The photo above shows an 11th
Armored Division M4 named "Bambino" at Camp Banning, California in
January, 1944. A close examination of the original print revealed
the Registration Number to be 3015981 indicating January, 1943
acceptance. From this, we might assume that PSC introduced the elongated
drivers' hoods in late 1942/early 1943. Bambino can be seen with a couple of new items - the
fittings for the spot and signal lamp and the bow machine gun dust cover (both
circled). The siren has been moved from its original position on the left front
fender to the glacis, where it sits on a brush guard. This unit
"still" has the early "bent rod" hull lifting rings,
although some December, 1942 PSC Shermans have been noted with the standard
lifting ring castings. Quite a few modifications were available for first
generation Shermans by the time this photo was taken in January, 1944. However,
modification kits were produced in limited numbers, and they were generally
reserved for tanks overseas or headed there. Training tanks in the US are
mostly seen unmodified, or in "as built" condition. The 11th Armored
Division left the Desert Training Center in early February, 1944, and Bambino
would have been inherited by the next unit assigned there. Most likely, this
tank would have become one of the 795 M4s remanufactured from August 1944
through April, 1945.
We don't know the tank's serial number, but the remanufactured M4 on
display at the Commemorative Air Force Museum in Dallas has features
that we associate exclusively with PSC. It is one of 3 surviving M4s
thought to be PSCs with the elongated drivers' hoods. From personal
examination, we can confirm that the lower section of the glacis is a
long casting that includes the bow machine gun socket. However, note
that it does not have the D51011 info cast in on the front, nor does it
have the little "buttons" on the corners of the casting. Like "Bambino"
in the previous caption, it "still" has the "bent rod" hull lifting
rings. This would likely be a clue that the production date was around
late 1942/early 1943. As with the Saumur M4 we suspect the turret is not
the original. It is another Buckeye Steel, in this case with a casting
date of 1-43 (January 1943) and a serial number of 1074 compared to 1475
of the Saumur's 3-43 turret. We were somewhat surprised to note that
the pistol port on a January 1943 turret is welded up (inset), since the
"eliminate the pistol port" edict did not really go into force until
mid 1943.
There
may be a couple more PSC M4s with the elongated drivers' hoods on this
earth, but perhaps buried deep underground at the Trinity Site at the
White Sands Missile Range in New Mexico. These tanks were
lead lined and outfitted with oxygen tanks for use by their two-man
crews. Various sensors were installed along with tethered rockets used
for gathering and retrieving soil samples inside the A-Bomb crater. The
photo above is thought to have been taken in April 1945 not long after
the tanks arrived at the test site. The turreted M4, which can be seen
as USA 3015952 (Jan. 1943) had not yet been painted silver, while the
turretless tank had already been painted white. In the series of photos,
USA 3015952 or the "silver tank" as it was called, is noted to have a
riveted lower hull, "bent rod" lifting rings and somewhat unexpected,
the fabricated type of air scoops. The "white tank" has later features
such as standard hull lifting rings and a welded lower hull. The
location of the additional steel slabs on the side of the "white tank"
indicate that it was a former T3 Mine Flail. As we shall discuss further
along, PSC converted 41 of its M4s to T3 Mine Flails. The sharp nosed
E8543 differential was likely a replacement, but there's a small chance
that it is the original since the last 11 T3s were converted by PSC in
July 1943. The tanks were used on 16 July 1945, the day that the bomb
was detonated as well as the day after. With that their mission was
complete. A caption on a photo of 3015952 (inset) states, "Enrico Fermi
was inside this modified lead-lined M-4 Sherman Tank. He entered the
blast area around 7:00 a.m. on July 16, 1945, to take soil samples." In
his book, "Birthplace of the Atomic Bomb," William S. Loring has it that
in February 1947, it was reported that "two tanks [were] in a dump to
the northeast of the base camp in amongst tractors, tracks, wire and
other debris." He believes that the most likely end for these
contaminated Shermans was that they were buried somewhere on the site.
The other manufacturers didn't
begin M4 production until early 1943, so PSC M4s would have been the only such models
available during the battles in Tunisia at that time. Most of the photos of US
Army Shermans seen in Sicily are M4A1s, but above shows an M4 advancing towards
Messina on August 15, 1943 two days before the end of the campaign. This tank
is named "Bad Boy," and is thought to have been with the 753rd Tank
Battalion. We identify it as a PSC built M4 based on the "high" weep
holes. This tank can be seen with what we label "the plain sprocket,"
which was introduced on PSC M4s and M4A1s in early 1943, and used by them until
the end of production in 1945. Quite a few PSC M4s and M4A1s are noted with the
aircraft cowl type fasteners used to secure sand shields before the
introduction of the "Universal" or "Interchangeable" type
sand shields in mid 1943. PSC already had some experience producing sand
shields from their time making Grants for the British. In the photo, one can
see how the section hangs off the fasteners. Later versions, including the
universal type sand shields, were screwed or bolted on to attachment strips.
Most "combat shots"
of PSC M4s are from the Italian Campaign. This well known photo of the
"Belle of Little Rock" of the 755th Tank Battalion was taken in the
Castelforte area on May 12, 1944 at the start of the Allied Offensive which
culminated in the capture of Rome on June 4th. PSC is reported to have
introduced the M34A1 Gun Mount into production at the end of March, and the
“universal type” sand shields at the end of April, 1943. Sand shields were not
popular with the troops and, as seen here, were mostly removed. Note the
attachment strips used to hold the later types of sand shield. "Belle"
can be seen with a welded lower hull. Pressed Steel "joined the pack"
and, by our head count, completed the transition to this around May, 1943. Casting
flaws were repaired by filling in with weld material. Belle's turret has about
the most extensive repairs we have ever seen. The M4 behind Belle appears to be
an earlier PSC with direct vision, and the Signal Corps photographer captured
the moment that the projectile left its 75mm gun.
The photo above shows tanks
B-14 (left) and B-13 of the 1st Tank Battalion, 1st Armored Division preparing
to advance to the Arno River on August 31, 1944. The tank riders are GIs of the
370th Infantry Regiment, the first element of the 92nd Infantry Division
(composed of "Negro troops" (sic)) to arrive in Italy. As best we
have been able to determine, only Pressed Steel Car and Baldwin Locomotive
produced M4s with direct vision. B-13 has the PSC glacis pattern, while B-14
can be seen with the sharp edged fabricated bow machine gun and antenna sockets
typical of Baldwin M4s. One might not expect to see the later M34A1 Gun
Mount on a direct vision M4, but "counting heads" years ago, we were
surprised to find no examples of Baldwin M4s that did not have direct vision. As
mentioned earlier, the Ordnance Department ordered the elimination of direct
vision from the M4 design on August 13, 1942. Baldwin produced 1233 M4s from
January 1943 through January 1944, and although we have yet to find any
documentation, the available evidence leads us to conclude that ALL of them
were made with direct vision. We suspect that the PSC M4 in this photo is at
least 7 months older than the Baldwin.
Above shows the scene in a
tank dump in the United Kingdom a few months before D-Day, June 6, 1944. The M4
in the foreground can be identified as a Pressed Steel by the Registration
Number 3036751, indicating April, 1943 production. This tank appears to have a
welded lower hull, and if so, it would have been one of the first to make the
transition. The Ordnance Department wanted a great number of modifications to
be applied to the US Army pool of approximately 1000 M4s and 400 M4A1s that
were in the U.K. in the months preceding the Invasion. Indeed, the number of
such modifications was so large that ETOUSA estimated that it would take 2
years for their personnel to complete the job. Consequently, many of the
Shermans had the mods installed assembly line fashion by British contractors. It
was noted that half of the US Shermans in the UK had the M34A1 Gun Mount (a
"Must" modification), but all of those were equipped with the earlier
M50 telescopic sight, when the M70F telescope was a "Must." Note that
one unit (arrow) still has the M34 Gun Mount. None of the US Shermans in the UK
had the "Quick Fix" modification (1) which was another
"Must." The "thin spot turret patch" (2) was merely
"Urgent," and was reported missing on 70 percent of the pool. In the
photo, the "overwritten" stars would not have been acceptable at a US
Tank Depot, which suggests that the applique armor was done in the U.K. The new
"Commander's Vane Sight" (inset) was a "Must," but is not
seen on these tanks, possibly because supplies had not yet arrived in theater. Certainly
some of the modifications were unreasonable. Sand shields were
"Urgent"? Many were removed even before the tanks landed in France. The
sand shields on 3036751 can be identified as the universal type by the vertical
slit (3) in the center section.
Only 525 units were produced
by PSC in 1943 before M4 production ended in August. Consequently, they are
relatively rare in photos in Northwest Europe. Above shows a well known image
of a PSC M4 in Belgium, September 9, 1944. The caption identifies the GIs as
60th Regiment, 9th Infantry Division. The 746th Tank Battalion was attached to
the 9th ID at the time. The 746th landed on Utah Beach as part of the second
wave on D-Day. This Sherman typifies the appearance of US Army M4s and M4A1s at
the outset of the Campaign in Normandy. Just about every modification made
available by the end of 1943 is seen installed. Note how the Commander's Vane
Sight has been retrofitted next to the original blade sight. The hedgerow
cutter would have been added in the field in July 1944 before the start of
Operation Cobra. Pressed Steel Car M4s and M4A1s were outfitted with either the
original welded spoke road wheels seen in the previous photo, or the pressed
metal type shown here.
Ordnance documents note that
41 new production PSC M4s were converted to T3 Mine Flails. These were
essentially copies of the British "Scorpion" design. The first batch
of 30 were converted in April 1943 from M4s built on Production Order T-3321. The
101 M4s and 299 M4A1s from this P.O. were produced in March and April, 1943. Thus,
the photo above provides an idea of the front appearance of a Spring 1943 PSC
M4. The positive hatch lock mechanisms (1) were reported to have been added to
the commander's and drivers' hatches in early March. Note the standard hull
lifting ring castings (2), the step bracket (3) and the "second"
position of the siren (4). The few photos of the first 30 T3s show them with
M34 Gun Mounts, and oddly, the rotor shields noted are seen "back" in
the earlier configuration, without the cast in side pieces (5).
In this rear view, one can see
the addition of the exhaust deflector (1), which is in the "closed"
position. This was said to have been introduced at PSC on March 11, 1943 at
Serial Number 13610. This tank "still" has a riveted lower hull
(circled). We believe that PSC began the transition to the welded lower hull in
April and completed it by May, 1943. Starting around the 2000
range, some Union Steel turrets are seen with the turret Part Number, D50878,
cast in on one or the other side. We would guess that the "12" above the Part Number may be
a reference to the turret mold that was used. The numbers noted run from 1 to
14. This turret appears to be serial number 2990. A very unscientific
"head count" suggests that the M34A1 gun mount was factory installed
on US turrets with Serial Numbers 3100 and higher. US turrets from about 3500
through 4400 are noted in the revised configuration that eliminated the pistol
port. The high or low position of the rear turret lifting rings may have
depended on the mold that was used. The earliest Union Steel turret we've noted
with the "lows" is 239, seen on a May 1942 production M4A1. However,
from about turret SN 300 through 470 the “highs” are seen again, with most of
those having the unusually large lifting rings, such as on turrets 345 and 415
discussed earlier. Finally, every US turret recorded from SN 494 and above has
the “lows.”
A number of the first 30 T3s
were shipped to Northwest Africa soon after they were converted. The 5th Army
Engineer Training Center in Algeria published a report on August 12, 1943
detailing a demonstration in which 2 standard "T-3 Exploders
(Scorpions)" and 1 "T-3 Exploder, Modified" negotiated their way
through minefields and wire obstacles. The two standard T3s completed most of
the course, although it is noted that they were fortunate to escape intact,
because their flails had failed to detonate some mines. The modified unit was
widely photographed, and may be the subject of some confusion. During the
demonstration, it "blew up" on a pair of mines that its flails had
missed. Both tracks were broken, and some bogies damaged, but the crew was
unharmed. Above shows the modified unit and the suspension damage sustained on
the right side. The boom of the modified T3 was 2 1/2 feet shorter than
standard, skids were added under the gearbox, and shielding plates were
installed to further protect the front of the tank. Note that even the siren's
brush guard was given some extra protection.
The tank Serial and T3
conversion numbers were stenciled on to the various mine flail components. The
outboard flail engine, and most likely the M4 itself, was Serial Number 13771,
T3 conversion number 12 (left). The boom sections (right) of the modified unit
appear to have been cobbled together from other T3s, including SN 13796,
conversion 20 and SN 13797 conversion 22. By the Serial Numbers, all of these
M4s would have been accepted in April, 1943. The report concludes that the T3
cannot "be expected to negotiate anything but fairly level ground." Additionally,
"concertina wire...entangled around the rotor...may be counted on to stop
current models," and "overheating of the Scorpion engine is a serious
problem which will necessitate modifications." Despite the negative
report, the 6617th Mine Clearing Company (Provisional) employed 12 T3s in
support of the 1st Armored Division during the breakout from Anzio in May,
1944. The T3s could not do an effective job, and were removed from service.
Here we see one of the final 11 T3s converted in
July, 1943 from new M4s built on Production Order T-3605, the last
Pressed Steel P.O. that included M4s. In August, 1944, this unit served
as the test bed for the installation of a large diameter drum known as the
"Rotoflail." Some Ordnance personnel suggested that flailing operations
were best performed with the turret reversed as seen here. USA 3037333
would have been accepted in June, 1943, and unlike the earlier T3s, can
be seen with the M34A1 Gun Mount. We suspect that June saw PSC's
transition to the "no pistol port" D50878 turret (1). Other items of
interest include the round air cleaners (2), the exhaust deflector (3)
in the open position and the "long" trailer towing pintel (4), reported
to have been introduced at PSC at the end of April. The original welded
spoke idler wheel gave some problems, and, in mid 1943, the Ordnance
Department mandated that they be replaced with the disc type (5) on all
new production Shermans. The last 50 PSC M4s were completed in July and
August. The drivers' hood applique and Quick Fix mods were reported to
have been introduced at PSC at that time, but we have not come across
any period photos of PSC M4s that would confirm if any had those
modifications factory installed.
This undated photo was taken
at the Lima Tank Depot in Ohio, most likely in the Fall of 1943. The lack of
bullet splash protection around the fire extinguisher pull housing (1) suggests
that the Sherman is a Pressed Steel Car M4. The installation of the Quick Fix
Modification is said to have taken over 140 man hours. It was necessary to
remove the turret in order to retrofit 1/4 inch armor plates and doors to the
ammunition bins. The weld scorch marks indicate recent completion of the job. After
all modification work was done, the depot was directed to clean and repaint the
interior in white where necessary. We've seen a few surviving Shermans that
have "decalcomanias" or stencils with "75 MM RDS"
affixed to the ammo bins (inset). The bins are marked with the number of rounds
as listed in the November, 1942 Technical Manual. The capacity of the original
M4 and M4A1 is stated as 90 rounds (or 94 if the tank was equipped with a .30
caliber AA machine gun, instead of a .50 caliber). The 12 unprotected ready rounds
around the turret basket wall were eliminated with the Quick Fix modification,
which reduced the number of rounds carried to 78. There were complaints about
this from users in the field, and it is mentioned that some crews removed the
armored lid from the 8 round rack on the turret basket floor, and piled
additional rounds on top.
Here we have an overhead view of Serial Number 28203 which would have
been accepted in April 1943. We approach the dates and Serial Numbers
listed in the Ordnance documents with some skepticism, but it was
reported that the company introduced the M34A1 Gun Mount on 29 March
1943, at SN 28203, so this might have been one of the first units built
with the M34A1. Most of the modifications seen on this tank were
introduced after April 1943, and the remanufacturing programs didn't
begin until August 1944, a few months after this photo was taken. Thus,
most of the mods were likely retrofitted as this unit was processed at a
Tank Depot. We've pointed out the weld seams at the point where the
hull top armor angles down. As a matter of Sherman minutia, we would
observe that there are no further seams from that point to the rear of
the hull on the few PSC M4s we have examined. Chrysler M4A4s are also
noted to have used this "seamless" configuration. Other welded hull
Shermans, including Second Generation models, are seen with seams at the
point where the turret splash meets the fuel cap splash guard (black
arrows). This tank was retrofitted with doubled up tow cables ("bridle
assemblies") on the front and rear. SN 28203 was used in trials of the
automatic tow hook. This would have permitted crews to recover a tank
without getting out to hook up when under fire (inset). The tow hook was
wanted on all retrievers intended for the Invasion of Japan, and a
Modification Work Order was released in late April stating that Tank
Recovery Vehicles "will not be shipped overseas after 30 April 1945,
unless this work order has been applied." Had the Invasion gone forward,
it is thought that bridle assemblies would have been retrofitted to all
AFVs taking part, as per the MWO, "The field will be instructed to
improvise bridles on combat vehicles to allow the hook to be connected
to the vehicle and tow it to a protected area for repairs." As another
matter of Sherman minutia, we would point out that this M4 can be seen
with the prominent D51011 casting marks with the highest serial number
we have recorded - 332, suggesting that at least 332 of these were cast. Photo courtesy of
George Fancsovits.
Pressed Steel Car built nearly
4 times as many M4A1(75)s as M4(75)s, and they served in all theaters from the
Sherman's debut with the British at El Alamein to the "last battle"
on Okinawa. On August 23, 1942 the company was given verbal instructions that it
was to produce 1000 standard made M4A1 Medium Tanks with an engineering change
that incorporated the 76mm Gun M1 mounted in the newly designed M34A1
Combination Gun Mount. It was intended that this order would be completed
before the end of 1942. This was entirely unrealistic, and as it turned out,
exactly one such unit was produced in 1942. SN 549, USA 3015305 was the pilot
model M4A1(76M1) and tests at APG led to recommendations for a number of
improvements to be made to subsequent units. One can see that this September 1942
production M4A1 "still" has M4 bogies with the original half round
track skids. Note that the standard cast air scoops and tail light guards have
not yet been installed. The Union Steel turret serial number appears to be
1034.
USA 3015334 was also accepted
in September, 1942, only a few units after the M4A1(76M1) pilot. This Sherman
was photographed in January, 1943 when it was used by the Barber-Colman Company
to demonstrate its "Air Flow Corrective Devices." The Barber-Colman
system was adopted for use on PSC M4A1s starting on December 1, 1943, and
Chrysler M4s starting on January 1, 1944. It featured "Pyramid Turning
Vanes" on the engine air intake and a "Hinged Air Exit Vane" in
place of the original exhaust deflector (insets). This unit is installed with
the standard cast air scoops (1), as is every PSC Sherman we have been able to
record with higher Serial or Registration Numbers. We might infer that the
later asymmetrical track skids (2) seen here were introduced at PSC in
September. This tank "still" lacks tail light guards, which our head
count suggests were introduced in October. Because they are often readable in
period photos, we like to record the Union Steel turret serial numbers and the
features visible. This one is # 1137.
The second model of the
M4A1(76M1), Serial Number 10953, USA 3015954, was not accepted until January,
1943, and was immediately shipped to the Armored Force Board at Ft. Knox,
Kentucky. Based on feedback from trials with the original pilot, a new turret
casting was made that featured an enlarged bustle which served to
counterbalance the gun, and provide the turret crew with a little more room. These
turrets were produced by Union Steel, and this particular casting can be seen
to be Serial Number 2. Note the access hatch at the top of the bustle. The gun
mount setup featured a new heavy duty recoil guard that weighed 800 pounds. Firing
tests were suspended in early February when it was found that recoil piston
rods were too weak. Improved piston rods were installed on the next M4A1(76M1)
(USA 3016065) received at Ft. Knox, and firing tests commenced on March 1,
1943. Gun travel locks were installed on both the front and rear of the
M4A1(76M1)s, and we would note that the securing arm of the front travel lock
was a single, wrap around piece, as opposed to the standard, but less stable
two piece units that entered Sherman production in the Fall of 1943. Pressed
Steel Car began the transition to the standard cast hull lifting rings in
December, 1942, but note that 3015954 can be seen with padded hull lifting
rings (asterisked) on both the front and rear. A Ft. Knox Receiving Report
lists not only the Serial and Registration Number, but "C723" as
well. We take this to mean that Serial Number 10953, USA 3015954 was the 723rd
cast hull (M4A1) produced by PSC. We believe this number is what is seen stamped
on the hull side in the rear of surviving PSC M4A1s.
The third M4A1(76M1) was
photographed at APG on April 1, 1943. This tank was Serial Number 13669, USA
3016670, US turret # 3 accepted in March, 1943. A few items of interest from a
production standpoint can be noted. The track skids (1) are in the
"final" or standard configuration. The use of heavy steel tracks
created a friction problem with the track skids. This was remedied by the
addition of a spacer (2 and inset) that elevated the return roller by about an
inch. A
modification kit was provided in mid 1943, so that the spacer could be
retrofitted to any Sherman built without it. Five of the six bogie arms seen
here are the "final" type (3), introduced at PSC starting around
January, 1943. In order to prevent the bogie arm rubbing plate bolts from
working loose, they were secured at the bottom with a nut. "Wrench
holes" (circled) provided access to the nuts. These bogies represent the
configuration used by PSC until early 1944, when the straight return roller
arms were replaced with upturned arms that eliminated the need for the spacer. The
positive hatch locks (4) are present on the commander's hatch, but not the
driver's hatches. However, the fitting for the equilibrator spring (5) can be
seen by the bow gunner's hatch. A couple of items we would not expect to see on
a March, 1943 PSC Sherman include the M3 type drive sprocket (6), and the
"padded" hull lifting ring (7) in the rear. The "padded"
lifting ring castings are oddities noted in only a few period photos of PSC
M4A1s made in late 1942, early 1943. Most of their Shermans appear to have
started out with the "bent rod" lifting rings, with a transition made
to the standard castings around December, 1942. We are not aware of any
surviving PSC M4s or M4A1s with the "padded" hull lifting rings.
This M4A1(76M1) was Serial
Number 13679, USA 3016680, US turret # 4 produced in March, 1943, a few units
after SN 13669 of the previous caption. This tank was the subject of a test in
the Spring of 1943 by the 40th Armored Regiment, 7th Armored Division stationed
at the Desert Training Center in California. There was some indecision, or
perhaps dissension, about the caliber of the Antiaircraft Machine Gun to be
carried by the Sherman. The 3rd Armored Division arrived in the UK in the Fall
of 1943. When they drew their Shermans, it was reported that half were equipped
with .30 caliber and half with .50 caliber AA MGs. "In many instances,
tanks that are equipped with the .30 caliber...had spare parts and accessories
for the .50 caliber." On April 1, 1943 the Ordnance Department settled the
issue by directing that only the .50 caliber was authorized for the Medium
Tank. The M4A1(76M1) program perhaps reflected the indecision, as they were to
be equipped with .30 caliber AA MGs. A purpose made travelling clamp was
provided, as shown above. The Reports from APG and the DTC concerning the
M4A1(76M1) were not negative, although suggestions were made for improvements. However,
on April 5, 1943, an Armored Force Board Report concluded that the turret was
unsatisfactory, too small "to develop the full potential capabilities of
the 76-mm gun." A month later, the Ordnance Committee terminated the
program. Only 12 units had been produced, and 9 were converted back to
M4A1(75)s. It should be noted that a few Shermans with "small"
turrets were upgunned with 76mms in the ETO during WW II. In the early 1950s,
over 700 such tanks were upgunned, and provided to Allies as Military
Assistance.
This rear view of SN 13679
shows the "Original Design" exhaust deflector (1) reported to have
been introduced at PSC on March 10, 1943 at Serial Number 13610. The deflector
was notched to accommodate the exhaust pipe (2) for the auxiliary generator.
The later Barber-Colman type deflector is said to have replaced this on
December 1, 1943, PSC's last month of M4A1(75) production. The "long"
trailer towing pintle (3 and inset) was reported introduced on April 29, 1943
at Serial Number 28205, so its appearance on SN 13679 seems a little early. We
suspect that, like the .30 caliber AA MG, the pintle was intended to be
standard equipment on the M4A1(76M1) series. In some instances, the long pintle
got bent up in service, which created an interference issue with the engine
access doors. A shorter pintle was designed, and became available by the end of
1943. It was used on "Second Generation" and remanufactured Shermans.
Note the rivets on the lower rear hull plate, including those used to secure
the idler wheel assemblies. The rear gun travel lock (4) of the M4A1(76M1) was
a 2 piece affair. When PSC finally got around to installing tail light guards
(5) on its M4A1s, circa October 1942, they were in the configuration shown
above. We've used an arrow to point out the groove in the center of the hull
casting. This is typical of upper hulls cast by General Steel.
The tail light guards used by
Pressed Steel, Lima Locomotive, and PCF are shown above. Each shape is unique,
and can help identify the maker of an M4A1 when seen in period photos.
Surviving M4A1s must be viewed with some skepticism, since the original guards
might have been damaged, and replaced with something non standard during
remanufacture or restoration.
In late 1942, the General
Steel Casting Company's Commonwealth Plant in Granite City, Illinois began
production of M4A1 upper hulls. Except for the T6 (Sherman) pilot, we don't
find any evidence that GS produced any hull castings with direct vision. By early
1943, GS provided approximately half of the upper hulls used by Pressed Steel
Car. Continental Foundry & Machine provided the balance of PSC's castings,
as well as nearly all of those required by the other M4A1 manufacturers - Lima
Locomotive and Pacific Car & Foundry. Starting in early 1943, General Steel
began to cast their logo (1) on the front of the hulls they produced. If it can
be seen in a period photo, the "G in a shield" logo can be considered
a recognition feature of an M4A1 made by Pressed Steel, or one of the 188
Grizzlies made by Montreal Locomotive. Above shows machining operations on a
General Steel hull. The groove at the rear (2) was not a feature of Continental
castings.
In the Spring of 1943, the
Armored Board at Ft. Knox directed Pressed Steel Car to provide 4 M4A1(75)s
(later reduced to 3) for inspection and test. Each would be installed with
progressively more modifications from the so called "Blitz List." PSC
shipped "1st Blitz" on May 17. With the exception of Blitz Item 35a,
"Eliminate Pistol Ports," most of the modifications on this unit had
already been incorporated into Sherman production. "2nd Blitz" was
accepted in May, 1943, and was shipped out on June 19, 1943. It is somewhat
more interesting as it included several new mods. Blitz Item 16a,
"Improved Suspension, Horizontal Volute Springs" was installed on
"3rd Blitz" as well. This version of HVSS had been in development for
about a year. The ride was a little smoother over rough terrain, but the track
width remained the same as VVSS at 16 and 9/16 inches, so this HVSS did nothing
to reduce the Sherman's ground pressure. This project was terminated in favor
of the improved HVSS with 23 inch tracks being developed by Chrysler. The
"no pistol port" Union Steel turret can be seen to be Serial Number
3432, mold(?) 7. On April 14, 1943, the turret drawing was revised to eliminate
the pistol port, as well as "increase thickness of armor in region of
traversing mechanism." We don't have a right side photo to confirm, but
suspect that turret 3432 was one of the first of the new castings that included
the so called "thickened cheek" on the right front.
This overhead view of "2nd Blitz" shows a few more new items. The
commander's hatch (1) is a revised design which featured integral springs on
the hinges. The final version of this hatch was released as a "Critical
Modification" on July 24, 1943, with "No tanks without this item to
be accepted after 11/8/43." Perhaps the most important safety item was
Blitz #46, "Hatch Over Loader.” "2nd Blitz" shows a prototype
version of the loader's hatch (2) with a different "hold open"
configuration. The final revision with head padding was released as a Critical
Modification on September 29, 1943, and PSC is reported to have introduced it
in October at SN 37300. Chrysler and Fisher Body, the other builders that
remained in the Sherman program after January, 1944, are said to have
introduced the loader's hatch in December, 1943. Plans for a field modification
kit were abandoned, as it was thought that a retrofit was too complicated. "2nd
Blitz" can also be seen with a preproduction version of the
"Commander's Vane Sight," Blitz Item 43. This was said to have been
introduced at PSC at about the same time as the loader's hatch. The machine gun
pintles on the turret roof may have been added by the Armored Board. In the
Fall of 1943, "2nd Blitz" was used as a test bed for a wooden mock up
of the commander's vision cupola (inset).
Pressed Steel Car shipped
"3rd Blitz" on August 23, 1943. This tank was listed as SN 29203/USA
3037734, PSC #3300, and would have been accepted in August. The "PSC
Number" may have been the Manufacturer's Serial Number. The MFR's SN is
stamped on the dataplates of some US built WW II AFVs, but we have never seen
it on a Sherman plate. In any case, if we've done the math correctly, this tank
would have been the 3300th overall Sherman, both M4 and M4A1, accepted at PSC. "3rd
Blitz" is dramatically different from "2nd Blitz." The hull
casting was revised to incorporate larger drivers' hatches as recommended by
the Army Medical Research Lab. "3rd Blitz" was installed with the
"Quick Fix" modification, as evidenced by the 1 inch applique plates
in the areas of the sponson ammunition bins. "Counting heads"
suggests that the last 100 M4A1(75)s made by PSC in December, 1943 featured the
large hatch hull casting, Part Number E8550. The examples noted differ from
"3rd Blitz" in that the hull castings were thickened in the area of
the sponson ammunition bins, eliminating the need for the welded on applique
plates.
This overhead view highlights
another dramatic change. Some Ordnance Department engineers found the original
D50878 turret to be too small, and recommended a larger turret. The casting
seen here was "borrowed" from the T20 series Medium Tank program, and
is listed as Part Number E6275. Ironically, the Armored Board concluded,
"The T23 type turret is not satisfactory for use as a 75-mm gun
turret...because the additional turret space is not essential and the increased
weight is not desirable." The Ordnance Committee action that terminated
the M4A1(76M1) program, authorized development of a larger turret for the 76mm
gun. Another E6275 turret was used for the pilot installation, and, with some
changes, this basic shape was adopted for use on Second Generation Shermans
armed with the 76mm gun. 1944 and later production 75 and 105mm Shermans used a
modified version of the original small turret that reinstated the pistol port
and added a loader's hatch. The only Sherman that mounted the 75mm in a larger
turret was the M4A3E2 (Jumbo). "3rd Blitz" can be seen with periscope
guards, which entered the Sherman production pipeline starting in September,
1943. The armored housing (1) around the gunner's periscope became a standard
fixture on Second Generation Shermans, as did the Blanket Roll Rack (2). The
rather large gun travel lock seen on "3rd Blitz" appears to be the
same as used on the M4A1(76M1)s. A "2 fingers" travel lock (Assembly
Number B301301) became standard on 75mm Shermans starting in the Fall of 1943.
It was about 4 inches shorter than the fixture used on Second Generation 76 and
105mm Shermans.
The factory installation of
the Quick Fix modification at PSC is reported to have occurred in August, 1943
at SN 29317. This seems to be pretty close to what we have found counting
heads. Many M4A1(75)s can be seen with the flat, rolled armor applique plates
made for welded hull Shermans. These were cut into sections or otherwise
adapted to fit the contours of the cast hull. Although undocumented so far, it
is obvious from period photos and surviving examples that PSC procured castings
made to fit the contours of its M4A1s. Our observations suggest that, until mid
October, most of the M4A1s that PSC produced with the Quick Fix modification
factory installed, used these castings. Above shows the castings on an M4A1 on
display in Springville, Alabama. Note the multiple contours of the front
"plate." We do not know the Serial Number of this tank, but recorded
the number "2687" stamped on the right rear side. We take this to be
a loose build sequence number (plus or minus 30). The 2687th PSC M4A1 would
have been accepted in September, 1943. Like Serial Number 415 in Nattick shown
previously, this tank was remanufactured in 1945, and converted to M42B1
Flamethrower shortly thereafter. The fenders have been extended out to
accommodate the E9 modification. The rather complex fender braces were
adjustable to fit the contours of the tank as demonstrated here. These braces
are seen on both M4s and M4A1s remanufactured by Chrysler-Evansville and
International Harvester. When Pressed Steel Car began producing the
M4A1(76)HVSS in January, 1945, the same type of adjustable fender braces were
used.
Quite a few of the PSC M4A1s
with cast applique appear in photos in the Pacific Theater of Operations. Above
shows "Margaret Anne" of D Company, 754th Tank Battalion. This tank
is listed as USA 3069681, indicating September, 1943 acceptance. In April, 1945
"Margaret Anne" was pulled out of the line near Manila, and used to
test the merits of an in tank air purification system that had been shipped
from the US. Trials of the system in a number of Shermans from 3 Tank
Battalions, and including combat use, found that the Protector, Facepiece,
E21R2 (inset) was much superior to the use of individual gas masks. On June 20,
1945, the Pacific Warfare Board recommended that the E21R2 system "be
standardized as the method for protecting tank crews against chemical warfare
agents." The standardization and installation of this system in medium
tanks appears to have been abandoned with the Japanese surrender. PSC began
installation of the gun travel lock in August at about the same time as the
Quick Fix modification. On "Margaret Anne" it can be seen that the
siren and brush guard were moved over to the left to avoid any interference
issues with the travel lock. This tank features the "turret patch"
and it is assumed that the pistol port would have been welded up. These appear
to have been used alongside the no pistol port turrets that PSC introduced in
June, 1943 until an improved turret entered the production pipeline in October.
Here we see a PSC M4A1 with
the cast applique and a no pistol port turret in the European Theater. USA
3038028 would have been one of the last tanks accepted at Pressed Steel in
August, 1943. This tank carries tactical markings of the 771st Tank Battalion,
and was photographed in Baal, Germany on February 24, 1945. Note the M4A3(76)
just in front. Had they been available in sufficient quantities, the US Army
would have replaced 75mm Shermans with this model powered by the superior 500
HP Ford V8 engine. The shipping destination code on 3038028 begins with
"HAIL," indicating Antwerp. The port, which has an immense shipping
capacity, was vital to the Allied drive into Germany. It was captured intact on
September 4, 1944, but due to an overly casual attitude on the part of the
Allied High Command, its approaches were not immediately cleared of the enemy. As
a consequence, it was not opened to shipping until the end of November. The
771st probably received this tank as a replacement in early 1945. When built,
USA 3038028 would not have been installed with the machine gun stowage on the
turret bustle or the blanket roll rack. These items were part of a combined
Modification Work Order released in July, 1944. The presence of these mods,
along with the concave replacement road wheels, suggests that this tank may
have been remanufactured at the outset of the program in August, 1944.
Above shows an M4A1 of the
767th Tank Battalion, photographed on October 24, 1944 during the Leyte
Campaign. The Technical Manuals have it that a total of 26 grousers were stored
in the sponson compartments beneath the air scoops. "Man O' War"
appears to have nearly 40 installed on the left side alone. An improved
transmission with double anchor brakes, and featuring the sharp nosed, E8543
differential housing was mandated to be installed on all US built Shermans
starting in September, 1943. With this change, PSC reintroduced the front cable
clamp (circled) originally seen on a few of its earliest M4A1s. There is no
Registration Number visible to "date" this tank, but if we assume
that the 2 inch smoke mortar was factory installed, we would guess early
October, 1943 acceptance. The turret serial number can be seen as 4318, mold(?)
13, the highest SN we have recorded from a no pistol port Union Steel turret. Counting
heads suggests that at around turret 4400 the castings were revised to include
a loader's hatch and pistol port.
This
"after the battle" photo is part of a series showing US tank losses on
Okinawa. Note how a section of armor has been cut out and salvaged from
the differential housing on the M4 Composite in the background. We
believe that the M4A1 in the foreground may have been the last Pressed
Steel Car Sherman battle casualty of WW II. In mid-May 1945, the records
of the 706th Tank Battalion report the loss of 3 Medium Tanks which are
specifically listed as M4A1s: 3069617 (PSC Sept. 1943 production),
3069808 and 3069829 (both PSC Oct. 1943 production). We suspect that all
of these would have had the welded on, cast applique, as seen on the no
pistol port turret M4A1 in the foreground. The inset shows that the
M4A1 was named "Dude Sr." and the last 3 digits of the Registration
Number can be seen as "617" which we take to mean that this example was
USA 3069617. According to an official report, 3069617 was KO'd on 14 May
1945, which was D Company's worst day for "Vehicular Casualties" as
they reported the loss of 4 Medium Tanks "destroyed by fire." The
706th's After Action Report states that D Company was in support of the
306th Infantry Regiment of the 77th Infantry Division during its
unsuccessful assault on Flattop Hill. The AAR reports that "four tanks
were disabled during the operation" on the 14th, while the "Vehicular
Casualties" report states that they were destroyed. We would mention
that D Company was ordinarily the light tank company of a US tank
battalion, but the "Vehicular Loading" table" for the 706th TB has it
that the unit came ashore with 60 "Med Tks" and 6 "105mm AG" [Assault
Guns] and no Light Tanks. Note that "Dude Sr." has features nearly
identical to "Man O' War" of the previous caption, even including the
2-inch smoke mortar fittings. However, just the stub of the original
blade sight remains on "Dude Sr." The M4
Composite, possibly named "Butt Buster", is thought to have been lost
by B/706th a few days before. These Shermans were likely KO'd on the
trail and pushed out of the away not long after.
Around mid-October 1943, Pressed Steel Car introduced a revised small
hatch upper hull that featured thickened sides in the areas of the
sponson mounted ammunition bins. The new casting eliminated the need for
welding on the external applique. The M4A1 on display at Ft Jackson, in
South Carolina was converted to E13-13 Mechanized Flamethrower in early
1944. We suspect that this was one of the first PSC M4A1s to
incorporate the revised hull. We've asterisked the cast in "bumps" on
the right side. Unfortunately, the Test Report on the E13-13 does not
list the Serial and/or Registration Number of this unit. The build
sequence number 3175 is stamped on the left rear of the hull, which we
take to mean that it was the 3175th (give or take) M4A1 produced by PSC.
We would note that a surviving October 1943 production PSC M4A1, build
sequence number 3153, "still" has the cast applique welded on. Another
change which appears to have been introduced at PSC in October is the
relocation and new configuration of the siren brush guard (circled).
Photo courtesy of Paul and Lorén Hannah.
Another change that was
introduced in late October, 1943 is the revised D50878 turret casting that
"brought back" the pistol port, and incorporated the loader's hatch. The
manufacturers that continued to produce Shermans in 1944 and 1945 were Pressed
Steel, Chrysler and Fisher Body. Each was given a "Freeze Date" for
the loader's hatch. PSC's was November 1, 1943, but "counting heads"
suggests that they began the transition in October. Since the E13-13 was a
conversion, we can't say with certainty that the General Steel (not Union
Steel) D50878 turret, serial number 5573, is original to this tank. The turret
can be seen with a few flamethrower fittings, and we would guess the
commander's vision cupola and machine gun stowage modifications were added
during the E13-13 conversion. We don't find any evidence that PSC factory
installed these mods to any of its M4A1(75)s. The E13-13 does not appear to
have been remanufactured before conversion. Note that it still has the original
type exhaust deflector (1) as well as the problematic "long" trailer
towing pintel (2). The double rear tow lugs (3) are first seen on Third Blitz. These
served to accommodate the quick release towing shackle with handle, and appear
to have been introduced at PSC in late September.
While examining the M4A1 at
Ft. Jackson, we noticed that the hull casting features ramp-like raised areas
by each of the drivers' hatches. This bit of Sherman minutia has since been
seen on a few other surviving M4A1s, such as SN 37260, a PSC October, 1943
production M4A1 on display in Sinsheim, Germany (right). Counting heads suggest
that the "ramps" first appear around August, 1943, and are limited to
hulls cast by Continental Foundry & Machine. Perhaps they were added to the
castings to provide a better platform for the catch of the positive hatch lock
mechanism?
The Ordnance Department
continued to cast about, without much success, for anti-mine solutions. Above
shows the T9E1 Mine Exploder at APG in April, 1944. Like most of the
"Pressure Type" Mine Exploder experiments, the T9E1 was found
"impractical for use under combat conditions." The device was tested
with Serial Number 37421, USA 3070018, which would have been one of the last
M4A1s accepted at PSC in October, 1943. This tank can be seen with the revised
hull with cast in "bumps," and the new low bustle turret casting with
pistol port and loader's hatch (arrow). Counting heads suggests that from this
point to the end of 75mm production at PSC (Serial Number 37899, USA 3070496),
all of the M4A1 had turrets that incorporated the loader's hatch.
It was the practice of the
Ordnance Department to conserve certain pilots at APG for future reference. USA
3070018 was photographed in February, 1947. We assume the T9E1 roller would
have been been retained as well, although it does not appear in the photo. The massive roller weighed as much as the tank, and the bumper (arrow) at the rear was installed so that a second tank could help push it. 3070018 can be seen with
the new siren brush guard. The "2 fingers" or "scissors
jaw" configuration of the gun travel lock shows to good effect. It is
thought that this type may have been designed since, in theory at least, the
gun could be released from its travelling position from inside the tank by
means of a wire. Tests at APG in September, 1944 found it to be unstable and
inadequate for either the 75mm or 76mm gun, and suggested a new design with a
wrap around clamp, similar to what had been used on the M4A1(76M1). Many
surviving Shermans are seen with the improved locking clamp (inset), but we
don't find any evidence that this was factory installed on any Shermans before
production ended in the Summer of 1945. Unlike Chrysler and Fisher Body, PSC
continued to install the step bracket after the gun travel lock was introduced.
This small item was eliminated on the M4A1(76) and other Second Generation
Shemans. On the subject of steps, the E8543 differential housing seen here is
the early type with the cast in steps. These interfered with the operation of
the quick release towing shackles. Consequently, the differential castings were
altered to eliminate the cast steps, and the standard E8543 differential was
installed with welded on metal strip steps instead.
The Ordnance Department's
constant demand for modifications was a sore point for some of the
manufacturers. Henry Ford, the "father" of mass production, was
somewhat vocal about this, since the Government was asking for greater and
faster production, while introducing numerous changes that required the design
and procurement of new parts, and only slowed down the process. Pressed Steel
Car's management appears to have been more willing to go the extra mile, and
provide the Government with whatever it wanted as quickly as possible. Consequently,
the many changes introduced in quick succession by PSC, make them the most
interesting of the manufacturers of the Sherman. Above shows the first two T1E3
Mine Exploders during a demonstration in the UK in May, 1944. "Aunt Jemima
2" can be seen as USA 3070232 indicating November, 1943 acceptance. When
the cast and welded hulls were redesigned to incorporate larger hatches, it was
noted that the bustle of the original 75mm turret could be fouled on the
protrusions of the large hatch hull. Consequently, the turret casting was
revised yet again. The turret bustle was raised a few inches in order to permit
the turret to rotate freely. "High bustle" and "low bustle"
are informal terms used to distinguish the difference in the castings. In the
photo, it can be seen that both "Aunt Jemimas" have small hatch upper
hulls with the cast in "bumps." However, both have high bustle
turrets, introduced by PSC in November, 1943 in anticipation of the large hatch
E8550 hulls that would come on line the following month.
This overhead view of USA 3070232 was taken at APG in March 1944 before
the tank was shipped to Great Britain. It can be seen that the part
number of the turret (circled) is "still" D50878. The turret serial
number appears to be 4595, the next to the highest Union Steel 75mm
turret SN we have recorded. It is thought that about the last 200 Union
Steel 75mm turret castings were in this high bustle format, and that
they were the only such turrets that retained the D50878 part number. At
present, all other high bustle, loader's hatch turrets we have
encountered are seen with a new part number - D78461. In fact, an item
in the Ordnance files lists "Turret D78461, to provide clearance for
doors, released 9/28/43." Note that the gunner's periscope was not
provided with a wire guard. An armored housing, similar to what can be
seen on Third Blitz, was introduced on Second Generation series
Shermans. The Whiting Corporation produced 200 T1E3 assemblies from
March through December 1944. About 72 were shipped to Europe.
Ultimately, it was concluded that the T1E3 "failed to meet the
requirements" for "locating and breaching minefields, and expeditiously
clearing and/or detecting scattered mines on roads and trails."
The final major change before
the end of M4A1(75) production at PSC was the introduction of the large hatch
hull casting. Since PSC was the only remaining manufacturer producing the M4A1,
the change only applied to them. The "Freeze Date" was given as November
30, 1943, which would indicate that the 175 units accepted in December would
have used the large hatch E8550 hull castings. However, "counting
heads" suggests that PSC was not able to meet the freeze date, and that
only about 100 such units were produced. At present, the large hatch hulls
recorded fall within the range from Serial Number 37800, USA 3070397 through to
the last PSC M4A1(75) Serial Number 37899, USA 3070496. Above shows an example
that was recovered in 1984 from the sea bed in what had been the US Amphibious
Assault Training Area in Devon in the UK. This tank had been converted to a
Duplex Drive "swimming tank", and was engaged in a training
exercise with Company A, 70th Tank Battalion when it sank 3/4 of a mile
offshore. An article in "After the Battle #45," describes the
efforts of a group of local citizens headed by hotelier Ken Small to recover
the tank, which Mr. Small had purchased 10 years earlier from the US Government
for $50. A couple of sentences in the article are of particular
interest..."A special search was made beneath the silt for the works
number plate...and fortunately although badly corroded the plate was still in
place. After cleaning the plate was still legible: 87830." We have not be
able to contact the late Mr. Small's son, but it seems highly likely that the
Serial Number from the dataplate would be 37830.
In December 1943, the Army
contracted with the Firestone Tire & Rubber Company for the production of
350 Duplex Drive assemblies to be applied to new M4A1(75)s. Because they were
recently built, unallocated and available, the majority of the DD swimming tank
conversions used Pressed Steel Car M4A1(75)s that had been produced in the last
few months of 1943. We suspect that about 90 of the large hatch M4A1(75)s were
converted to DDs, while another 10 were used in Engine Endurance and other
tests at the various Proving Grounds. The DD project was highly classified, and
therefore much of the documentation was not preserved. However, we did come
across the shipping report reproduced above. The prototype is listed towards
the bottom of the page as USA 3070327. It was ordered from Lima Tank Depot on
December 16, 1943, and shipped to Firestone for DD conversion 2 days later. The
prototype used DD parts that the British had provided, and due to some
US/British thread incompatibility issues, developed problems and sank in
shallow water during testing at Ft. Story, Virginia. The Registration Numbers
of the first 23 M4A1s shipped from LTD to Firestone for DD conversion are
listed. Note that all but the prototype have RNs in the 30704XX (December large
hatch production) range. This appears to have been a case of "last in,
first out." There is at least one typo in the document - 3080448 was most
likely 3070448, one of the two pilots shipped to Ft. Story for trials. Along
with 3070441, this was later placed in secure storage at the Lima Tank Depot
"for possible future development or production work." If we assume
that Mr. Small's DD is actually Serial Number 37830, its corresponding
Registration Number, USA 3070427, is listed in the document.
Mr. Small's DD now stands as a
memorial in Torcross to the servicemen who were lost during Exercise Tiger, an
amphibious training operation conducted off the coast of Devonshire. On the
morning of April 28, 1944, negligence on the part of the naval screening force
left a convoy of LSTs open to attack by German E-Boats. Two LSTs were sunk and
another badly damaged. Nearly 700 US soldiers and sailors lost their lives in
this tragedy.
The photos above highlight
some of the features of the large hatch M4A1(75). It is thought that all of the
US DD conversions would have had late E8543 differential housings. Both the
early version with cast in steps, as well as the later with welded on steps
have been seen. Note the fittings for the Barber-Colman type exhaust deflector
(circled). This was reported to have been factory installed by PSC starting
December 1, 1943, and, if accurate, would have applied to the last 175 M4A1s
accepted, including all of the large hatch units. The example on the right is
said to have been a DD of the 741st Tank Battalion. The disastrous decision to
launch the Battalion's 32 DDs in extremely rough seas nearly 3 miles off Omaha
Beach resulted in the loss of 27 by sinking. Miraculously, 2 of the 741st's DDs
managed to swim in, and 3 were deposited on shore by their LCT when their
canvas screens were torn by shrapnel prior to the decision to launch. This
Sherman, along with a small hatch DD, and the turret from another were recovered
by M. Claude Lemonchois, and are on display at the D-Day Wrecks Museum in
Port-en-Bessin, France. Left side photo courtesy of Alf Adams.
The casting information on the
high bustle turret of the Torcross DD is of interest because it is a General
Steel, not Union Steel turret. The turret Serial Number is 5939 and it has the
later D78461 part number. We can document one other General Steel D78461 turret
installed on a DD, but can't publicize it at present, except to note that the
serial number is about 100 units lower than the one on the Torcross. From this
we can merely conclude that General Steel provided some of the high bustle
turrets used by Pressed Steel in the last months of production. The majority of
the General Steel D78461 turrets were used on the Second Generation M4A3(75)Wet
Shermans made by Fisher Body. Turret Serial Numbers recorded on those run from
6020 through 7679. As a point of Sherman minutia,
we would note that the secondary antenna brackets on the turrets used by Fisher
are seen fabricated from several pieces, as shown in the inset on the right,
whereas the ones on the two General Steel DD turrets appear to be one piece
forgings.
It is thought that the 3 DD
turrets at Port-en-Bessin were cast by Pressed Steel's primary supplier, Union
Steel. The single low bustle turret is Serial Number 4452. Other Union Steel
low bustle, loader's hatch turrets that have been recorded are 4444 and 4471.
The D50878 casting marks on both low and high bustle Union Steel turrets are
seen on the left front (inset), and the Serial Number is repeated on the
turret's left side. We don't find evidence that a padlock fitting (inset) was
factory installed by PSC with the introduction of the loader's hatch. It may
have been installed on some of the late production M4A3(75)Wets, or retrofitted
later in the post war years. Curiously, this turret has the fitting for the sun
compass (circled in red) installed by the British, or added by US Tank Depots
on Commonwealth Lend Lease Shermans. We can only note that the compass fitting
is seen on some but not all of the US converted DDs.
It
was not possible to record the Serial Numbers of the 2 high bustle
D50878 turrets at Port-en-Bessin due to their condition. Examples that
have been noted are Serial Numbers 4548 (inset), 4564 and 4595. Above
shows a rear view of the large hatch DD. The overhead photo of the
November 1943 production "Aunt Jemima 2," USA 3070232 featured earlier
shows the recessed lifting handles on the rear engine deck plate in the
"usual" side by side orientation. Here we see that that the handles have
been reoriented front to back. This is also the case on the Museum's
small hatch DD. From this we might infer that PSC instituted this small
change in either November or December 1943. It was standard throughout
production of the M4A1(76). M. Lemonchois recovered a number of US AFVs
from the sea off Omaha Beach, including the M7 Priest seen in the
background. While he was not able to find the Ordnance Serial Numbers of
the DDs, he reported the M7's was 2537, and that the vehicle was lost
by the 58th Armored Field Artillery Battalion.
Update:
At some point in the last few years, a large section of marine growth
(inset) was removed or fell away from the turret of the large hatch DD
at Port-en-Bessin. This enables us to see that the turret serial number
is either 4732 or 4762. Either way, this would now be the highest Union
Steel 75mm turret serial number we have recorded. This "revelation"
changes the counting heads equation somewhat, since it suggests that
Union Steel may have produced over 200 high bustle, 75mm turrets. In
addition, it is reported that the US Government bought the museum's
small hatch DD and intends to display it at the National Museum of the
United States Army at Ft. Belvoir, Virginia. If that is accurate, we
hope we might be able to obtain the turret's serial number in the
future.
Nearly 300 DDs embarked from
the UK. Those that survived D-Day were converted to regular gun tanks when time
and circumstance permitted. Above shows a large hatch model photographed in July,
1944 by the 3rd Armored Division to show the "T2 Rhinoceros" device
developed as a mean to breech the hedgerows of Normandy. Hundreds of tanks were
installed with various types of these cutters before the start of Operation
Cobra in late July. Here one can see that the USA Registration Number was
painted on the turrets of DDs, since the skirting would have obscured it in the
usual position on the hull sides. This December production M4A1 can be seen to
be USA 3070459. The DD's headlamps (1) and guards were extended up in order for
the light beams to clear the screen when it was in the lowered position. A
section of the ventilator was removed (2) to accommodate part of the DD's
hydraulics. The differential housing of 3070459 does not show the telltale weld
scars of the "prow" of the DD conversion. We suspect that the
original differential was damaged, and that this tank was turned in for high
echelon repair by one of the three US Tank Battalions that employed Duplex
Drive Shermans on D-Day. It seems likely that the 3rd Armored Division drew it
from the 1st Army replacement pool.
This screen capture from a
Signal Corps movie shows another large hatch former DD of the 3rd Armored
Division in Cologne, Germany in March, 1945. The fitting (circled) for the
reinforcing strut on the high bustle turret provides the DD clue. The
Registration Number can be seen as USA 3070398. The corresponding Serial Number
of this tank would have been 37801. At present this is the first large hatch
M4A1(75) we can document. We would note that SN 37798, USA 3070395 and SN
37799, USA 3070396 were small hatch models, designated "M4A1E3," and
used in automatic torque converter tests at Aberdeen Proving Ground.
The British received 80 of the
US converted M4A1 DDs, all of which were allocated to the 8th Armoured Brigade
for the Invasion. Photos indicate that some of them were the large hatch
models. Above shows an example in action with the Sherwood Rangers, the junior
Regiment of the 8th AB. The unit was photographed on August 4, 1944 advancing
towards Ondefontaine, France on a farm lane in the hedgerow country typical of
Normandy. The "SCR 528" stenciled on the turret stands for
"Signal Corps Radio Model 528," the standard tank radio used by the
US at the time. For some reason, the British did not overpaint this along with
the USA Registration Number when they applied the circle tactical marking
indicative of C Squadron. Perhaps they used the SCR 528 in lieu of the British
#19 on the DDs received from the US? Because the M4A1 DDs transferred to the
British in the UK were not originally intended for Lend Lease, they did not
have British WD Numbers assigned beforehand. A May 24, 1944 Roster of the
Nottinghamshire Sherwood Rangers Yeomanry lists the USA Numbers of some of
their DDs, and several are in the large hatch range, such as USA 3070473,
3070488 and 3070492. Photo courtesy of the Imperial War Museum, IWM B8588.
It was the policy of the Army
to employ used tanks for conversion projects. In the Summer of 1943, Pressed
Steel Car was contracted to convert 936 M4s, M4A1s and M4A3s to M32 series tank
retrievers. Production commenced in December, 1943, but there had been some
difficulty in rounding up used Shermans. In order to get the program underway,
an exception was made, and it was agreed that 91 new M4A1s would be pulled from
the line at PSC. The new Shermans required only conversion, not remanufacture,
which was a much more extensive process involving the replacement of engines
and other internal systems with new or rebuilt components. The 91 new
conversions were done from December, 1943 through March, 1944, and were
assigned Serial Numbers 6 through 96, and USA Numbers 40149307 through
40149397. As some of the earliest M32 series conversions, a number of these
were shipped to Europe in time to take part in the D-Day Invasion and
subsequent build up in Normandy. Above shows front and rear views of Serial
Number 59, USA 40149360, completed in January, 1944, and photographed at APG in
February. The new M4A1s provided for conversion would have been from PSC's last
few months of production, more or less the same M4A1s available for the DD
program. One can see that Serial Number 59 has the thickened sides in the areas
of the sponson mounted ammunition bins. This unit features the early E8543
differential housing with the cast in steps. As mention previously, the
Barber-Colman exhaust deflector was reported to have been introduced on PSC
M4A1s on December 1, 1943. If this unit was accepted before then, it is likely
that the new deflector would have been added during the M32B1 conversion.
It seems possible, but
improbable that one or two large hatch M4A1(75)s were pulled new from the
assembly line and converted to M32B1. If so, they would have featured the small
"chute" turret port as seen on Serial Number 59 from the previous
caption. The turret port (circled) above can be seen as a rather large
"door." Counting heads suggests that the door replaced the chute at
PSC around August 1944, months after the "new" M32B1 conversions had
been completed. Until recently, there was no evidence whatsoever of any large
hatch M32B1 conversions. The snapshot above shows an example in the markings of
the 20th Tank Battalion, 20th Armored Division. It is thought that this photo
was taken in the mountains of Austria sometime after V-E Day (May 8, 1945). A
bit of the Registration Number can be seen in another photo, and it begins with
USA 40155, indicating that it was converted by PSC from a used M4A1. We suspect
that this tank was one of the large hatch M4A1s that had been assigned to
Ordnance Department tests in early 1944, and afterwards, it was turned in for
remanufacture and conversion. One of the large hatch M4A1s used in Engine Tests
at Ft Knox is listed as USA 3070454. Federal Machine & Welder is reported
to have converted that same Registration Number to M32B1, so, it would seem,
there may have been at least two large hatch M4A1 retriever conversions. "GI
snapshot" from Leife Hulbert collection.
As mentioned previously, we have not found the
Ordnance Serial Number factory stamped anywhere on the exterior of
surviving Pressed Steel Car built Shermans. This has made studying them a
great challenge. The photo above shows the location
of what we believe is a loose build sequence number. We have seen this
stamped on one or the other side of a number of PSC Shermans. The
company's 381st M4A1 would have been accepted in September, 1942.
Update: In 2018, Pierre-Olivier got permission to have
a look inside, and found that the tank still had its original
dataplate. Although the plate is badly rusted, the serial number could
still be read as 644 (inset), which indicates that it was indeed
accepted in September, 1942. The Sherman Minutia team counts
it as a minor victory any time we can find a known good serial number
on a surviving PSC! This tank is on display in Calhoun, Georgia, and
like many of the surviving M4A1s, received numerous modifications when
it was rebuilt.
One of the Sherman Technical Manuals refers to a "Speed Caution Plate"
(left) affixed to the hull wall to the left of the driver's seat. We
prefer to use the informal term "dataplate." Not many surviving Shermans
still have them. Most that do, have replacement plates, added during
rebuild programs. Original Sherman dataplates include the name of the
company that manufactured the tank. Above right shows what we believe
may be the only extant Pressed Steel Car M4 dataplate. The Serial Number
was stamped in the box in the upper right-hand corner. The year of
acceptance was stamped inside the box in the lower left. In general, the
initials of an Army official were stamped inside the box in the lower
right, as certification that the vehicle had been built and tested to
the prescribed standards. Unfortunately, that area is painted over on
this plate. We are interested in cataloging surviving M4 Series dataplates. Should any readers be in the position to photograph a
more readable example of a PSC M4 or M4A1(75) dataplate, we would be
happy to have a report.
HOME