during the Battle of the Bulge.
Commonwealth Vehicle Parks were scoured, and by the first week of
January, 1945, a total of 351 Shermans had been transferred. The
transfers are reported to have consisted of 254 radial engined Shermans
"I/II," including 87 "Sherman IIA 76mm" [M4A1(76)s], along with 44
Sherman III [M4A2] and 53 Sherman V [M4A4]. These latter types were not
sanctioned for combat use by the US, and the Third Army ordered that the
M4A4s "should not be used except in case of an emergency"...and should
be dropped from the pool when standard type replacements brought the
reserve pool up to 25 per cent." We found no similar order regarding the
M4A2s, but photos, such as those above, show that some were used in
combat. The tactical markings painted on this Fisher built, direct
vision M4A2 show that it was "B-15" of the 31st Tank Battalion, 7th
Armored Division. Several features identify this as one of the 535 M4A2s
remanufactured in the US in 1944. Note the full suite of applique armor
to the hull sides, drivers' hatches and turret. The turret with "high"
lifting rings is typical of 1942 Fisher production, suggesting that the
M34A1 gun mount was retrofitted. The rear photo shows the Barber-Colman
type exhaust deflector, which the evidence indicates was introduced on
new M4A2 production at Fisher on 1 January, 1944, and was a modification
listed in the remanufacture program. This tank looks pretty new, and we
suspect that it was never issued to a Commonwealth unit, although the
spare track holders, first aid box on the right rear, and the footman
loops on the turret were no doubt added by the British when it was made
ready for issue. B-15 was probably a recent issue, since it was not
whitewashed with calcimine, as had been ordered for all of the
Battalion's vehicles during the second week of January as the unit
enjoyed a brief respite for rest and refit. It is thought that this
scene was filmed during the third week of January when the Battalion was
part of a task force that recaptured St. Vith. The heroic
delaying action of the 7th Armored Division in the St. Vith area from
17-23 December 1944, so disrupted the German timetable that it is cited
as one of the primary reasons for the failure of the Ardennes Offensive.
Some
M4A2 based
Duplex Drive Shermans were used for the Rhine and Elbe
River crossings in March and April, 1945. As of 13 March, 1945, the
44 RTR, 4th Armoured Brigade and the
Staffordshire Yeomanry, now part of the 33th AB, are
listed with a few Sherman III DDs, along with the more
numerous Sherman V DDs. Also for the Rhine crossing, C Company of
the US 736th Tank Battalion, as well as the US 748th Tank
Battalion were equipped with DDs, some from British stocks, and
some of which may have been M4A2s. The photo above
is captioned "Sherman DD tanks with flotation screens
lowered move forward during the Rhine crossing, 24 March
1945". The
"Black Rats" insignia painted on the differential of the
center tank would tend to identify these as DDs of the 44th
RTR. The
center DD appears to be M4A4 based, while the one partially visible
in the foreground would be an M4A2 judging by the proximity of the
road wheels. Courtesy of IWM, Photo BU 2148.
293 of the British Duplex Drive conversions were based on the M4A2 or Sherman III. The
design of the Sherman III DD was delayed somewhat, and the 21st Army
Group Tank State for June 1944 does not list any on strength, but rather
189 Sherman V DDs, along with 76 Sherman II DDs (the US M4A1
conversions). At present, we aren’t aware of any photos of Sherman III
DDs “in action” before 1945. The unit preserved at the Tank Museum at Bovington is
the only surviving DD with its original floatation screen intact. In
2021, a correspondent reported that a member of the staff looked inside
at the dataplate, and found that the tank was produced by the Pullman
Standard Car Co, and that the Serial Number is 9992. Like Serial Number
9882 in Australia featured earlier, it was accepted in December, 1942,
and has cast drivers' hoods (1), along
with fabricated antenna (2) and bow machine gun sockets (3), features
noted on some Pullman M4A2s produced in late 1942/early 1943. As a DD, this
example has several improvements introduced in late 1944/early 1945 as a
result of user experience with the original DD design. In order to
prevent the raised screen from collapsing in rough seas, the struts were
strengthened and made self locking, turret struts were added, and the
rear screen was raised. Left side photo courtesy of "Megashorts".
M4A2s in USMC service
According to author Romain Cansiere, the US
Marine Corps' original decision to use the M4A2(75) as its Main Battle
Tank had nothing to do with diesel fuel. Rather, the type was "the first
one the Corps could obtain quickly in large numbers" from the limited
supply of Medium Tanks available in late 1942, early 1943. Furthermore,
we suspect that requisitions may have stipulated Fisher built M4A2(75)s
exclusively, as we have yet to see a photo of a USMC M4A2 produced by
another manufacturer. They are stated to have received a total of 493
units. Since no official distinction was made between the small and
large hatch models, it has not been possible to determine the exact
number of small hatch M4A2s they received. At present, our guess is
around 300. November 20, 1943 marked the Sherman's combat debut with the
USMC when the 14 M4A2s of Company C, 1st Tank Battalion attempted to
land on Tarawa in support of the 2nd Marine
Division. The tanks had not been outfitted with fording equipment, and
many were drowned when they fell into underwater craters. Others were
disabled when their electronics were ruined as sea water flooded in. As a
consequence, only 5 of the M4A2s were operational at the end of D-Day.
Nonetheless, the survivors provided indispensable support to the
Marines. When the island was declared secure on November 23rd, China Gal
and Colorado were the only Shermans still operational. The photo above
shows "Condor" of the 3rd Platoon, which was reported to have been
disabled on D-Day by a Japanese 75mm gun. A close examination of the
photo reveals that Condor had USA 3035025 stenciled on the front side in
blue drab. This indicates May, 1943 acceptance. Reports have it that
Company C received new M4A2s just before they shipped out of San Diego
in July, 1943, and photos suggest that all had the same features as
Condor, such as, for instance, M34A1 gun mounts. Common mid 1943
modifications like the "Quick Fix" ammunition protection, or positive
hatch lock mechanisms are notably absent.
Our
Canadian friend, Jim Goetz has a "bucket list" goal of visiting every
surviving Sherman tank in the world. He had to take a number of
"trains, planes and automobiles" to get to Guadalcanal to see the M4A2
shown above. Jim reported that the Serial Number is 26908, indicating
July, 1943 acceptance. Counting heads leads us to conclude that Fisher
introduced power trains with the "final," sharp nosed E8543
differential housings (1) during that month. The turret has what we
believe is a factory installation of the the thickened cheek armor (2)
and a welded up pistol port (3). These two mods generally went hand in
hand at factory or Tank Depot, until the supply of such turrets was
exhausted, and replaced with new castings made without pistol ports,
and with cast in thickened cheeks. The side applique plates(4), part of
the "Quick Fix" modification were probably installed by a USMC Ordnance
unit from kits provided by the Army. The Battle of Guadalcanal, one of
the most interesting campaigns of WW II, took place from August 1942 to
February 1943. The Marines were equipped with a few M2A4 and M3 Light
Tanks, but no Shermans. Indeed, SN 26908 had not even been built when
the island was secured. Perhaps the garrison stationed there afterwards
requested a range target? The name "Jezebel" is faintly visible on the
right front applique plate, and we would observe that an M4A2 named
"Jezebel" served with the 4th Marine Tank Battalion during the
Roi-Namur Campaign in February, 1944.
We estimate that the USMC received
about 200 large hatch M4A2(75)s as they became available in late
1943. Of these, 12 were converted to M32B2 Tank Recovery
Vehicles. It is thought that the large hatch M4A2(75) made its
combat debut with the Marine Corps in June, 1944 at Saipan. Photos show
them serving there alongside small hatch M4A2s with both the 2nd and
4th Marine Tank Battalions. After Tarawa, the USMC "got religion" when
it came to waterproofing their tanks. In some cases, the Marines
fashioned their own wading trunk designs, but the unit shown above
appears to have been equipped with the "official" version, made
available in kit form in early 1944. Preparing a Sherman for deep water
fording was a laborious undertaking. According to the Technical Manual,
if the job was done properly, the tank would be able to operate in
water up to 6 feet for all of 8 minutes. This
Sherman named Gremlin IV of the 3rd Platoon of B Co.,4th Tank
Battalion appears to have fallen into a shell hole in the surf, which
drowned out the engines. Marine large hatch M4A2s and M4A3s can be
difficult to distinguish, but the M4A2s were "dry stowage," and a bit
of the factory installed side applique plate (circled in red) can be
seen here. The M4A3s were not equipped with the applique plates, since
they were "Wet Stowage" tanks in which the ammunition bins had been
repositioned to the floor of the vehicle.
By 1945 the USMC had started to
transition from the diesel M4A2 to the gasoline powered M4A3. Of the
three USMC Tank Battalions that took part in the Iwo Jima Campaign, the
3rd TB retained their M4A2s, while the 4th and 5th both fielded M4A3s.
For Operation Iceberg, the landings on Okinawa and Ie Shima, the 1st and
2nd TBs continued with M4A2s while the 6th used M4A3s. It
had been planned to totally re-equip Marine armor units with M4A3s for
Operations Olympic and Coronet, the invasion of the Japanese homelands.
However, after the surrender of Japan, some USMC M4A2s did soldier on
during occupation duty in China which could be considered the last use
of the diesel Shermans with US forces. By the time of the Korean War the
only Shermans the Marines were using were M4A3s. USMC
102632 is believed to have served Occupation Duty with the 1st Marine
Tank Battalion, and was photographed in Tianjin in May, 1946, during a parade. As
best we can determine, none of the large hatch M4A2s were built with
the commander's all round vision cupola (1) or the T-shaped towing
shackles (2), so these would have been retrofits.
Soviet
M4A2s
According to US
records, the Soviets were allocated 1103 M3 Lees as part of the First
Lend Lease Protocol. These were scheduled for delivery starting November
1941 and ending in June 1942. Needless to say, the Soviets were not
impressed with the design. Even so, as best we can determine, they
ordered an additional 278 M3 Lees under the 2nd Lend Lease Protocol
which ran from July 1942 to June 1943. The 2nd Protocol also included a
small order for 219 M4A2s and 2 M4A4s. Production planning in the US
assumed that the Soviets would have ordered up to 2000 M4A2s under the
2nd Protocol, but based on their experience with the Lee, they seem to
have held back. In any case, the M4A2s would have been very early models
as they were allocated in September 1942. It is noted that 8 of them
were "repossessed" before shipment. The first 26 are reported to have
arrived "at a northern port of entry" in November 1942. After that the
pace of receptions can only be described as “glacial.” In the event,
further shipments amounting to a total of 211 arrived before the end of
the first half of 1943. After January, most came in via the more
indirect and circuitous "Southern route" through the port of
Khorramshahr in Iran. This was due to the arctic weather and the danger
to the convoys posed by the "U-Boat menace" on the "Northern route." One
of the first 26 M4A2s was sent to the Soviet Armor Center at Kubinka
for evaluation. This unit was reported as USA 3021079, indicating Fisher
Body, August 1942 production. It is thought that by August, Fisher
M4A2s had taken on a consistent appearance typified by the use of
1-piece differential housings, fabricated, not cast, antenna, bow
machine gun and turret splash components, and use of the rather large
siren seen here, which was made by the Mars Signal Light Company. The
early M4A2s suffered from a number of teething problems, but all in all,
the months long Kubinka evaluation, as reported by author Yuri
Pasholok, gave 3021079, "very high marks. The American combat vehicle
was not much inferior to the T-34, [and] surpassed it in some respects."
On November 17, 1942, an American civilian technician named Michael
Ikonomou visited Molotovsk where he examined the first 26 M4A2s, which
were waiting to be off loaded from the Liberty Ship John Walker. He
noted, "One Medium Tank M4A2...was also observed with an all steel track
T-49; all other tanks observed had rubber tracks T-41." USA 3021079 can
be seen above with the recently designed T-49 type, a cast steel track
with "interrupted parallel grousers." Pasholok reports that the tank was
run at Kubinka with T41 rubber tracks with and without grousers
installed, as well as the T-49 steel tracks. "In general, tests have
shown that both types of off-road tracks give the same result."
The
Tank Section of the American Supply Mission to the USSR was "charged
with
making the Lend Lease tank program effective." However, its efforts
were
severely limited since, as of February 1943, it consisted of only one
officer,
Col. Edward Grey, and three civilian technicians. A training school was
established at the Gorky Reception Center for Foreign Vehicles, but
"lack
of adequate assistance...in many cases has resulted in premature
failure of the
equipment in Red Army hands...these difficulties have resulted in a
lack of
appreciation of the value of American tank equipment, and doubt in the
minds of
officials of the Soviet Government as to the ability of the United
States to
make the tank section of the Lend Lease program effective." The US
techs
found that many of the first lot of 26 M4A2s were plagued with flaws
including
burnt injectors and leaking radiators. At least 8 had engine problems
"requiring major overhaul operations." The serial numbers of 25 of
these units were recorded, along with a description of the problems
encountered. The serial numbers run from 2320 to 2583, indicating that
all were
produced by Fisher Body from May through August, 1942. In the mean
time,
Detroit Diesel and the Ordnance Department continued work to improve
the
original twin engine design, and released field modifications
of the
cooling systems and air cleaners for M4A2s produced up to October,
1942. The
tank section appears to have received the cooling system modification
from the
US in January, 1943, since they reported that they began installing it
at that
time. President Roosevelt was determined to provide effective Lend
Lease to the
Soviets, and eventually the tank section was adequately supported with
men and
materiel. The Americans did not record the serial number of the Kubinka
Test
tank, but USA 3021079 corresponds to SN 2572. This unit can be seen in
the photo above with M4 bogies with the second type of track skid. It is
thought that Fisher completed the transition to M4 bogies by the end of
September. The technicians' reports don't mention M3 bogies, but
despite the absence of photos, we can't help but think that a number of
the early production M4A2s received by the Soviets would have had them.
One of
the M4A2s that was was serviced at Gorky in January, 1943 was SN 2428.
After
only 100 miles, it "was brought into the shop with one bad engine and
the
clutches out of adjustment." (Maintenance of clutch alignment on the
twin
diesel power pack was an absolutely essential skill for crews and
mechanics to
learn in order to keep the M4A2 running smoothly.) There is no mention
in the
Gorky shop files of anything unusual about the tank's differential
housing.
However, SN 2428 (July, 1942) is listed along with SN 2493 (August,
1942) as
having had "combination welded and cast differential and final drive
assemblies." These were prototypes to be tested at Aberdeen Proving
Ground, with the idea that the welded/cast design might save some
foundry casting
capacity, which was stretched to the limit at the time. As it was, only
2493
was evaluated at APG, and the welded/cast differential project was
shelved as
it offered no significant benefit over the standard cast assembly. SN
2428
never made it to APG. The tank, with its expensive prototype
differential, was
reported "shipped by error August 20, 1942 to the Russians" by Army
Field Service officials at the Toledo Tank Depot. From this we assume
that the
first lot of 26 M4A2s was processed at TTD, and likely sailed on the SS
John
Walker a week or two later. The photo on the left provides a view of
the
welded/cast differential housing on SN 2493 at APG on September 1,
1942. We
must conclude that the photo on the right, taken at the Fisher Tank
Arsenal in
July, shows SN 2428 since a comparison of the casting marks on the gun
shields
(circled) shows an obvious difference.
The
Sherman’s combat debut with the Soviets appears to have
occurred in early May,
1943. The 5th Guards Tank Brigade, which was reportedly equipped with
18 M4A2s
and 17 Lend Lease Valentines, was employed as part of an unsuccessful
Soviet
offensive on the North Caucasus Front. The 5th GTB fought in a month
long
series of actions around the village of Krymskaya (now the city of
Krymsk) in
the Krasnodar Krai, in southern Russia. The unit suffered heavy
losses, mainly due
to
mines and artillery. However, the 5th GTB records note the heroic
efforts of
its “tankists,” who were able to evacuate and
repair quite a few of their
vehicles.By June 6,
attrition had ground down the 5th GTB to only 3 serviceable M4A2s and 8
Valentines, and it was withdrawn from the front, and placed in reserve
for rebuilding.
Starting in late July, the 5th GTB
received a number of T-34s
to replace its losses. It
then participated in a further series of actions
in the same area until being placed in reserve in early December, at
which
point it handed over what is assumed to have been its 6 remaining M4A2s
to the
257th Tank Regiment. When asked to comment on the Sherman’s
performance, a 5th
GTB Report noted, “Compared
to the T-34, the M4A2 is more easily controllable, more resilient
during long
marches, as the engines do not require frequent adjustment. In battle,
these
tanks work well.” The photo above is captioned,
"M4A2
from the 5th Guards Tank Brigade in Novorossiysk along Mira (Morskaya)
Street, Sept 1943."
The unit’s M4A2s
could only have been from the
first 211 received, and since they were allocated in September, 1942,
it is thought that all of them would have had direct vision as seen on
this example.
A
few other Soviet armor units
are thought to have been equipped with some of the first 211 M4A2s
received. The 229th Tank Regiment is stated to have been equipped with
39 Shermans when it entered combat on July 11, 1943 in the northern
sector of the Kursk salient. In the course of only 3 days, the unit was
decimated, as it reported 14 tanks knocked out and burned, and another
17 badly damaged. By the end of July, the Regiment reported the loss of
all its M4A2s. The 63rd "Taman" Tank Brigade is listed as having been
equipped with 12 M4A2s in
March, 1944. The unit fought in the Sevastopol Campaign in April and
May, 1944. The photo above was taken
"in the vicinity of
Sevastopol, Crimea, April 1944.”
Despite the 1944 date, the “early” appearance of this M4A2 would lead us to assume that it was one
of the first 211. Fisher Body typically used the rather large Mars Signal Light Company siren
that can be seen on this example.
Note that
while the August, 1942 production Kubinka test tank (USA 3021079) shown
previously was equipped with M4 bogies,
this
unit can be seen with the earlier M3 type.
While
the British practically begged for the new Sherman tanks as production
ramped
up in mid 1942, the Soviets were somewhat less than enthusiastic. They
only
ordered 219 M4A2s and 2 M4A4s under the Second Lend Lease Protocol, and
possibly as a result of their experience of these, "Under the third
Protocol [which ran from July, 1943 to June, 1944] British agreed to
give
Russians 3000 tanks of British manufacture. The Russians did not want
any U.S.
tanks direct from the U.S. and none were provided." Needless to say,
the
Brits were somewhat embarrassed by this agreement, since they had
planned their
tank production and shipping allocations based on the assumption that
the
Soviets would order large numbers of Shermans from the US. The US had
assumed
the same, and planned M4A2 production accordingly. A June 1943 memo
from the
British Army Staff in Washington D.C. noted that the Soviets "have a
curious preference for Valentines of which our maximum offer is 1000."
The
Americans were willing to make up the difference by providing and
shipping 2000
Shermans from the US. There may have been some pre Cold War politics
involved
since, after a month of back and forth, the Soviets had not agreed to
accept
the Shermans, and a British staffer noted, "They are being very
tiresome."
Ultimately, the Soviets consented, and approximately 1780 M4A2(75)s
were
allocated to them from July, 1943 through May, 1944. Many of these
Shermans
were shipped via the "Southern route." The all weather "Persian
Corridor" was the means by which vast quantities of Lend Lease materiel
was supplied to the Soviets.
The stills above are from film shot by the US
Army’s Persian Gulf Command. They show M4A2(75)s awaiting overland
shipment to the USSR via the Trans-Iranian Railway. Since the Shermans of the Third Protocol were allocated in July, 1943 and after, most were mid 1943 and later production. However, note that some of the M4A2s seen on the left “still” have the M34 Gun Mount (1). This was replaced by the M34A1 Gun Mount (2) in all Sherman production by the end of April, 1943.
Thus the M4A2s with the M34 mounts had probably been sitting around for
months in lots in the US, before being modified in the Summer or Fall
of 1943 at Tank Depots, and finally shipped out. For example, these
tanks were built before the “Quick Fix” (3) and turret applique (4) mods
were available, so those would have been retrofitted at Depots. On the other hand, the
tanks in the photo on the right represent the ultimate version of the
M4A2(75), where the hull was redesigned to permit the incorporation of
the “Second Generation” feature of larger drivers’ hatches. About 1000
of these are thought to have been produced by Fisher Body from November,
1943 through May, 1944. We estimate that the Soviets received perhaps
800 “large hatch” M4A2(75)s. It was intended to discontinue production
of 75mm Shermans at the end of 1943, but the M4A2(75) remained in
production into 1944, and only at Fisher, primarily to satisfy the US
commitment of the Third Protocol.
The
M4A2s allotted for the Third Protocol began to arrive in the USSR in
November, 1943. Aside from the Northern and Southern Routes, Yuri
Pasholok reports that 149 M4A2s arrived in November at Vladivostok, the
main port of entry on the Pacific Coast. The Soviet Union refused to
join with the Western Allies in their war against Japan until August,
1945. In the meantime, the Japanese, who were anxious for the Soviets to
remain neutral, agreed not to interfere with Lend Lease cargos from the
US West Coast, provided the goods were "civilian" or "non-military" in
nature, and shipped on Soviet flagged vessels, a number of which were
themselves Lend Lease. Considering the geopolitical situation, it is
remarkable that in exchange for neutrality, the Soviets wrangled what
amounted to a "free pass" from the Japanese. Consequently, over half of
all Lend Lease supplies came into the USSR via the "Pacific Route."
Statistics show that most of the materiel was non-military, but needless
to say, this neutrality arrangement did not sit well with Japan's
German ally. The undated photo above shows WOWs (Women Ordnance Workers)
at the Richmond Tank Depot in California, near the port of San
Francisco. Note the sharp angles of the fabricated drivers' hoods (1),
an exclusive feature of Fisher M4A2s manufactured starting in late 1942.
Both of the tanks seen here are outfitted with the standard type of
sand shields (2) which would lead us to put the date as "circa mid
1943." These M4A2s
were most likely intended for shipment across the Pacific to the
Soviets, as the evidence suggests that US Marine Corps M4A2s were not
processed at US Tank Depots. According to Yuri Pasholok, "Altogether,
229 tanks got to the front by the eastern route, of which 80 arrived
somewhere in the second half of 1944." So it would seem that, on
occasion, the Soviets did sneak a few Shermans in via the "Pacific
Route."
Official Lend Lease figures for M4A2(75)
shipments to the Soviets vary a little, but for our purposes, we will
use 1991 as our base, with 211 being from the Second Protocol, and 1780 from the Third. We
have estimated that about 800 of the Third Protocol Shermans would have
been large hatch M4A2(75)s, which leaves approximately 980 small hatch.
Most of the few available WW II photos of these tanks were taken by the
Germans, and show destroyed units, with the large hatch models
appearing far more frequently than the small hatch. The uncaptioned
photos above are from a series showing a pair of KO’d small hatch Fisher
built M4A2(75)s. In some of the images, their turret numbers are in
similar “fonts,” and can be seen as 55 and 56, suggesting that the tanks
were from the same unit and were photographed on the same day. We
believe their appearance would reflect that of most of the Fisher small
hatch M4A2(75)s that the Soviets received. Both tanks have sharp nosed
E8543 differential housings, and “no pistol port” turrets. These
features began to appear in production at Fisher in the Summer of 1943.
Both tanks have the Quick Fix (1) and the driver’s hood armor (2)
modifications. Along with the gun travel lock (3), these were reported
to have been introduced at Fisher in August, 1943. Both have periscope
guards (4), and commander’s vane sights (5), which are stated to have
been introduced in September. At some point, a filler cap for “engine
oil gauge” (6) was introduced in production on all M4A2s. We have yet to
come across any documentation, but the earliest it appears in a photo
of a unit with a known good Serial Number is September, 1943.
Baldwin Locomotive produced only 12 M4A2s from
October to November, 1942. After that, the company manufactured 1233 M4s
from January 1943 to January 1944. ALCO began Sherman production with
the M4A2 in September, 1942. They produced 150 units up to April, 1943.
At the beginning of 1943, they were directed to switch production over
to the M4, and manufactured a total of 2150 units from February through
December, 1943. We believe that all of the M4A2s made by Baldwin and
ALCO would have been direct vision models. No doubt many were
distributed to the Allies as Lend Lease, although we can not document a
single example at present. Records found by researchers at the Russian
Archives have revealed that, for the purposes of casualty and/or repair
reports, at least some Soviet units recorded the USA Registration
Numbers of their Lend Lease Shermans, etc. Of the 100 plus listings
provided to us from these records, about half are Fisher M4A2s and half
Pullman. Federal Machine and Welder produced 540 M4A2s from December,
1942 through December, 1943. So far, we have recorded the Registration
Numbers of 10 FMWs in service with the Soviets, with most of the entries
indicating units produced in the second half of 1943. We believe that FMW used the same glacis plate
pattern, and the same antenna bracket (1) as did Pullman on most of its
1943 production Shermans. Thus, there are no
immediate visual distinctions between the two companies’ M4A2s. The
photo above shows “060,” a combat casualty of the 226th Tank Regiment,
reported to have been knocked out near the village of Panevo in March
1944. We suspect that this M4A2 was made by FMW by virtue of its 3-piece
differential housing. Pullman
appears to have had steady supplies of the 1-piece units by early 1943,
while FMW used a mix of 1 and 3 piece diffs up until about July. More
examples are needed, but another possible difference might be that FMW ,
like Fisher, mounted the grouser blank off plates on top of the armor,
whereas Pullman mounted them flush. This tank is relatively unmodified, but can be seen
with the positive hatch lock mechanisms with equilibrator springs
(inset) which were introduced in Sherman production in the first quarter
of 1943. The periscope guards on the drivers’ hatches were reported to
have been installed on FMW M4A2s in late September, 1943. It is thought
that Pullman, which ended Sherman production in September, never factory
installed them. We can only guess that the guards would have been
retrofitted to this unit in the Fall of 1943 (or later) at a Tank Depot,
but it is curious that no other mods of the time are present.
In
1994, a 72 year old WW II veteran dropped off a manuscript at the US
Embassy in Moscow. The manuscript eventually found its way to Fort Leavenworth,
where it was translated by a military analyst and historian named James
Gebhardt, who described it as "The most detailed description I have
seen of the employment of U.S. military equipment by the Red Army." The
manuscript was published as "Commanding the Red Army's Sherman Tanks:
The World War II Memoirs of Hero of the Soviet Union Dmitriy Loza." The
book shed light on a previously obscure topic, and has become a "must
read" for those interested in the Sherman Tank. An internet source describes the photo above as "A column of tanks, M4A2 "Sherman"
5th Guards Tank Army, in May 1944." These small hatch M4A2s exhibit many
of the modifications introduced in production in the Fall of 1943,
including the sharp nosed differential housing (part number E8543). On
the first 3 tanks, the position of the siren and guard on the glacis
just below the left side hull lifting ring, may be a clue that they are
Federal Machine and Welder M4A2s produced in either November or
December, 1943. Note that the tank riders are armed with submachine
guns. According to Dmitriy Loza, the TOE [Table of Equipment] of a Tank
Brigade included a Battalion of submachine gunners (tankodesantniki). "Our submachine
gunners were like brothers to us...[At halts] The tankers could sleep
and our submachine gunners protected our tanks and us. And..."As soon as
the Germans opened fire...they jumped off and ran behind the tanks."
Loza also mentions that Soviet tankers were offered an "incentive" of
"1000 rubles for each destroyed AFV." His battalion agreed to pool the
reward money and pass it on to the families of their fallen comrades.
Most photos showing Soviet
Shermans in the final months of WW II, are of M4A2(76)s.
However, a few M4A2(75)s appear to have remained in
service to the end. The photo above shows a possible example
during the Battle for Vienna which took place from April 2 to April 13,
1945. This Sherman served with the 14th Guards Independent Motorcycle
Battalion of the 9th Guards Mechanized Corps. This was a heavily armed
Reconnaissance Battalion primarily equipped with Harley-Davidson
motorcycles. The Battalion's firepower was augmented by a company of
about 10 Shermans, commanded by Lt. J.A. Marianin, whose M4A2(76), with
"02" painted on the turret, appears in the background of the photo. The
M4A2(75) was reported to have been the first Soviet tank to enter
Vienna, and this photo along with a couple of others of Marianin and
his M4A2(76) were taken to mark the occasion. Lt. I.G. Dronov and Sgt.
N.I. Idrisov pose in front of the tank which has the drivers' hood
castings and the type of antenna bracket typical of Pullman or Federal
Machine M4A2(75)s. Perhaps a bit of the gun travel lock may be seen
over Lt. Dronov's right shoulder?
There are at least 4 surviving
small hatch M4A2(75)s in the former Soviet Union. At present, the
serial numbers of these tanks are not known, but the example on display
at the Military Historical Museum in Lenino-Snegiri (north-west of
Moscow) once had "USA 3038978" painted on as shown in the inset. This number would
represent June, 1943 Pullman production, and we can at least observe
that the overall appearance of the tank is appropriate to mid 1943. It
looks to be in a similar configuration to "060" from the previous
caption, with the only apparent modification being the periscope guards
(1) on the drivers' hatches. The glacis is made up of two pieces of
armor plate (2 & 3), with the drivers' hoods (4 & 5), bow
machine gun (6) and antenna bracket castings (7) welded in. Again we
would note that Federal Machine M4A2s are seen with similar glacis
patterns, right down to the antenna bracket casting with a flat area at
the base.
The round indentations on a single armor plate of the
Snegiri M4A2 constitute an interesting "aberration" seen on this tank
and no other surviving Sherman of which we are aware. A former metal worker
describes these as "The marks a power hammer leaves after straightening a
warped plate." The thousands of components that went to make up a
Sherman were inspected at delivery, and at other times during the
assembly process. We can only assume that when this particular hull was
welded together, the indented plate passed muster, since, ultimately,
the completed tank was accepted by the US Government. The photo provides
a good view of the lifting ring casting (1) that became standard on
most Shermans starting in 1943. "SS in an oval" (2) can be seen on the
bustle of the turret. This was the caster's logo of Scullin Steel of St.
Louis, Missouri, one of the smaller producers of Sherman turrets. They
appear to have been a regular source of turrets for Pullman. For
instance, during the month of February, 1943 Scullin is reported to have
delivered 175 turrets to Pullman, while another small company, Buckeye
Steel provided 84, and the large producer, General Steel-Eddystone
delivered 12. Additional casting marks on the roof of this particular no
pistol port D50878 turret give the turret serial number as 978 (inset),
which we take to mean that, as of mid 1943, Scullin had delivered about
1000 turrets.
The
hulk shown above is thought to be the only surviving example (if we can
call it that) of a Soviet large hatch M4A2(75). It
is on display at the National Military Museum in Bucharest, Romania.
This tank is reported to have fallen into the Prut River near Petresti
in August 1944. From the location, it is likely that this tank served
with an armored unit of the 5th Mechanized Corps on the 2nd Ukrainian Front. Shortly
after it was lost, Russian forces recovered the turret, presumably for
refitting to another Sherman. A local who was granted permission to
salvage the engine, appears to have salvaged a good deal more than that.
What was left was recovered in 2000, and placed on displayed at the
museum. While the serial number of this tank is not known at present,
the forward cable clamp can be seen in the "first" position (1), and the
return roller arms are straight (2) as opposed to upturned, which would
lead us to think it is an early production (November/December, 1943)
example. Information and photo courtesy of Doug Kibbey.
French use of M4A2
The
Allies invaded Northwest Africa on November 8, 1942. It was hoped that
Vichy French Forces in the colonies of Algeria and Morocco would not
oppose the “Operation Torch” landings, but instead would join the Allies
in the fight against the Axis. Unfortunately, this did not occur and
British and US Forces had to fight their way ashore. However, the French
capitulated a few days later on November 10, and following delicate and
occasionally embarrassing political negotiations, agreed to rejoin the
Allies. French General Henri Giraud played an important role during and
after the Casablanca Conference in January 1943. As a consequence, the
US agreed to supply materiel to the so called “Free French in North
Africa,” which helped to establish and train several Divisions,
including three Armored Divisions. The "International Aid Statistics"
Report indicates that the French received 656 "Tanks, Medium and Heavy"
through Lend-Lease. In fact all of them were Sherman Medium Tanks, and
France was the third largest recipient of the Sherman, after the British
Empire and the USSR. Deliveries
of medium tanks under the official Lend Lease program occurred in 1943
and 1944. The 656 Shermans allocated to the Free French consisted of 274
new production M4A4s, 362 new production M4A2s and 20 remanufactured
M4A2s. It is thought that all were shipped to Northwest Africa, except
for the 20 M4A2s allocated in October 1944. Most likely, these came in
through Marseille, France sometime in early 1945.
All
but the last 20 Shermans were delivered to the ports of Algiers
(Algeria) and Casablanca (Morocco) in 1943. The French formed three
Armored Divisions, each equipped with 165 Shermans. US
advisors required that homogeneous Armored Divisions be created. That
is, to ease logistics, the M4A2 diesels should entirely equip two of the
Divisions, while the gasoline powered M4A4s should equip the third. The
2ème Division Blindée indeed was entirely outfitted with M4A2s. It was
intended that the 1ère Division Blindée be equipped only with M4A2s, and
the 5ème Division Blindée exclusively with M4A4s. However, the original
allocations to the 1ère and 5ème Divisions had not been all of one
type, and both were formed with 110 M4A4s and 55 M4A2s. Despite multiple
American requests for standardization, the French refused to exchange
Regiments between Armored Divisions, as it was felt such transfers would
affect unit cohesion and morale. In
the end, M4A4s were allocated to the 2ème Régiment de Chasseurs
d'Afrique and 2ème Régiment de Cuirassiers of the 1ère Division Blindée,
and to the 1er Régiment de Chasseurs d'Afrique and 1er Régiment de
Cuirassiers of the 5ème Division Blindée. The 110 M4A2s were evenly
allocated to the 5ème Régiment de Chasseurs d'Afrique (1ère DB) and the
6ème Régiment de Chasseurs d'Afrique (5ère DB). The
photo above in entitled "Free French Forces train with U.S. supplied
Sherman tanks in Algeria, 1943" and shows newly issued M4A2s that the
carry the "drapeau consulaire" (1) or "drapeau 1804", of Napoleonic origins, which was adopted as the symbol of the French First Army.
Of the 362
diesel engined M4A2(75)s allocated to the “French in North Africa”
between May and July, 1943, photographic evidence suggests that most of
those distributed to the 2ème Division Blindée were manufactured in
1943, but some 1942 production units are also seen in the mix. For instance, the photo above left shows "Perthus" of the 12ème Régiment de Chasseurs d'Afrique, with
Direct Vision (1), and the M34 Gun Mount with the narrow rotor shield
(2), features typical of 1942 Shermans. “Ile de France,” another M4A2 of
the 12ème Régiment de Chasseurs d'Afrique is shown on the right. The
sharp nosed “Mary Ann” differential housing (3) was introduced into
production at Fisher Body in July 1943, and it is thought that “Ile de
France” would have been one of the M4A2s allocated to the French during
that same month. Note the wider rotor shield of the M34A1 gun mount (4).
Both of these tanks appear to have received a few “in the field”
modifications, including the turret appliqué armor patch (5). The
visible gap in the patch on “Ile de France” suggests that it was a case of an unnecessary application (see below for further details).
These tanks were photographed landing on Utah Beach on August 1st or
2nd, 1944, and each can be seen with a “Somua” plate affixed to the
front, a souvenir of the old Somua S-35 tanks the Regiment had had in
North Africa.
The
2ème Division Blindée was chosen to take part in the Normandy Campaign,
and shipped out of North Africa with its 165 M4A2s on April 11, 1944.
It arrived in the United Kingdom 11 days later, where it continued to
train. The Division was the subject of a good deal of Press coverage
when it landed in Normandy in early August, 1944, as it was the first
major French unit to reenter France. The US Ordnance Department directed
that US Army Shermans located in the UK receive a number of upgrade
modifications prior to the Invasion of Europe. Since the 2eme DB was
attached to the US Third Army, its tanks were considered subject to the
directive, and the Division was provided with quantities of the various
modification kits. However, it would appear that French Maintenance
units were overwhelmed by the number of modifications, and did not have
the time or manpower to apply them “by the book.” For instance, period
photos and a few surviving examples, show that the hull appliqué plates
that were part of the "Quick Fix" modification kit were merely tack
welded on, a technique that would been rejected by US Army inspectors.
The image on the left is from newsreel footage shot in
North Dalton, UK, in July, 1944, and
shows French mechanics welding an appliqué plate on "Arcis sur Aube,"
an M4A2 of the 501ème Régiment de Chars de Combat. The right side photo
shows the non continuous weld beads on "Massaoua," an M4A2 destroyed on
August 15, 1944 in Ecouché, Normandy. A few of the surviving 2eme DB
monument Shermans on display in France, like "Massaoua," are missing
their applique plates, most likely due to the inadequacy of the original
tack welding method.
One of the modifications
mandated for installation on US Shermans in the UK was Blitz Item No.
57,
"Increase thickness of Turret Armor in Region of Traversing Gear."
There
were a couple of scooped out "thin spots" on the right front side of
the turret's interior wall that provided clearance for the crew to work
the
traversing mechanism. It was reported that the enemy aimed for these
thin
spots, so an exterior patch kit was produced to correct this defect. In
the
meantime, the D50878 turret mold was altered by providing a "cast in
thickened cheek" which eliminated the need for the welded on turret
patch
modification. Ordnance engineers considered the pistol port to be a
weak spot
on the Sherman's turret, and made the unfortunate decision to eliminate
it from
the revised casting. The new turret castings entered the production
pipeline in
the Summer of 1943, and it is obvious from period photos and surviving
examples
that the French received a few M4A2s with "cast in thickened cheek/no
pistol port" turrets. In any case, an interesting anomaly seen on a
handful of 2eme DB Shermans is the unnecessary application of the
welded on
turret patch to the revised turrets (see
the 75mm
turret page
for further details). "Valois,"
"Massaoua" and "Chemin des Dames" are historical examples
featuring unnecessarily applied turret patches. The cast, two piece
applique
sections were not made to fit the revised turret, and Massaoua
(pictured above)
shows a particularly poor fit. Lack of direction from US Ordnance
personnel,
and/or simply a language barrier misunderstanding were the likely
culprits in
the case of the unneeded turret appliqué.
The two barred Croix de
Lorraine (Cross of Lorraine) was adopted as the symbol of the Free
French Forces
who chose to continue to resist the Nazis after the Fall of France in
June,
1940. The unit symbol chosen by the 2ème Division
Blindée consisted of a blue
circle containing a map outline of the country of France over which was
superimposed the Cross of Lorraine. This symbol (1) appears painted on
nearly
every vehicle of the 2eme DB. Another of the modifications mandated for
installation on US Shermans in the UK before D-Day was the "2 inch
Smoke
Mortar." The
mortar was to be installed inside at the left front of the turret
through a
hole drilled or burned into the armor.
It would appear
that
some French units chose not to install the mortar "by the book,"
possibly because they lacked the time or the proper tools. A few M4A2s
of the
501ème Régiment de Chars de Combat are seen with
the smoke mortar affixed to
the exterior of the turret on the right side as shown above (2) on
"Friedland," photographed in Paris on August 25, 1944, the day the
German Garrison surrendered the French Capital. "Friedland" can also be seen with a stowage box (3)
on the rear of the turret which, along with the installation of a large
stowage box on the upper rear hull plate, was a common practice in the
2ème Division Blindée. Collection Benjamin Josset via Laurent Fournier.
Here
we would like to feature an M4A2(75) that served with the 12ème
Régiment de Chasseurs d'Afrique of the 2ème DB from the time the unit
landed at Utah Beach in early August, 1944 through to VE-Day in May,
1945. There are quite a few period photos of "Corse" showing that she
was tank number 35, Matricule Number 420644. Perhaps one of the crew
members was a native of the island of Corsica, and named the tank after
his home? Chars Français website
reports that, during an inspection in February, 1944, the Division
commander, General Philippe Leclerc, noticed that a tiny outline of the
island of Corsica (1) was painted below the Cross of Lorraine Division
symbol, and ordered that it be removed, because it was not
"regulation." The photos make it apparent that the crew ignored the
order. In September, 1944 during the fighting in Dompaire, Corse was
reportedly hit by two phosphorus shells which caused her to glow in the
dark. The
crew stated that they tried to wash off the chemical with water, and
even went so far as to use some French wine they had stashed in a
jerrycan. "Corse"
is reported to have participated in the Alsace Campaign in late 1944,
the defense of Strasbourg in early 1945, and the battle of the Royan
Pocket in April, 1945. The snapshot on the left was taken on
August 25, 1944 during the Liberation of Paris. Note the tack welding
of the applique plate (2). Other photos show that Corse had a no pistol
port turret, and one can see the unnecessary turret patch with the gap
(3) between the sections. The tank can be seen with both the original
commander's blade sight (4), along with the vane sight (5) that
replaced it, and was probably retrofitted at a US Depot or in England
before the Invasion. The photo on the right perhaps shows the tank
commander Jean Titeaux, and the driver, Lucien Matron. The antenna
bracket (6) is typical of those seen on Pullman and Federal Machine
M4A2s. Note
the Lima Tank Depot type comb device with the 3 U-bolts welded on (7).
It would appear that the crew carried the assembled ram rod (8) on the
outside of the tank in the position shown here. Left side photo courtesy of Myriam Montagné.
An
M4A2(75) named "Corse" is in a storage lot at the Saumur Tank Museum.
The staff was able to determine through "paint archeology" that the
hull was indeed that of the historic "Corse." Period photos suggest
that M4A2s remained in service with the French Army at least up to
1956. Our subject appears to have been one of those that continued to
serve post war. We base this on the presence of the "serial number in a
box" (inset, pointer) which has been noted on a number of surviving
French Shermans and other AFVs. The "SN in a box" is usually
accompanied by a rebuild or heavy maintenance tag which includes the
place where the work was done, and often a date from the 1950s. The tag
is missing on "Corse," but one can see its former location (circled).
In any case, as far as we have been able to determine, Pullman Standard
did not stamp the serial number anywhere on the exterior of its
Shermans, so, as researchers, we are grateful to the French for the "SN
in a box." Serial Number 30850 would have been accepted in August,
1943, and it is likely that "Corse" was one of the 300 plus Lend Lease
M4A2s allocated to the "French in North Africa" in July, 1943. It
should be noted that "Corse" no longer has the "no pistol port,
unnecessary turret patch" turret that can be seen in the period photos.
Over
30 years ago, Corse was spotted in a storage lot at Saumur with a
turret retrofitted with a massive gun mount (1) holding the CN 75-50, a
French design derived from the powerful 75mm gun of Germany's WW II
Panther Tank. The turret was also retrofitted with a loader's hatch (2),
and a commander's all around vision cupola (3). This appears to have
been the original attempt to cram the CN 75-50 gun into the "small"
Sherman 75mm/105mm turret. The final design was quite a bit different,
with the turret enlarged by extensions on both the front and rear. The
first example was shipped to Israel in 1955, and the "new" upgunned
Sherman was designated "M50." M50s saw extensive service with the
Israeli Defense Forces from 1956 up to 1973, and, famously, more than
held their own against the more modern tanks fielded by the Arab States.
In the photo, it can be seen that Corse no longer had its engine decks
(4) in the late 1980s. Since then, the CN 75-50 turret has been replaced
with a D50878 turret cast by Scullin Steel, which is appropriate, since
SS was one of the suppliers to Pullman. However, as noted previously,
this turret has a working pistol port, so is not original to the tank. Photo courtesy of Laurent Deneu.
The
5ème Régiment de Chasseurs d'Afrique was the
single regiment of the 1ère Division Blindée
that was entirely equipped with M4A2(75)s (55 tanks). The unit came ashore
with
Operation Dragoon follow up forces, and first entered combat on August
21,
1944. During the course of the campaign, most of its losses were
replaced with
other M4A2s, but a few M4A1(76)s appear to have been received in late
February,
1945, along with a few M4(105) HVSS in early May, 1945. As with the
2ème
Division Blindée, the regiment’s M4A2s
consisted of a mix of early and
late models from various manufacturers, including some with Direct
Vision. The
photo above shows "Lasalle", a Fisher-built M4A2 of the 5ème
RCA,
entering the German city of Baden-Baden on April 12, 1945. The M34 Gun
Mount
suggests that this tank was produced before April, 1943. Photo courtesy
of
ECPAD, TERRE-10278-L11.
In
early November, 1944, the 6ème Régiment de
Chasseurs d'Afrique became the first unit of the 5ème
Division Blindée to enter into combat. Documents and period
photos reveal that the majority of the Shermans that equipped the
Regiment were M4A2(75)s. French tanks were generally named by their
crews, but “counting heads” suggests that less than
half of the Shermans in the 6ème RCA carried names. Most of
them only show a “speed number,” such as "33"
pictured above left. Photo courtesy of ECPAD.
As
mentioned previously, the last 20 "official" Lend Lease M4A2s were
allocated to the French in October, 1944. Taking into account shipping
times,
these tanks probably didn’t arrive in theater until the
beginning of 1945. They
would have been remanufactured in the US, so would have had the full
suite of
modifications, including appliqué armor plates in front of
the drivers’ hatches
(1) and on the hull sides (2), the gun travel lock (3), the blanket
roll rack
(4) and stowage for the machine gun on the rear turret bustle.
Remanufactured
M4A2s
are seen in all units of the 1ère Division
Blindée and in the 6ème RCA, 5ème
DB. Three remanufactured M4A2s have been identified in the
2ème Division
Blindée as well. The photo on the left shows
“Davout” of the 2ème Régiment
de
Cuirassiers. This tank is a 1942 Fisher Body produced M4A2 with Direct
Vision. On
the right is an M4A2 said to be of the 5ème RCA, but
otherwise unidentified due
to the absence of any unit markings. The lack of any crew stowage on
these
tanks, suggests that they were photographed post war. Both photos
courtesy of
ECPAD.
It is thought that the French received a few
of the 120
M4A2(75)s that were part of the emergency transfer by the British to
the US in January 1945. The units shown above both served with the 6ème Régiment de
Chasseurs d'Afrique of the 5ème DB. These tanks have
features that
indicate that they were among the 535 M4A2s remanufactured in the US in
1944. The drivers’ hoods with direct vision seen on Tank
Number 53 would indicate that it was produced in 1942. Such a tank
would have been built originally with an M34 Gun Mount. The M34A1 Gun
Mount with its wider rotor shield would have been added along with the
numerous other modifications during remanufacture. Both tanks show
fittings, such as the spare track holders, typically added to
Commonwealth Shermans before issue. Although these photos are undated,
the crew stowage suggests that they are war time shots. A
road sign for Göbrichen, Germany can
be seen in another photo of Tank Number 53. The 6ème RCA was in that area in
mid April, 1945.